SCORE 61 Remove, replace, and install new steel roof joists Client: Masselink Paul R | Permit type: Building permit - commercial renovation (interior & exterior) | Permit status: Closed-expired | Expiration date: August 29, 2010 | Permit id: B09-01465 | |||||
Remove, replace, and install new steel roof joists Date: November 3, 2009 Value: $6,330 Permit status: Closed-expired | Completion date: July 27, 2015 | Permit id: B09-01465 | |||||
Install a 48 sq. Ft. Wall sign on the south face no higher than 16 ft. From the entrance platform per plans. Date: August 18, 2011 Permit status: Closed-finaled | Completion date: July 20, 2016 | Permit id: P-Sgn-2011-0605 | |||||
Flush mounted channel letters on the side of the building. Date: July 13, 2016 Value: $4,265 Permit status: Issued | Permit id: P-Sgn-2016-0555 | |||||
Demolition and addition of walls & doors & ceilings - minor remodeling of office interior. Date: June 3, 2011 Value: $10,000 Permit status: Closed-no response | Completion date: March 22, 2012 | Permit id: Bc-Int-2011-071 | |||||
Structural reinforcement for cooling tower implementation. Date: September 23, 2015 Value: $200,000 Permit status: Closed-finaled | Completion date: May 9, 2016 | Permit id: Bc-Int-2015-190 | |||||
Repair steel columns Date: May 26, 2011 Value: $500 Permit status: Closed-finaled | Completion date: July 8, 2011 | Permit id: Bc-Reno-2011-07 | |||||
Demo & renovate offices per plan and replace windows per print Date: June 24, 2014 Value: $187,000 Permit status: Waiting for temp u and o | Permit id: Bc-Reno-2014-09 | |||||
Conversion of existing storage space to new office space. Office area to include 2 new toilet shower rooms, caf, meet conf rooms, elevator and stair. New lighting and hvac throughout. Date: June 29, 2017 Value: $825,000 Permit status: Closed-use and occupancy | Completion date: October 20, 2017 | Permit id: Bc-Int-2017-131 |