Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
2007 indiana elevator code section 2. 20. 4-the elevator steel wire rope suspension cables do not meet Date: October 11, 2012 Client: Eli Lilly | Permit type: State variance | Permit status: Closed | Completion date: December 6, 2012 | Permit id: Svr12-00249 | |||||
Lilly technology center south buildings 132 133 134 138 142 147 182 146concourse & skybridge / build Date: June 5, 2014 Value: $100,000 Permit type: Structural | Permit status: Review | Current use: Other special use | Permit id: Str14-02460 | |||||
Metes and bounds legal / eli lilly and company / 1525 sf remodel of existing 70929 sf / cdr??? / con Date: June 5, 2014 Value: $300,000 Permit type: Structural | Permit status: Review | Current use: Other special use | Permit id: Str14-02461 | |||||
SCORE 99 Metes & bounds legal/ eli lilly company/ bldg 33/ bh1 utilities design phase 1/ 12 sf per plans/ c Permit type: Structural | Permit status: Issued | Expiration date: August 4, 2015 | Current use: Other industrial | Permit id: Str14-03370 | |||||
SCORE 93 Metes & bounds legal/ eli lilly company/ bldg 33/ bh1 utilities design phase 1/ 12 sf per plans/ c Permit type: Structural | Permit status: Issued | Expiration date: August 4, 2015 | Current use: Other industrial | Permit id: Str14-03370 | |||||
SCORE 96 Metes & bounds legal / comm remodel 1271 sf / cdr# 374658 / const ty: i-b spk / occ: b / eli lilly Permit type: Structural | Permit status: Closed | Completion date: March 23, 2015 | Expiration date: June 2, 2015 | Current use: Office | Permit id: Str14-06162 | |||||
SCORE 96 Metes & bounds legal / comm remodel 1271 sf / cdr# 374658 / const ty: i-b spk / occ: b / eli lilly Permit type: Structural | Permit status: Closed | Completion date: March 23, 2015 | Expiration date: June 2, 2015 | Current use: Office | Permit id: Str14-06162 | |||||
SCORE 96 Eli lilly & company/ building k312/ fcs expansion/ cold storage field work project number 305-7178/ Permit type: Structural | Permit status: Issued | Expiration date: July 5, 2015 | Current use: Other industrial | Permit id: Str14-06561 | |||||
SCORE 96 Eli lilly & company/ building k312/ fcs expansion/ cold storage field work project number 305-7178/ Permit type: Structural | Permit status: Issued | Expiration date: July 5, 2015 | Current use: Other industrial | Permit id: Str14-06561 | |||||
Metes & bounds legal/ eli lilly/ k1 / 1-k136/ breakroom & fitness center/ commercial remodel 4524 Date: December 30, 2014 Value: $300,000 Permit type: Structural | Permit status: Review | Current use: Other industrial | Permit id: Str14-06637 | |||||
Metes & bounds/ eli lilly/ north k1 north cooling towers/ new 3 sty exterior stairs for cooling u Date: January 20, 2015 Permit type: Improvement location permit | Permit status: Issued | Expiration date: February 23, 2017 | Permit id: Ilp15-00067 | |||||
SCORE 96 Metes & bounds/ eli lilly/ north k1 north cooling towers/ commercial remodel 2964 sf per plans/ cd Permit type: Structural | Permit status: Issued | Expiration date: September 24, 2015 | Current use: Other industrial | Permit id: Str15-00103 | |||||
SCORE 96 Metes & bounds/ eli lilly/ north k1 north cooling towers/ commercial remodel 2964 sf per plans/ cd Permit type: Structural | Permit status: Issued | Expiration date: September 24, 2015 | Current use: Other industrial | Permit id: Str15-00103 | |||||
SCORE 99 Metes & bounds legal/ eli lilly k100/ continous manufacturing/ commercial remodel 4924 sf per plans/ Permit type: Structural | Permit status: Closed | Completion date: September 1, 2015 | Expiration date: October 14, 2015 | Current use: Manufacturing | Permit id: Str15-00291 | |||||
SCORE 96 Metes & bounds legal/ eli lilly k100/ continous manufacturing/ commercial remodel 4924 sf per plans/ Permit type: Structural | Permit status: Closed | Completion date: September 1, 2015 | Expiration date: October 14, 2015 | Current use: Manufacturing | Permit id: Str15-00291 | |||||
SCORE 96 Lilly technology center north/ building k325 b integrated project delivery team studio/ change of oc Permit type: Structural | Permit status: Closed | Completion date: July 13, 2015 | Expiration date: December 13, 2015 | Current use: Office | Permit id: Str15-01291 | |||||
SCORE 92 Lilly technology center north/ building k325 b integrated project delivery team studio/ change of oc Permit type: Structural | Permit status: Closed | Completion date: July 13, 2015 | Expiration date: December 13, 2015 | Current use: Office | Permit id: Str15-01291 | |||||
Remodel of two existing rooms Date: April 13, 2015 Permit type: Structural | Permit status: Hold | Current use: Manufacturing | Permit id: Str15-01454 | |||||
Lilly technology center redmodel / building k- 1st floor remodel per plans submitted / 6 sf / Date: April 20, 2015 Permit type: Structural | Permit status: Review | Current use: Manufacturing | Permit id: Str15-01603 | |||||
Eli lilly remodel / (b181) steam station upgrade per plans submitted / 1067 sf / cdr: 377402 / c Date: April 30, 2015 Permit type: Structural | Permit status: Hold | Current use: Other industrial | Permit id: Str15-01904 | |||||
SCORE 96 Eli lilly remodel / lilly k105 clean in place (cip) reagents per plans submitted / 1276 sf / cdr Date: May 4, 2015 Contractor: Joseph Cathcart Permit type: Structural | Permit status: Closed | Completion date: October 16, 2015 | Expiration date: December 14, 2015 | Current use: Manufacturing | Permit id: Str15-01984 | |||||
SCORE 96 Eli lilly remodel / lilly k105 clean in place (cip) reagents per plans submitted / 1276 sf / cdr Date: May 4, 2015 Contractor: Nancy Long Permit type: Structural | Permit status: Closed | Completion date: October 16, 2015 | Expiration date: December 14, 2015 | Current use: Manufacturing | Permit id: Str15-01984 | |||||
Eli lilly remodel / (b181) steam station upgrade per plans submitted / 1067 sf / cdr: 377402 / c Date: May 18, 2015 Permit type: Structural | Permit status: Review | Current use: Other industrial | Permit id: Str15-02321 | |||||
Metes and bounds / comm int remodel / 6 sf / cdr: 378399 / const type: ii-b / occ: f-1 / i4s / cen Date: June 4, 2015 Permit type: Structural | Permit status: Review | Current use: Manufacturing | Permit id: Str15-02629 | |||||
SCORE 96 Metes & bounds/ eli lilly/ ltc north campus/ bldg k314/ crso project/ 5th floor/ commercial remodel Permit type: Structural | Permit status: Issued | Expiration date: March 27, 2016 | Current use: Other special use | Permit id: Str15-04250 | |||||
SCORE 96 Metes & bounds/ eli lilly/ ltc north campus/ bldg k314/ crso project/ 5th floor/ commercial remodel Permit type: Structural | Permit status: Issued | Expiration date: March 27, 2016 | Current use: Other special use | Permit id: Str15-04250 | |||||
Engine generator relocation only Date: September 2, 2015 Value: $25,000 Permit type: Structural | Permit status: Cancelled | Current use: Manufacturing | Permit id: Str15-04625 | |||||
Metes & bounds legal/ eli lilly/ lilly technology center north/ basement retaining wall lilly lab pr Date: September 2, 2015 Value: $175,000 Permit type: Structural | Permit status: Issued | Expiration date: April 26, 2016 | Current use: Other commercial | Permit id: Str15-04628 | |||||
SCORE 93 Lilly complex howard st entrance / prefabricated guard house 24 sf / cdr exempt / i4s / center twp Permit type: Structural | Permit status: Closed | Completion date: February 4, 2013 | Expiration date: July 30, 2013 | Current use: Other industrial | Permit id: Str12-05148 | |||||
SCORE 93 Lilly complex / detached stand-alone canopy 3247 sf / cdr361027 / i4s / center twp - permitted under Permit type: Structural | Permit status: Renewed | Expiration date: March 19, 2014 | Current use: Other industrial | Permit id: Str12-05344 | |||||
Lilly complex south side of railroad walkway / new canopy over walkway 4 sf / cdr361027 / i4u / c Date: October 25, 2012 Value: $300,000 Permit type: Structural | Permit status: Closed | Completion date: February 4, 2013 | Expiration date: July 30, 2013 | Current use: Other industrial | Permit id: Str12-05380 | |||||
Comm interior remodel 16 sf per plans / cdr#_________/ const type: ii-b occ: b / eli lilly projec Date: June 3, 2013 Value: $222,000 Permit type: Structural | Permit status: Hold | Current use: Office | Permit id: Str13-02187 | |||||
Like-for-like replacement of 42 fume hoods and miscellaneous interior finish renovations to multiple Date: September 18, 2013 Value: $2,500,000 Permit type: Structural | Permit status: Cancelled | Permit id: Str13-04201 | |||||
SCORE 96 Lilly technology center south/ building k1 a/ commercial remodel 8085 sf per plans/ cdr # 367373/ Permit type: Structural | Permit status: Issued | Expiration date: March 24, 2014 | Current use: Other industrial | Permit id: Str13-04229 | |||||
SCORE 96 Lilly technology center south/ building k1 a/ commercial remodel 8085 sf per plans/ cdr # 367373/ Permit type: Structural | Permit status: Issued | Expiration date: March 24, 2014 | Current use: Other industrial | Permit id: Str13-04229 | |||||
SCORE 96 Metes and bounds legal / eli lilly building k362 - idm lab relocation / 62 sf remodel per plans / Permit type: Structural | Permit status: Permit amendment | Expiration date: June 21, 2014 | Current use: Office | Permit id: Str13-04639 | |||||
SCORE 96 Metes and bounds legal / eli lilly building k362 - idm lab relocation / 62 sf remodel per plans / Permit type: Structural | Permit status: Permit amendment | Expiration date: June 21, 2014 | Current use: Office | Permit id: Str13-04639 | |||||
SCORE 96 Metes & bounds legal / comm remodel 7 sf per plans / cdr# 368253 const type: ii-a spk spk / occ: b Permit type: Structural | Permit status: Issued | Expiration date: March 4, 2015 | Current use: Manufacturing | Permit id: Str13-04907 | |||||
SCORE 96 Metes & bounds legal / comm remodel 7 sf per plans / cdr# 368253 const type: ii-a spk spk / occ: b Permit type: Structural | Permit status: Issued | Expiration date: March 4, 2015 | Current use: Manufacturing | Permit id: Str13-04907 | |||||
SCORE 96 Metes & bounds legal / 1 sf remodel / cdr: 368313 /const: i-b / occ. B / i4u / center twp. Permit type: Structural | Permit status: Issued | Expiration date: June 4, 2014 | Current use: Other special use | Permit id: Str13-05088 | |||||
SCORE 96 Metes & bounds legal / 1 sf remodel / cdr: 368313 /const: i-b / occ. B / i4u / center twp. Permit type: Structural | Permit status: Issued | Expiration date: June 4, 2014 | Current use: Other special use | Permit id: Str13-05088 | |||||
Eli lilly / building k314 lab 4 / installation of fume hood 2 sf per plans / cdr: ______ / const Date: November 8, 2013 Value: $15,000 Permit type: Structural | Permit status: Review | Current use: Other special use | Permit id: Str13-05135 | |||||
SCORE 99 Lilly complex / detached stand-alone canopy 3247 sf / cdr361027 / i4s / center twp - permitted under Client: Eli Lilly & Co Attn Corporate Taxes Lilly Corporate Center | Permit type: Structural | Permit status: Renewed | Expiration date: March 19, 2014 | Current use: Other industrial | Permit id: Str12-05344 | |||||
SCORE 99 Lilly complex howard st entrance / prefabricated guard house 24 sf / cdr exempt / i4s / center twp Client: Eli Lilly & Co Attn Corporate Taxes Lilly Corporate Center | Permit type: Structural | Permit status: Closed | Completion date: February 4, 2013 | Expiration date: July 30, 2013 | Current use: Other industrial | Permit id: Str12-05148 | |||||
SCORE 99 Lilly complex north side of railroad walkway / new canopy over walkway 4 sf / cdr361027 / i4u / c Client: Eli Lilly & Co Attn Corporate Taxes Lilly Corporate Center | Permit type: Structural | Permit status: Closed | Completion date: February 4, 2013 | Expiration date: July 30, 2013 | Current use: Other industrial | Permit id: Str12-05343 | |||||
SCORE 93 Lilly complex north side of railroad walkway / new canopy over walkway 4 sf / cdr361027 / i4u / c Client: Eli Lilly & Co Attn Corporate Taxes Lilly Corporate Center | Permit type: Structural | Permit status: Closed | Completion date: February 4, 2013 | Expiration date: July 30, 2013 | Current use: Other industrial | Permit id: Str12-05343 | |||||
SCORE 96 Lilly technology center south/ raymond street vehicle inspection/ new 1 sty vehicle inspection canop Client: Eli Lilly & Company | Permit type: Structural | Permit status: Closed | Completion date: June 1, 2012 | Expiration date: June 19, 2012 | Current use: Other industrial | Permit id: Str11-04472 | |||||
SCORE 93 Lilly technology center south/ raymond street vehicle inspection/ new 1 sty vehicle inspection canop Client: Eli Lilly & Company | Permit type: Structural | Permit status: Closed | Completion date: June 1, 2012 | Expiration date: June 19, 2012 | Current use: Other industrial | Permit id: Str11-04472 | |||||
Lilly technology center south/ raymond street vehicle inspection/ new 1 sty vehicle inspection canop Date: October 31, 2011 Permit type: Improvement location permit | Permit status: Issued | Expiration date: December 21, 2013 | Permit id: Ilp11-01858 | |||||
Lilly technology center south raymond street vehicle inspection new 1 sty vehicle inspection canop Date: October 31, 2011 Client: Eli Lilly & Company | Permit type: Improvement location permit | Permit status: Issued | Expiration date: December 21, 2013 | Permit id: Ilp11-01858 |