Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: May 11, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 340325 | |||||
Mechanical permit Date: July 20, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 347295 | |||||
Demolition permit Date: February 22, 2011 Client: Mt Vernon Street Llc | Permit status: Expired | Permit id: 326029 | |||||
Alteration permit Date: March 21, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 330916 | |||||
Suppression permit Date: July 7, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 336734 | |||||
Electrical permit Date: August 3, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 346427 | |||||
Zoning/use permit Date: April 19, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 323519 | |||||
Permit for the demolition of ne story portion at rear, for the erection of a rear deck at the second story rear, erection of a rear deck at the third story rear, for the erection of a roof deck, for the creation of one open air parking space, all in an existing three story structure to be used as a three family dwelling. Date: February 17, 2011 Client: Mt Vernon Street Llc | Applicant: Joseph Beller, Esq. | Permit type: Appeal | Permit status: Granted | Completion date: March 11, 2011 | Permit id: 14518 | |||||
Electrical permit Date: August 3, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 346427 | |||||
Alteration permit Date: April 21, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 337072 | |||||
Plumbing permit Date: May 23, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 342579 | |||||
Zoning use permit Date: April 19, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 323519 | |||||
Mechanical permit Date: July 20, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 347295 | |||||
Demolition permit Date: February 22, 2011 Client: Mt Vernon Street Llc | Permit status: Expired | Permit id: 326029 | |||||
Suppression permit Date: July 7, 2011 Client: Mt Vernon Street Llc | Permit status: Completed | Permit id: 336734 | |||||
Permit for the demolition of ne story portion at rear, for the erection of a rear deck at the second story rear, erection of a rear deck at the third story rear, for the erection of a roof deck, for the creation of one open air parking space, all in an existing three story structure to be used as a three family dwelling. Date: February 17, 2011 Client: Mt Vernon Street Llc | Applicant: Joseph Beller, Esq. | Permit type: Appeal | Permit status: Granted | Completion date: March 11, 2011 | Permit id: 14518 | |||||
SCORE 100 Wire 3 apartments , install a new 200amp service with with 100amp as per 2008 nec and install fire alarm system as per nfpa-72 Date: August 3, 2011 Contractor: Kline David Client: Mt Vernon Street Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: September 6, 2011 | Permit id: 346427 | |||||
SCORE 100 Installing 1" water pipe from main to the meter,installing house trap fresh air inlet Date: May 23, 2011 Contractor: Ferko Plumbing Client: Mt Vernon Street Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 6, 2011 | Permit id: 342579 | |||||
SCORE 100 Install (2) fire places Date: June 30, 2011 Contractor: Ferko Plumbing Client: Mt Vernon Street Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 18, 2011 | Permit id: 350697 | |||||
SCORE 99 Complete renovation of 3 family. Level ii alteration iebc. Fully sprinklered building. Erection of new stairs,rooftop deck ans rear deck, new phc approved windows and doors, new finishes. Demo one story rear addition. Replace rear wall section as shown. Date: May 6, 2011 Contractor: Loonstyn Bros Construction Llc Client: Mt Vernon Street Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: December 22, 2011 | Permit id: 337950 | |||||
SCORE 99 Repair damaged brick wall in rear of building with salvaged bricks from the site. Historical commission to approve mortar provide adequate shoring prior to start of work Date: April 21, 2011 Contractor: Loonstyn Bros Construction Llc Client: Mt Vernon Street Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: August 18, 2011 | Permit id: 337072 | |||||
SCORE 100 Installation of fire suppression system for triplex per submitted plan. Date: July 7, 2011 Contractor: Elite Fire Protection Client: Mt Vernon Street Llc | Permit type: Suppression permit | Permit status: Completed | Completion date: August 18, 2011 | Permit id: 336734 | |||||
SCORE 99 Remove & replace (15) windows in exist openings. Date: March 21, 2011 Contractor: Loonstyn Bros Construction Llc Client: Mt Vernon Street Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: June 23, 2011 | Permit id: 330916 | |||||
SCORE 99 Demo all no bearing load bearing walls on inside of building. Date: February 22, 2011 Contractor: Loonstyn Bros Construction Llc Client: Mt Vernon Street Llc | Permit type: Demolition permit | Permit status: Expired | Completion date: May 29, 2011 | Permit id: 326029 | |||||
Installation of hvac, ductwork to include direct vent gas fired warm air furnace within each dwelling unit as per plan. Date: July 20, 2011 Client: Mt Vernon Street Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 18, 2011 | Permit id: 347295 | |||||
SCORE 99 Demolish one story structure- creation of one open air parking space- erection of roof decks on one story two story three story portion with a piot house(for third story roof deck) Date: April 19, 2011 Contractor: Loonstyn Bros Construction Llc Client: Mt Vernon Street Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 20, 2011 | Permit id: 323519 | |||||
SCORE 100 Installing 5 toilets 5 lavs,3 tubs,3 kitchen sinks,3 water heaters,3 laundry Date: May 11, 2011 Contractor: Ferko Plumbing Client: Mt Vernon Street Llc | Permit type: Plumbing permit | Permit status: Completed | Completion date: August 18, 2011 | Permit id: 340325 |