SCORE 97 Building demolition and debris removal vacant lot demolition of an existing cement storage silo to grade as per owners request Date: April 4, 2001 Contractor: Tim Brown Client: Cement Co, Dundee | Permit id: B01001781 | |||||
SCORE 56 General repairs processing plant remove existing foundation at existing air products and chemicals plant. Date: November 1, 2002 Contractor: Robert Garsee Permit id: B02005217 | |||||
SCORE 56 New construction project processing plant new construction of a processing plant at existing air products facility as per plans. Date: August 8, 2003 Contractor: William Fannin Client: Chemicals, Inc., Air Products & | Permit id: B02004850 | |||||
SCORE 59 General repairs processing plant replace existing tank w foundation for a water tank at u. S. Filters n. O. East facility as per plans. Date: April 21, 2003 Contractor: Robert Dowty Client: Filter, U S | Permit id: B03001820 | |||||
SCORE 89 Building addition (less than 50% new) processing plant w. Conner ellis Date: February 9, 2004 Contractor: W. Conner Ellis Client: Recovery Ser, U S Filter | Permit id: E04000899 | |||||
SCORE 59 Antenna colocation on existing wireless tower. No ground work. No electrical. No change in tower height. Permit type: Renovation (non-structural) | Permit status: Permit issued | Expiration date: January 29, 2015 | Current use: Business use | Permit id: 14-20168-Rnvn | |||||
SCORE 99 Replace (4) existing antennas with (2) new antennas and replace existing ground equipment cabinets with new cabinets. (sprint) Permit type: Renovation (non-structural) | Permit status: Certificate of occupancy | Completion date: July 9, 2014 | Expiration date: February 15, 2013 | Current use: Business use | Permit id: 12-21915-Rnvn | |||||
Install new fuel cell cabinet on the existing elevated platform and install storage module on the existing concrete pad under the platform within the compound per plans. Date: September 7, 2012 Value: $49,545 Permit type: Renovation (structural) | Permit status: Permit issued | Expiration date: April 17, 2013 | Current use: Business use | Permit id: 12-23731-Rnvs | |||||
SCORE 79 Replace (4) existing antennas with (2) new antennas and replace existing ground equipment cabinets with new cabinets. (sprint) Permit type: Renovation (non-structural) | Permit status: Certificate of occupancy | Completion date: July 9, 2014 | Expiration date: February 15, 2013 | Current use: Business use | Permit id: 12-21915-Rnvn | |||||
SCORE 56 New construction project processing plant new construction of a water treatment unit for processing water at an existing processing plant as per plans. Date: January 29, 2004 Contractor: Bob Dowty Client: Recovery Ser, U S Filter | Permit id: B03004986 | |||||
SCORE 59 Tornado damage repair to existing building - re-skin metal shops, replace metal roofs and pearlings. Permit type: Renovation (non-structural) | Permit status: Permit issued | Expiration date: August 23, 2017 | Current use: Business use | Permit id: 17-06521-Rnvn | |||||
SCORE 85 Tornado damage - re-skin metal shop, replace metal roofs and purlins. Permit type: Renovation (non-structural) | Permit status: Application submitted | Current use: Business use | Permit id: 17-06161-Rnvn | |||||
SCORE 96 Storm damage - repair overhead distribution system 17-06521-rnvn Date: March 3, 2017 Contractor: Edward Joseph Deubler Iii Permit type: Electrical repair / replacement / addition | Permit status: Permit issued | Expiration date: September 3, 2017 | Current use: Business use | Permit id: 17-07333-Erpr | |||||
SCORE 99 New construction project manufacturing plant construction of concrete silos for cement storage as per plans. Date: October 15, 1998 Contractor: Charles Jones Client: Industries, Lone Star | Permit id: B98005291 | |||||
SCORE 93 Electrical reconnect processing plant clarke battle planned outage reconnect Date: January 24, 2001 Contractor: Clarke Battle Client: Industries, Lone Star | Permit id: E01000527 | |||||
SCORE 98 General repairs maintenance facility general repairs and relocate circuits Date: June 1, 2001 Contractor: Rickey Kastner Client: Industries, Lone Star | Permit id: E01004134 | |||||
SCORE 98 General repairs processing plant maintenance contract 6 mo. Gary williams Date: July 20, 2001 Contractor: Gary Williams Client: Industries, Lone Star | Permit id: E01005525 | |||||
SCORE 98 General repairs processing plant gary williams cement plant general maintenance Date: June 24, 2002 Contractor: Gary Williams Client: Industries, Lone Star | Permit id: E02004741 | |||||
SCORE 98 Semi annual inspection processing plant gary williams Date: September 18, 2003 Contractor: Gary Williams Client: Industries, Lone Star | Permit id: E03007225 | |||||
SCORE 93 Electrical reconnect processing plant clark battle Date: January 8, 2001 Contractor: Clarke Battle Client: Star Industry, Lone | Permit id: E01000190 | |||||
SCORE 98 Circuits only processing plant circuits Date: June 5, 2001 Contractor: Gary Williams Client: Star Industry, Lone | Permit id: E01004217 | |||||
SCORE 98 Semi annual inspection office building gary williams Date: December 26, 2002 Contractor: Gary Williams Client: Star Industry, Lone | Permit id: E02009818 | |||||
SCORE 98 Semi annual inspection processing plant steven ordes Date: January 27, 2004 Contractor: Steven Ordes Client: Star Industry, Lone | Permit id: E04000558 | |||||
SCORE 86 Electrical reconnect office building a. B. Reimann Date: March 26, 2001 Contractor: A.B. Reimann Client: Moko Investment, Llc | Permit id: E01002292 | |||||