Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: December 20, 2012 Permit status: Completed | Permit id: 444472 | |||||
New construction permit Date: August 1, 2012 Permit status: Completed | Permit id: 418108 | |||||
Mechanical permit Date: January 9, 2013 Permit status: Completed | Permit id: 447187 | |||||
Zoning/use permit Date: July 19, 2012 Permit status: Completed | Permit id: 415798 | |||||
Zoning/use permit Date: April 26, 2013 Permit status: Completed | Permit id: 458409 | |||||
Suppression permit Date: October 25, 2012 Permit status: Completed | Permit id: 429112 | |||||
Alteration permit Date: June 24, 2013 Permit status: Completed | Permit id: 468505 | |||||
Use permit Date: March 18, 2014 Permit status: Completed | Permit id: 507561 | |||||
Plumbing permit Date: August 27, 2012 Permit status: Completed | Permit id: 424314 | |||||
Electrical permit Date: January 10, 2013 Permit status: Completed | Permit id: 439074 | |||||
Mechanical permit Date: January 9, 2013 Permit status: Completed | Permit id: 447187 | |||||
Zoning use permit Date: July 19, 2012 Permit status: Completed | Permit id: 415798 | |||||
Plumbing permit Date: August 27, 2012 Permit status: Completed | Permit id: 424314 | |||||
Zoning use permit Date: April 26, 2013 Permit status: Completed | Permit id: 458409 | |||||
New construction permit Date: August 1, 2012 Permit status: Completed | Permit id: 418108 | |||||
Alteration permit Date: June 24, 2013 Permit status: Completed | Permit id: 468505 | |||||
Electrical permit Date: January 10, 2013 Permit status: Completed | Permit id: 439074 | |||||
Mechanical permit Date: December 20, 2012 Permit status: Completed | Permit id: 444472 | |||||
Suppression permit Date: October 25, 2012 Permit status: Completed | Permit id: 429112 | |||||
Use permit Date: March 18, 2014 Permit status: Completed | Permit id: 507561 | |||||
SCORE 99 Permit to construct new footing and foundation only. Date: August 1, 2012 Contractor: Michael Murawski Permit type: New construction permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 418108 | |||||
SCORE 100 Install curbtrap,main drain,lateral & 3 4water svc & 2 sprinkler. Pa1#20122302168(commercial) Date: August 27, 2012 Contractor: Best Choice Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: June 23, 2015 | Permit id: 424314 | |||||
Erect a new 3 story commercial structure with cellar as per plans. Date: July 19, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 20, 2012 | Permit id: 415798 | |||||
SCORE 82 Installation of ductwork for vacant spaces on second and third floors. Date: January 9, 2013 Contractor: Desher Bruce J Permit type: Mechanical permit | Permit status: Completed | Completion date: June 3, 2014 | Permit id: 447187 | |||||
SCORE 82 Ductwork throughout single family home Date: December 20, 2012 Contractor: Desher Bruce J Permit type: Mechanical permit | Permit status: Completed | Completion date: June 3, 2014 | Permit id: 444472 | |||||
SCORE 100 Install 300amp service with subpanel in 2 apts installing wiring throughout building for lights, receptacles, fixtures, fire alarm per 2008 nec & nfpa 72 (mixed use) Date: January 10, 2013 Contractor: Gerald Kaewell Permit type: Electrical permit | Permit status: Completed | Completion date: April 20, 2013 | Permit id: 439074 | |||||
SCORE 100 Rerough 2-tub 3-sinks, 3-toilet 1-kitchen sink, 1-laundry tub (commercial) Date: September 13, 2012 Contractor: Best Choice Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: November 8, 2015 | Permit id: 427279 | |||||
Permit to construct three story structure with cellar as per plans approved under ap#428781. Date: October 5, 2012 Permit type: New construction permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 428782 | |||||
SCORE 100 Installation of nfpa 13r 13 sprinkler system Date: October 25, 2012 Contractor: Shannon Fire Protection Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 429112 | |||||
Addition of a 2 story commercial structure with mezzanine and cellar. Date: September 27, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 27, 2012 | Permit id: 428873 | |||||
Change use from vacant to barber shop on first floor Date: March 18, 2014 Permit type: Use permit | Permit status: Completed | Completion date: March 18, 2014 | Permit id: 507561 | |||||
Interior fit-out construction of two dwelling units on second and third floor of a shell building (ibc review) as per approved plans. Certificate of occupancy for two family dwelling only. Separate use registration and c. O. Permits required prior to occupancy of 1st floor. New fire suppression permit required for new floor configurations see a p 468503 for plans Date: June 24, 2013 Permit type: Alteration permit | Permit status: Completed | Completion date: August 10, 2013 | Permit id: 468505 | |||||
Addition and use change from all commercial to vacant commercial 1st floor (a use permit is required prior to occupancy) and one dwelling unit on the 2nd flr and one dwelling unit on the 3rd with a pilot house and roof deck as shown in the application. Date: April 26, 2013 Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 26, 2013 | Permit id: 458409 |