SCORE 95 Connect 15 north capitol street, n. W. With underground service by building 28 of service conduit also install bend and abandon service conduit; sidewalk of north capitol street north of "p" street, n. W. This construction permit requires a separate occupancy permit. The attached plans and condtions are a part of this permit. If steel plates are used at this job site an additional permit is needed. Wr #33948 tcp-see attached cut #27853 stephen j. Park (202) 388-2573 sjpark@pepco. Com (g curtis) Date: December 21, 2012 Contractor: Pepco Permit type: Excavation; electric ml conduit (trench) | Permit status: Permit expired | Expiration date: May 9, 2013 | Permit id: Pa78112 | |||||
SCORE 95 Connect 15 north capitol street, n. W. With underground service by building 28 of service conduit; sidewalk of north capitol street north of "p" street, n. W. As indicated on the attached prints. Wr #33948 tcp-custom cut 327853 stephen j. Park (202) 388-2573 sjpark@pepco. Com (g curtis) Date: July 16, 2013 Contractor: Pepco Permit type: Excavation; electric connection (trench) | Permit status: Permit expired | Expiration date: November 21, 2013 | Permit id: Pa84739 | |||||
SCORE 99 Tempoary construction fence Date: August 17, 2016 Contractor: Douglas Development Client: Jemals 15 North Capitol Llc Jemals 15 North Capitol Llc | Permit type: Fixture; fence to 42" (open design) | Permit status: Denied | Expiration date: November 18, 2016 | |||||
SCORE 99 Fixture; fence to 42" (open design) Contractor: Douglas Development Permit status: 2 | Expiration date: November 18, 2016 | Permit id: 0 | |||||
SCORE 96 Paving; leadwalk repair replace existing, fixture; bike rack(s), fixture; fence to 42" (open design), landscaping; tree planting, projections; awning(s), projections; bay window(s), projections; window well(s) Contractor: Will Teass Permit status: 12 | Expiration date: April 1, 2018 | Permit id: 0 | |||||
SCORE 96 New combined lot at 15 and 1512 north capitol (currently working through subdivision). Alteration of two, two story + cellar, row-houses into 5 stories + cellar multifamily building. Demolition of existing lead walks and bay projections at 15 & 1512 north capitol. Replace leadwalk at 15 north capitol. New bike rack adjacent to lead walk. New awning at front entry. New window wells and rails. New bay projection from grade to 4th floor. New tree planting in front of building. Date: May 9, 2017 Contractor: Will Teass Permit type: Paving; leadwalk repair/replace existing, fixture; bike rack | Permit status: Assigned | Expiration date: April 1, 2018 | Permit id: 0 | |||||
SCORE 70 Construction staging area Permit status: Approved | Expiration date: August 31, 2017 | Permit id: 0 | |||||
SCORE 96 New combined lot at 15 and 1512 north capitol (currently working through subdivision). Alteration of two, two story + cellar, row-houses into 5 stories + cellar multifamily building. Demolition of existing lead walks and bay projections at 15 & 1512 north capitol. Replace leadwalk at 15 north capitol. New bike rack adjacent to lead walk. New awning at front entry. New window wells and rails. New bay projection from grade to 4th floor. New tree planting in front of building. Contractor: Will Teass Permit status: Assigned | Expiration date: April 1, 2018 | Permit id: 0 | |||||
SCORE 95 Connect 15 north capitol street, n. W. With underground service by building 28 of service conduit also install bend and abandon service conduit; sidewalk of north capitol street north of "p" street, n. W. This construction permit requires a separate occupancy permit. The attached plans and condtions are a part of this permit. If steel plates are used at this job site an additional permit is needed. Wr #33948 tcp-see attached cut #27853 stephen j. Park (202) 388-2573 sjpark@pepco. Com (g curtis) Date: March 7, 2013 Contractor: Pepco Permit status: Permit expired | Expiration date: May 9, 2013 | Permit id: Pa78112 | |||||
SCORE 95 Connect 15 north capitol street, n. W. With underground service by building 28 of service conduit; sidewalk of north capitol street north of "p" street, n. W. As indicated on the attached prints. Wr #33948 tcp-custom cut 327853 stephen j. Park (202) 388-2573 sjpark@pepco. Com (g curtis) Date: September 18, 2013 Contractor: Pepco Permit status: Permit expired | Expiration date: November 21, 2013 | Permit id: Pa84739 | |||||
SCORE 99 Fixture; fence to 42" (open design) Contractor: Douglas Development Permit status: 2 | Expiration date: November 18, 2016 | Permit id: 0 | |||||
SCORE 95 15 n cap st nw, 3x3 s/w cut o/m 48 w c/l n cap st nw and 38 n c/l p st nw per 730, permit no: 689047 wr no: 2823171 Date: August 30, 2016 Contractor: Wash Gas And Light Co Permit type: Excavation; gas connection (trench) | Permit status: Permit expired | Expiration date: October 28, 2016 | Permit id: Pa183009 | |||||
SCORE 96 Paving; leadwalk repair replace existing, fixture; bike rack(s), fixture; fence to 42" (open design), landscaping; tree planting, projections; awning(s), projections; bay window(s), projections; window well(s) Contractor: Will Teass Permit status: 1 | Expiration date: November 29, 2017 | Permit id: 0 | |||||
SCORE 70 Construction staging area Permit status: Resubmit | Expiration date: February 27, 2018 | Permit id: 0 | |||||
SCORE 95 In alley , behind 1400blk & 1500blk of north capitol st nw. Between florida ave nw & o st nw. Lashed to existing cable. Approx 1043 ft of aerial fiber cable total. Date: May 8, 2014 Contractor: Verizon Permit type: Over head work; string telecom wire/fiber | Permit status: Permit expired | Expiration date: September 16, 2014 | Permit id: Pa95230 | |||||
SCORE 96 New combined lot at 15 and 1512 north capitol (currently working through subdivision). Alteration of two, two story + cellar, row-houses into 5 stories + cellar multifamily building. Demolition of existing lead walks and bay projections at 15 & 1512 north capitol. Replace leadwalk at 15 north capitol. New bike rack adjacent to lead walk. New awning at front entry. New window wells and rails. New bay projection from grade to 4th floor. New tree planting in front of building. Contractor: Will Teass Permit status: Approved (pending payment | Expiration date: November 29, 2017 | Permit id: 0 | |||||
SCORE 95 Construction staging area Date: October 11, 2013 Contractor: Pepco Holdings Inc Permit status: Permit expired | Expiration date: November 26, 2013 | Permit id: Pa10117837 | |||||
SCORE 70 Construction staging area Date: September 27, 2016 Permit status: Permit expired | Expiration date: January 13, 2017 | Permit id: Pa10333474 | |||||
SCORE 95 Construction staging area Date: March 16, 2017 Contractor: Wash Gas And Light Co Permit status: Permit expired | Expiration date: May 15, 2017 | Permit id: Pa10380904 | |||||
SCORE 70 Construction staging area Date: August 8, 2017 Permit status: Permit expired | Expiration date: August 31, 2017 | Permit id: Pa10379020 | |||||
SCORE 70 Construction staging area Permit status: Resubmit | Expiration date: February 27, 2018 | Permit id: 0 |