SCORE 64 New foundations to support storage tank, dryer, compressor for new compressed natural gas fueling station; 8 hi fence Applicant: Clean Energy/monica Ultreras | Permit status: Permisud | Expiration date: September 30, 2011 | Permit id: 1004140052 | |||||
SCORE 64 Install k-rail and additonal compressed natural gas (cng) time fill post (6) outlets Date: June 22, 2015 Contractor: Nicosia Consulting International Ll Applicant: Nicosia Consulting Int Llc | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: June 21, 2016 | Permit id: 1506220059 | |||||
SCORE 72 Electrical for rain water valve and diversion system. Supplemental permit Date: January 2, 2013 Contractor: Sals Plumbing Inc Applicant: Martin Joseph Vernola | Permit status: Finaled | Completion date: January 24, 2013 | Expiration date: January 2, 2014 | Permit id: 1301020006 | |||||
SCORE 64 Plumbing for k-rail & compressed natural gas (cng) time fill post Date: December 30, 2015 Contractor: Nicosia Consulting International Ll Applicant: Nicosia Consulting Int Llc | Permit status: Permisud | Expiration date: December 29, 2016 | Permit id: 1512300002 | |||||
SCORE 64 Upgrade at cng station Date: August 6, 2012 Contractor: Nicosia Contracting International Applicant: Clean Energy/monica Ultreras | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: August 6, 2013 | Permit id: 1207180039 | |||||
SCORE 98 Construction of canopy at fueling stations 60x Applicant: Dan Lingle | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: April 20, 2016 | Permit id: 1410230058 | |||||
SCORE 56 Construciton of canopy at wash area 18x24 Applicant: Daniel Lingle | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: April 20, 2016 | Permit id: 1410230059 | |||||
SCORE 72 Relocate rain water valve and diversion rainswitch. Date: December 19, 2012 Contractor: Sals Plumbing Inc Applicant: Martin Joseph Vernola | Permit status: Finaled | Completion date: January 24, 2013 | Expiration date: December 19, 2013 | Permit id: 1212190007 | |||||
SCORE 66 Install underground infiltration storm chambers Date: April 21, 2015 Contractor: Es Engineering Inc Applicant: Environ Strategy | Permit status: Permisud | Expiration date: April 20, 2016 | Permit id: 1406170001 | |||||
SCORE 64 Install k-rail and additonal compressed natural gas (cng) time fill post (10) outlets Date: December 30, 2015 Contractor: Nicosia Consulting International Ll Applicant: Nicosia Consulting Int Llc | Permit status: Permisud | Expiration date: December 29, 2016 | Permit id: 1512300006 | |||||
SCORE 64 Electrical powering of fueling system Date: August 6, 2012 Contractor: Nicosia Contracting International Applicant: John Knight | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: August 6, 2013 | Permit id: 1205150011 | |||||
SCORE 72 Electrical for rain water valve and diversion system. Date: December 19, 2012 Contractor: Sals Plumbing Inc Applicant: Martin Joseph Vernola | Permit status: Permisud | Expiration date: December 19, 2013 | Permit id: 1212190005 | |||||
SCORE 64 Upgrade existing shop for compressed natural gas fueled trks currently in use for liquid fueled trash refuse trucks. Planning approval rpp20100441. Date: December 2, 2010 Contractor: Ws Construction Co Applicant: Tom Mitchell | Permit status: Permisud | Expiration date: December 2, 2011 | Permit id: 1012020023 | |||||
SCORE 64 Plumbing for k-rail & compressed natural gas (cng) Date: June 22, 2015 Contractor: Nicosia Consulting International Ll Applicant: Nicosia Consulting Int Llc | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: June 21, 2016 | Permit id: 1506220032 | |||||
SCORE 64 Upgrade existing shop for compressed natural gas fueled trks currently in use for liquid fueled trash refuse trucks. Planning approval rpp20100441. Applicant: Tom Mitchell | Permit status: Permisud | Expiration date: December 2, 2011 | Permit id: 1009020072 | |||||
SCORE 74 Installation of phase ii eur healy equipment Applicant: Cline Mike | Permit status: Permisud | Expiration date: November 3, 2009 | Permit id: 905070035 | |||||
SCORE 99 C/o & install new 24 gage zincalume cornigated metal 144sqs Applicant: Ace Roofing Systems | Permit status: Permisud | Expiration date: April 2, 2001 | Permit id: 10030032 | |||||
SCORE 99 C o & install new 24 gage zincalume cornigated metal 144sqs Applicant: Ace Roofing Systems | Permit status: Permisud | Expiration date: April 2, 2001 | Permit id: 10030032 | |||||
SCORE 69 Installation of phase ii eur healy equipment Applicant: Cline Mike | Permit status: Permisud | Expiration date: November 3, 2009 | Permit id: 905070035 | |||||
SCORE 59 New foundations to support storage tank, dryer, compressor for new compressed natural gas fueling station; 8 hi fence Applicant: Clean Energy/monica Ultreras | Permit status: Permisud | Expiration date: September 30, 2011 | Permit id: 1004140052 | |||||
SCORE 67 Construction of canopy at fueling stations 60x Applicant: Dan Lingle | Permit status: Finaled | Completion date: December 14, 2015 | Expiration date: April 20, 2016 | Permit id: 1410230058 | |||||
SCORE 65 Electrical for rain water valve and diversion system. Date: December 19, 2012 Contractor: Sals Plumbing, Inc Applicant: Martin Joseph Vernola | Permit status: Permisud | Expiration date: December 19, 2013 | Permit id: 1212190005 | |||||
SCORE 65 Electrical for rain water valve and diversion system. Supplemental permit Date: January 2, 2013 Contractor: Sals Plumbing, Inc Applicant: Martin Joseph Vernola | Permit status: Finaled | Completion date: January 24, 2013 | Expiration date: January 2, 2014 | Permit id: 1301020006 | |||||
SCORE 56 Install underground infiltration storm chambers Date: April 21, 2015 Contractor: Es Engineering, Inc Applicant: Environ Strategy | Permit status: Permisud | Expiration date: April 20, 2016 | Permit id: 1406170001 | |||||
SCORE 65 Relocate rain water valve and diversion rainswitch. Date: December 19, 2012 Contractor: Sals Plumbing, Inc Applicant: Martin Joseph Vernola | Permit status: Finaled | Completion date: January 24, 2013 | Expiration date: December 19, 2013 | Permit id: 1212190007 | |||||
SCORE 64 Electrical to install time fill compressed natural gas fueling station on existing property. Date: September 30, 2010 Contractor: Vant Hul Construction Inc Applicant: Ultreras Monica | Permit status: Permisud | Expiration date: September 30, 2011 | Permit id: 1004050009 | |||||
SCORE 59 Electrical to install time fill compressed natural gas fueling station on existing property. Date: September 30, 2010 Contractor: Vant Hul Construction, Inc Applicant: Ultreras Monica | Permit status: Permisud | Expiration date: September 30, 2011 | Permit id: 1004050009 |