Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Use permit Date: November 26, 2012 Permit status: Completed | Permit id: 439640 | |||||
Sign permit Date: April 17, 2015 Permit status: Completed | Permit id: 586749 | |||||
Zoning/use permit Date: June 18, 2007 Permit status: Completed | Permit id: 64982 | |||||
Electrical permit Date: August 7, 2014 Permit status: Completed | Permit id: 554522 | |||||
Plumbing permit Date: March 17, 2015 Permit status: Completed | Permit id: 594080 | |||||
Demolition permit Date: February 10, 2015 Permit status: Completed | Permit id: 589801 | |||||
Suppression permit Date: July 10, 2014 Permit status: Completed | Permit id: 548460 | |||||
Mechanical permit Date: March 27, 2015 Permit status: Completed | Permit id: 594611 | |||||
Suppression permit Date: April 23, 2015 Permit status: Completed | Permit id: 598297 | |||||
Demolition permit Date: April 2, 2014 Permit status: Completed | Permit id: 528075 | |||||
Plumbing permit Date: July 3, 2014 Permit status: Completed | Permit id: 539759 | |||||
Mechanical permit Date: September 24, 2014 Permit status: Completed | Permit id: 553755 | |||||
Administrative permit Date: November 24, 2014 Permit status: Completed | Permit id: 571491 | |||||
Electrical permit Date: June 2, 2015 Permit status: Expired | Permit id: 602119 | |||||
Alteration permit Date: August 18, 2014 Permit status: Completed | Permit id: 538507 | |||||
Mechanical permit Date: January 17, 2013 Permit status: Completed | Permit id: 444355 | |||||
Alteration permit Date: November 20, 2012 Permit status: Completed | Permit id: 438933 | |||||
Administrative permit Date: May 11, 2015 Permit status: Completed | Permit id: 608987 | |||||
Sign permit Date: August 20, 2009 Permit status: Completed | Permit id: 215857 | |||||
Plumbing permit Date: May 1, 2009 Permit status: Completed | Permit id: 213547 | |||||
Electrical permit Date: January 4, 2013 Permit status: Completed | Permit id: 446347 | |||||
Sign permit Date: December 4, 2014 Permit status: Completed | Permit id: 570555 | |||||
Electrical permit Date: May 26, 2009 Permit status: Completed | Permit id: 217499 | |||||
Zoning/use permit Date: May 14, 2009 Permit status: Completed | Permit id: 208648 | |||||
Use permit Date: February 11, 2014 Permit status: Completed | Permit id: 516360 | |||||
Alteration permit Date: June 4, 2009 Permit status: Completed | Permit id: 211370 | |||||
Sign permit Date: June 14, 2007 Permit status: Completed | Permit id: 64984 | |||||
Plumbing permit Date: January 28, 2013 Permit status: Completed | Permit id: 446884 | |||||
Use permit Date: September 26, 2013 Permit status: Completed | Permit id: 493111 | |||||
Zoning/use permit Date: May 1, 2014 Permit status: Completed | Permit id: 521531 | |||||
Alteration permit Date: March 3, 2015 Permit status: Completed | Permit id: 584608 | |||||
Permit for a take-out restaurant. Date: January 5, 2009 Applicant: Joseph Beller, Esquire | Permit type: Appeal | Permit status: Withdrawn | Permit id: 8130 | |||||
Alteration permit Date: June 4, 2009 Permit status: Completed | Permit id: 211370 | |||||
Administrative permit Date: April 17, 2015 Permit status: Completed | Permit id: 595969 | |||||
Sign permit Date: August 20, 2009 Permit status: Completed | Permit id: 215857 | |||||
Electrical permit Date: June 2, 2015 Permit status: Expired | Permit id: 602119 | |||||
Electrical permit Date: August 7, 2014 Permit status: Completed | Permit id: 554522 | |||||
Demolition permit Date: March 26, 2014 Permit status: Completed | Permit id: 526346 | |||||
Sign permit Date: April 17, 2015 Permit status: Completed | Permit id: 586749 | |||||
Alteration permit Date: November 20, 2012 Permit status: Completed | Permit id: 438933 | |||||
Use permit Date: February 11, 2014 Permit status: Completed | Permit id: 516360 | |||||
Demolition permit Date: February 10, 2015 Permit status: Completed | Permit id: 589801 | |||||
Mechanical permit Date: September 24, 2014 Permit status: Completed | Permit id: 553755 | |||||
Use permit Date: September 26, 2013 Permit status: Completed | Permit id: 493111 | |||||
Zoning use permit Date: September 4, 2014 Permit status: Completed | Permit id: 551887 | |||||
Suppression permit Date: July 10, 2014 Permit status: Completed | Permit id: 548460 | |||||
Administrative permit Date: November 24, 2014 Permit status: Completed | Permit id: 571491 | |||||
Alteration permit Date: March 3, 2015 Permit status: Completed | Permit id: 584608 | |||||
Mechanical permit Date: March 27, 2015 Permit status: Completed | Permit id: 594611 | |||||
Alteration permit Date: September 12, 2014 Permit status: Completed | Permit id: 540878 | |||||
Plumbing permit Date: December 19, 2014 Permit status: Completed | Permit id: 580955 | |||||
Zoning use permit Date: May 14, 2009 Permit status: Completed | Permit id: 208648 | |||||
Plumbing permit Date: May 1, 2009 Permit status: Completed | Permit id: 213547 | |||||
Suppression permit Date: April 23, 2015 Permit status: Completed | Permit id: 598297 | |||||
Zoning use permit Date: June 18, 2007 Permit status: Completed | Permit id: 64982 | |||||
Electrical permit Date: May 26, 2009 Permit status: Completed | Permit id: 217499 | |||||
Use permit Date: November 26, 2012 Permit status: Completed | Permit id: 439640 | |||||
Plumbing permit Date: March 17, 2015 Permit status: Completed | Permit id: 594080 | |||||
Sign permit Date: December 4, 2014 Permit status: Completed | Permit id: 570555 | |||||
Sign permit Date: June 14, 2007 Permit status: Completed | Permit id: 64984 | |||||
Plumbing permit Date: January 28, 2013 Permit status: Completed | Permit id: 446884 | |||||
Mechanical permit Date: January 17, 2013 Permit status: Completed | Permit id: 444355 | |||||
Electrical permit Date: January 4, 2013 Permit status: Completed | Permit id: 446347 | |||||
Permit for a take-out restaurant. Date: January 5, 2009 Applicant: Joseph Beller, Esquire | Permit type: Appeal | Permit status: Withdrawn | Permit id: 8130 | |||||
SCORE 100 Interior finishes work to the main lobby to include include tile walls, painting and stainless steel panels installation. Date: June 4, 2009 Contractor: Hms Interiors Inc Permit type: Alteration permit | Permit status: Completed | Completion date: July 23, 2009 | Permit id: 211370 | |||||
SCORE 99 Front sidewalk of office bld, remove and replace existing house trap. Date: May 1, 2009 Contractor: Stanley Rajauski Jr Permit type: Plumbing permit | Permit status: Completed | Completion date: December 1, 2009 | Permit id: 213547 | |||||
SCORE 100 Install illum contour channel Date: April 17, 2015 Contractor: Allied Sign Systems Permit type: Sign permit | Permit status: Completed | Completion date: May 14, 2015 | Permit id: 586749 | |||||
SCORE 86 Installation of 42 ploenum category 6 cables in compliance with 2008 nec at wells fargo branch location as per nec 2008. Installation to comply with articles 300. 21, 300. 22 & 8 of the 2008 nec. Date: June 2, 2015 Contractor: Mcnair Electrical And Mechanical Permit type: Electrical permit | Permit status: Expired | Completion date: June 2, 2015 | Permit id: 602119 | |||||
SCORE 99 Lavys, water closets, drinking fountain, urinals, mop sinks, kitchen sink, floor drains and water heater - the installation will compy with the philadephia plubming code 2004 Date: March 17, 2015 Contractor: Mccloskey Mechanical Cont Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: May 21, 2015 | Permit id: 594080 | |||||
SCORE 88 Int demo-interior demolition of floors 4,5,7,8,14,16. No structural work. (no demoilition activity shall commence prior to the required abatement of asbestos is completed by licensed asbestos remediation contractor, and a copy of required abatement documentation is presented to district field inspector.) Date: May 2, 2014 Contractor: Universal Cutting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: June 30, 2014 | Permit id: 534222 | |||||
SCORE 95 Hvac work to include new ductwork with associated registers diffusers, cooling tower, make up air handling unit, heat pumps, and all other work as per approved plans. Date: September 5, 2014 Contractor: Falasca Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: July 1, 2015 | Permit id: 533970 | |||||
SCORE 88 Int demo-interior demolition of floor (12th floor only)no structural work. (no demoilition activity shall commence prior to the required abatement of asbestos is completed by licensed asbestos remediation contractor, and a copy of required abatement documentation is presented to district field inspector.) Date: April 7, 2014 Contractor: Universal Cutting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: June 13, 2014 | Permit id: 529004 | |||||
SCORE 100 Temporary certificate of occupancy for the 16th floor only. Date: June 4, 2015 Contractor: Clemens Construction Co Inc Permit type: Administrative permit | Permit status: Completed | Completion date: June 8, 2015 | Permit id: 614914 | |||||
T. C. O. Floors 13,14,15 Date: June 11, 2015 Permit type: Administrative permit | Permit status: Completed | Completion date: June 15, 2015 | Permit id: 616880 | |||||
1 day tco floors 1 & 2 Date: June 12, 2015 Permit type: Administrative permit | Permit status: Completed | Completion date: June 15, 2015 | Permit id: 617132 | |||||
Manufacture and install (1) set of (15) channel letters per drawing. Date: June 18, 2007 Permit type: Zoning/use permit | Permit status: Completed | Completion date: April 4, 2008 | Permit id: 64982 | |||||
Amending bldg permit #524307 per revised plans. Date: April 17, 2015 Permit type: Administrative permit | Permit status: Completed | Completion date: July 1, 2015 | Permit id: 595969 | |||||
SCORE 100 Furnish and install new fire alarm pull station horn strobes, smoke detectors and strobes tied into existing system as per nfpa72 (cc district) Date: March 27, 2015 Contractor: Michael Kowal Permit type: Electrical permit | Permit status: Completed | Completion date: November 3, 2015 | Permit id: 595838 | |||||
For the change in use to financial services (wells fargo bank) at the first floor commercial space #1 as per plans. Relocation of tenants dunkin doonits and wendy to commercial spaces #2 and #3 as per plans. No signs on this application. Not filed Date: March 28, 2014 Permit type: Use permit | Permit status: Completed | Completion date: March 28, 2014 | Permit id: 525425 | |||||
SCORE 100 New tenant fit out for wendys including sanitary and domestic water (restaurant) Date: September 18, 2014 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: January 23, 2015 | Permit id: 554606 | |||||
SCORE 88 For the erection of a covered walkway as per plans and section 3306. 7 of the 2009 ibc. Date: September 12, 2014 Contractor: Safespan Pa Llc Permit type: Alteration permit | Permit status: Completed | Completion date: June 8, 2015 | Permit id: 540878 | |||||
For int. Alterations t o existing structure incl the construction of (180) dwelling units, accessory amenity and leasing office space on flrs 2 thru 17, and residential lobby @ 1st floor, and for the erection of egress stair pilot house at lower roof, as per plans. Date: May 6, 2014 Permit type: Alteration permit | Permit status: Completed | Completion date: June 29, 2015 | Permit id: 524307 | |||||
For the addition of pilot house for egress stair on 1 story portion on the north side of the bldg facing alley, for the demolition of existing facade facing, removal of existing awnings and signage, for the erection of architectural embellishments, for the erection of an awning on 15th st. Facade, no signs on this on this application Date: May 1, 2014 Permit type: Zoning/use permit | Permit status: Completed | Completion date: May 1, 2014 | Permit id: 521531 | |||||
New use - 3rd - 17th flr - for use as 173 residential condos with 1st 7 2nd flr uses to remain as previously zoned. Date: September 26, 2013 Permit type: Use permit | Permit status: Completed | Completion date: September 26, 2013 | Permit id: 493111 | |||||
SCORE 100 For the installation of a fire suppression system on the ground floor of an existing building. Service provided via an existing 6" fire service main line with backflow prevention assembly. Date: April 23, 2015 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 598297 | |||||
SCORE 100 Install new service, lighting, branch wiring, recepts and equipment connections, install telecommunications cabling & jacks, audio and equipment as per 2008 nec (cc district) install wiring and devices as per nfpa72 Date: November 10, 2014 Contractor: Lyndee Corporation Permit type: Electrical permit | Permit status: Completed | Completion date: April 24, 2015 | Permit id: 567527 | |||||
SCORE 100 Install new service, lighting, branch wiring, recepts and equipment connections as per 2008 nec (cc district) install wiring and devices as per nfpa72 Date: November 10, 2014 Contractor: Lyndee Corporation Permit type: Electrical permit | Permit status: Expired | Completion date: November 10, 2014 | Permit id: 567526 | |||||
SCORE 100 Fit out relocated dunkin donut to new space to include 3-sink, 4-floor drain & 4-wc & 1-prep sink (mixed use) Date: October 3, 2014 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: January 23, 2015 | Permit id: 558785 | |||||
For the amendment of building permit ap#538507, to remove proposed mezzanine and expand tenant area at ground floor level. No exterior facade or store-front work. Separate permits required for installation of proposed signs, fire suppression system alterations, plumbing alterations, mechanical, and electrical work. Asbestos abatement to be completed prior to commencement of permit scope of work. Date: September 26, 2014 Permit type: Administrative permit | Permit status: Completed | Completion date: November 25, 2014 | Permit id: 558492 | |||||
SCORE 100 15"lateral, house trap and partial house drain replacement into the building - "self-certifications are no longer permitted" - "all excavations and plumbing trenches in excess of 5 feet in depth must have approved shoring in place at the time of inspection" Date: December 19, 2014 Contractor: J S Plumbing Company Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 580955 | |||||
SCORE 100 Erection of 5 wall signs for wells fargo in accordance with approved zoning. Date: December 4, 2014 Contractor: Philadelphia Sign Company Permit type: Sign permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 570555 | |||||
Amending bldg permit #524307 for the removal of elevator lobby doors, as per plans. The project was reviewed for code compliance using chapter 34 compliance alternatives for which it received a passing scord and is therefore deemed compliant. That compliance path does not require the construction of interior elevator lobbies, therefore, elevator lobby doors are not required.. Date: November 24, 2014 Permit type: Administrative permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 571491 | |||||
SCORE 100 Disconnect existing elec service as necessary & install 50-temporary lights & recepts for construction purposes as per nec 2008 (comm) from 8 7 14 to 11 7 14 Date: August 7, 2014 Contractor: Lyndee Corporation Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2014 | Permit id: 554522 | |||||
SCORE 95 Install mechanicals, ducting, registers, diffusers, applicances to serve tenant space. Date: September 24, 2014 Contractor: Falasca Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 553755 | |||||
For the erection of signs and awnings at the ground floor only. Five signs Date: September 4, 2014 Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 4, 2014 | Permit id: 551887 | |||||
SCORE 95 Install of commercial cooking exhaust systems. One (1) island type commercial kitchen hood and one (1) wall type commercial kitchen hood. Work to include,ductwork and fans. Separate permit is required for cooking extinguishing system Date: December 22, 2014 Contractor: Falasca Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 578117 | |||||
SCORE 99 17th floor roof. Install new 1 1 2 instulation foam over existing roof. Fully adhere ogo white tpo versico roof system td roof deck, walls. Install new draw inserts. Install new flashing details. Install edge metal detail. Install new walkway pads. Date: November 20, 2012 Contractor: Elite Roofing And Contracting Permit type: Alteration permit | Permit status: Completed | Completion date: November 29, 2013 | Permit id: 438933 | |||||
SCORE 100 Installation of 2 sets of illuminated channel letters signage as per plans. Date: August 20, 2009 Contractor: Aztec Signs And Graphics Inc Permit type: Sign permit | Permit status: Completed | Completion date: September 10, 2009 | Permit id: 215857 | |||||
SCORE 100 This is a first floor tenant in a multi story high rise with office space, we added new sign circuit from existing panel with time clock,as per 2005 nec (cc dist) Date: May 26, 2009 Contractor: Cobra Electric Permit type: Electrical permit | Permit status: Completed | Completion date: June 21, 2010 | Permit id: 217499 | |||||
SCORE 100 Renovation to existing lobby. Remove existing fixtures and install (19) light fixtures, connect to existing circuit as per 2005 (cc dist) Date: July 10, 2009 Contractor: New Light Electric Inc Permit type: Electrical permit | Permit status: Expired | Completion date: July 10, 2009 | Permit id: 225820 | |||||
SCORE 100 First floor install 8 pedicare chairs, 2 handsinks, 1 lav & 1wc (retail) Date: January 28, 2013 Contractor: Randy Ho Permit type: Plumbing permit | Permit status: Completed | Completion date: March 7, 2013 | Permit id: 446884 | |||||
SCORE 97 Replace 15-outlets, 20-lgts fixtures, 4-emer lgts & 2-emer exist signs as per nec 2008 (comm) Date: January 4, 2013 Contractor: Anthony Franklin Permit type: Electrical permit | Permit status: Completed | Completion date: May 4, 2013 | Permit id: 446347 | |||||
SCORE 100 Installation of signage Date: May 14, 2009 Contractor: Aztec Signs And Graphics Inc Permit type: Zoning/use permit | Permit status: Completed | Completion date: May 14, 2009 | Permit id: 208648 | |||||
SCORE 100 15kv service,208v&480v substations,busway,lighting,branch wiring,devices,tele cabling devices equip,audio visual cabling equipment & security cabling devices equipment & fa to incl cabling devices & equip per 2008 nec & nfpa 72(mixed use) Date: July 15, 2014 Contractor: Lyndee Corporation Permit type: Electrical permit | Permit status: Completed | Completion date: September 27, 2014 | Permit id: 541020 | |||||
SCORE 100 Replace 11 speakers, 1 rack amp, 1 music player and 1 volume controller as per nec 2008 (cc district) Date: November 3, 2014 Contractor: Christopher Richard Permit type: Electrical permit | Permit status: Completed | Completion date: May 5, 2015 | Permit id: 571879 | |||||
SCORE 100 Install one asul r-102 9 gallon wet chemical kitchen suppression system a per kitchen supression system ez standards Date: December 30, 2014 Contractor: Atlantic Fire Equipment Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 582203 | |||||
Level ii alteration includes installation of (2) interior atms and (2) exterior atms and a night drop. Date: March 3, 2015 Permit type: Alteration permit | Permit status: Completed | Completion date: May 19, 2015 | Permit id: 584608 | |||||
SCORE 100 Cap off 2-existing laterals pa20150750255 "self-certifications are no longer permitted" - "all excavations & plumbing trenches in excess of 5 in depth must have approved shoring in place at the time of inspection Date: March 16, 2015 Contractor: J S Plumbing Company Llc Permit type: Plumbing permit | Permit status: Completed | Completion date: March 20, 2015 | Permit id: 596121 | |||||
SCORE 100 For the installation of hvac mechanical equipment to include new ductwork, register diffusers grilles, water-sourced heat pumps, electric duct heater, and electric baseboard heaters. Date: March 27, 2015 Contractor: Cms Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: May 21, 2015 | Permit id: 594611 | |||||
Temporary certificate of occupancy for floors #3 through #12 and floor #17 only. Date: May 11, 2015 Permit type: Administrative permit | Permit status: Completed | Completion date: May 15, 2015 | Permit id: 608987 | |||||
SCORE 100 Install new switches,recepts and lights for 7 teller stations and 12 offices as per 2008 nec (cc district) Date: March 27, 2015 Contractor: Michael Kowal Permit type: Electrical permit | Permit status: Completed | Completion date: November 3, 2015 | Permit id: 593093 | |||||
Interior demolition 1st floor - business Date: February 10, 2015 Permit type: Demolition permit | Permit status: Completed | Completion date: March 10, 2015 | Permit id: 589801 | |||||
Interior alterations. Combine tenant spaces 1511 thru 1515. No change in occupancy classification iebc existing. New partitions, new fit out, finishes, equpiment, furnishings, as per plans for 1st floor and lower level basement commercial spaces. Building fully sprinklered. Additional permits req: electrical, plumbing, hvac, sprinklers, signs. Date: May 7, 2014 Permit type: Alteration permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 529661 | |||||
SCORE 88 Interior demolition of floors 2,6, and 15 no structural work. (no demoilition activity shall commence prior to the required abatement of asbestos is completed by licensed asbestos remediation contractor, and a copy of required abatement documentation is presented to district field inspector.) Date: April 2, 2014 Contractor: Universal Cutting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: June 30, 2014 | Permit id: 528075 | |||||
SCORE 88 Interior demolition of non load bearing assemblies only. No demoilition activity shall commence prior to the required abatement of asbestos is completed by licensed asbestos remediation contractor, and a copy of required abatement documentation is presented to district field inspector. Date: March 3, 2014 Contractor: Universal Cutting Inc Permit type: Demolition permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 522067 | |||||
Change in use at the 2nd - 17th floors to 1 total residential units with accessory fitness center, leasing office and common areas. Date: February 11, 2014 Permit type: Use permit | Permit status: Completed | Completion date: February 11, 2014 | Permit id: 516360 | |||||
SCORE 100 Relocate 1 sprinklers on the basement and 1st fl of 151 chestnut street. Date: July 10, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 548460 | |||||
SCORE 100 Plumbing alterations to an existing structure and for the construction of (180) dwelling units with an accessory amenity and leasing office space - sanitary, storm and water supply piping throughout per the approved plans - (927)fixtures total - note: house trap, lateral and sewer connection are "by others" Date: July 3, 2014 Contractor: E J Raith Mechanical Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: June 16, 2015 | Permit id: 539759 | |||||
SCORE 86 Installation of three (3) signs comprised of channel letters and logos to be installed on opposing corner facades. All work shall comply with the approved plans. This work activity shall be performed by contractors and sub-contractors licensed by the city of philadelphia. Post this permit . Post the project information sign . Date: January 22, 2015 Contractor: Street Lighting Signs Llc Permit type: Sign permit | Permit status: Completed | Completion date: June 12, 2015 | Permit id: 581195 | |||||
SCORE 100 For the installation of new mains, lines, (1499) sprinklers, and an additional 4" diameter standpipe (250gpm) for the 2nd through the 13th floor, including penthouse and exit stairs, to connect to existing standpipe system with a new fire pump installation, in conformance with nfpa 2007, standard 13 & 14. Separate fire suppression permit to be required at pilot house sprinkler installation. Date: October 8, 2014 Contractor: Oliver Sprinkler Co Inc Permit type: Suppression permit | Permit status: Completed | Completion date: June 5, 2015 | Permit id: 548473 | |||||
Proposed for the use of the first floor for a nail salon. Space #1509 Date: November 26, 2012 Permit type: Use permit | Permit status: Completed | Completion date: November 26, 2012 | Permit id: 439640 | |||||
For the interior fit-out of ground floor commercial space, to include interior wall ceiling floor finishing, installation of new accessible bathrooms, accessible service counters, new partition wall installations, interior lighting scheme, and new structural framing for proposed mezzanine level. No exterior facade or store-front work. Separate permits required for installation of proposed signs, fire suppression system alterations, plumbing alterations, mechanical, and electrical work. Asbestos abatement to be completed prior to commencement of permit scope of work. Date: August 18, 2014 Permit type: Alteration permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 538507 | |||||
SCORE 95 For the installation of an hvac system to connect to existing system, with new ductwork, register diffusers grilles, exhaust and supply fans, and two (2) new water-sourced heat pumps. Date: October 29, 2014 Contractor: Falasca Mechanical Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 16, 2015 | Permit id: 563724 | |||||
Partial change of occupancy with level 2 alterations for a nail salon fit out as per plan. Separate permits required for ventilation of nail stations, electrical and plumbing Date: December 20, 2012 Permit type: Alteration permit | Permit status: Completed | Completion date: March 7, 2013 | Permit id: 444002 | |||||
Install ventilation system for nail salon to include 6 grds, 1 exhaust fan, 1 make-up air fan and all associated ductwork. See a p#444002 for plans Date: January 17, 2013 Permit type: Mechanical permit | Permit status: Completed | Completion date: March 14, 2013 | Permit id: 444355 |