Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: August 18, 2010 Contractor: William B. Crist Jr Permit type: Electrical permit | Permit status: Final | Completion date: December 8, 2010 | Expiration date: December 8, 2010 | Permit id: 2010-069717 Ep | |||||
Upgrade elec service residence Date: March 21, 1997 Value: $250 Permit type: Mechanical permit | Permit status: Final | Completion date: March 31, 1997 | Expiration date: August 29, 2007 | Permit id: 1997-003411 Mp | |||||
SCORE 59 Demolish a circa 1949 1 story 1152 square foot single family residence Date: August 2, 2010 Contractor: Curtis Griffin Applicant: Curtis Griffin | Applicant Phone: (512) 694-5204 | Permit type: Building permit | Permit status: Final | Completion date: August 17, 2010 | Expiration date: August 17, 2010 | Permit id: 2010-065976 Bp | |||||
SCORE 59 Demolish a circa 1949 1 story 3 square foot detached garage Date: August 2, 2010 Contractor: Curtis Griffin Permit type: Building permit | Permit status: Final | Completion date: August 10, 2010 | Expiration date: August 10, 2010 | Permit id: 2010-065977 Bp | |||||
SCORE 100 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Applicant Phone: (713) 260-4166 | Permit type: Building permit | Permit status: Final | Completion date: January 3, 2011 | Expiration date: January 3, 2011 | Permit id: 2010-069717 Bp | |||||
SCORE 100 1122 sidewalk fee paid in lieu of construction see attachednmtconstruct new driveway approach and sidewalk from curb to residence see attached plansnmtnew construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: November 16, 2010 Contractor: Mhi Plantation Homes Permit type: Driveway / sidewalks | Permit status: Final | Completion date: December 2, 2010 | Expiration date: December 2, 2010 | Permit id: 2010-069717 Ds | |||||
SCORE 100 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: August 23, 2010 Contractor: Raymond Willis Permit type: Mechanical permit | Permit status: Final | Completion date: December 9, 2010 | Expiration date: December 9, 2010 | Permit id: 2010-069717 Mp | |||||
SCORE 98 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: August 18, 2010 Contractor: George Christianson Permit type: Plumbing permit | Permit status: Final | Completion date: December 9, 2010 | Expiration date: December 9, 2010 | Permit id: 2010-069717 Pp | |||||
SCORE 100 Install irrigation system to res Date: December 6, 2010 Contractor: Mhi Plantation Homes Permit type: Plumbing permit | Permit status: Final | Completion date: December 10, 2010 | Expiration date: December 10, 2010 | Permit id: 2010-104102 Pp | |||||
SCORE 100 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: August 18, 2010 Contractor: William B. Crist Jr Permit type: Electrical permit | Permit status: Final | Completion date: December 8, 2010 | Expiration date: December 8, 2010 | Permit id: 2010-069717 Ep | |||||
SCORE 98 New construction 3 bed 4 bath sfres with attached two car garage private drive covered front porch and back patio Date: August 18, 2010 Contractor: George Christianson Permit type: Plumbing permit | Permit status: Final | Completion date: December 9, 2010 | Expiration date: December 9, 2010 | Permit id: 2010-069717 Pp |