New construction permit Date: August 10, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 293994 | |||||
Plumbing permit Date: November 1, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 309486 | |||||
Suppression permit Date: February 28, 2011 Client: Gunnison Land L P | Permit status: Completed | Permit id: 303359 | |||||
Electrical permit Date: October 22, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 307899 | |||||
Mechanical permit Date: November 12, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 311282 | |||||
Zoning/use permit Date: July 30, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 266174 | |||||
Permit for the erection of a three story semi detached structure(maximum height nte 35 feet) with cellar(flat roof) with bay window completely outside the property line with an open deck on the third floor front with a 42 inch high protective railing , with bays in the rear for use as a single family dwelling. (fast track) Date: April 28, 2010 Client: Gunnison Land L P | Applicant: Jason Colfer | Permit type: Appeal | Permit status: Granted | Completion date: July 13, 2010 | Permit id: 11613 | |||||
Mechanical permit Date: November 12, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 311282 | |||||
Suppression permit Date: February 28, 2011 Client: Gunnison Land L P | Permit status: Completed | Permit id: 303359 | |||||
Plumbing permit Date: November 18, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 312489 | |||||
New construction permit Date: August 10, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 293994 | |||||
Zoning use permit Date: July 30, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 266174 | |||||
Electrical permit Date: October 22, 2010 Client: Gunnison Land L P | Permit status: Completed | Permit id: 307899 | |||||
Permit for the erection of a three story semi detached structure(maximum height nte 35 feet) with cellar(flat roof) with bay window completely outside the property line with an open deck on the third floor front with a 42 inch high protective railing , with bays in the rear for use as a single family dwelling. (fast track) Date: April 28, 2010 Client: Gunnison Land L P | Applicant: Jason Colfer | Permit type: Appeal | Permit status: Granted | Completion date: July 13, 2010 | Permit id: 11613 | |||||
SCORE 100 New construction of a new 3 story sfd with cellar and 2nd fl. Roof deck Date: July 30, 2010 Contractor: Lawndale Construction Mgmt Llc Client: Wallace Chelsea Kathryn | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 30, 2010 | Permit id: 266174 | |||||
SCORE 100 "new construction of an attached 3 story sfd with 2nd fl roof deck and cellar per plans and spec; no parking and no garage proposed". Permit is for the construction of a fully suppressed, three story, single family dwelling with a rear deck. No excavation below adjacent existing footing foundation approved without a revised permit and plan prepared by a registered structural engineer. Separate permits required for plumbing, electrical, mechanical, and fire suppression work. Date: August 10, 2010 Contractor: Lawndale Construction Mgmt Llc Client: Wallace Chelsea Kathryn | Permit type: New construction permit | Permit status: Completed | Completion date: May 12, 2011 | Permit id: 293994 | |||||
SCORE 100 Install new fire suppression system for sfd and new backflow system as per plan. Date: February 28, 2011 Contractor: Fire Protection Services Inc Client: Wallace Chelsea Kathryn | Permit type: Suppression permit | Permit status: Completed | Completion date: May 13, 2011 | Permit id: 303359 | |||||
SCORE 100 Install 2 amp service, total rewire as per 2008 nec (south dist) Date: October 22, 2010 Contractor: James Wilkins Client: Wallace Chelsea Kathryn | Permit type: Electrical permit | Permit status: Completed | Completion date: March 23, 2011 | Permit id: 307899 | |||||
SCORE 100 3 toilets,3 laundry,2 tubs,1 kitchen sinks,1 washing machine drain Date: November 18, 2010 Contractor: Richards Barrymore Client: Wallace Chelsea Kathryn | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 27, 2013 | Permit id: 312489 | |||||
SCORE 100 Install direct vent goodman 90,0 warm air furnace, ac coil & condenser with related duct work Date: November 12, 2010 Contractor: Christopher G. Long Client: Wallace Chelsea Kathryn | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 13, 2011 | Permit id: 311282 | |||||
SCORE 100 3 toilets,3 lavatory sink,2 bath tubs,1 kitchen sink,1 washing machine Date: November 1, 2010 Contractor: Richards Barrymore Client: Wallace Chelsea Kathryn | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 27, 2013 | Permit id: 309486 |