Preparation area canopy. Date: May 1, 2001 Value: $25,000 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0105010044 | |||||
Canopy over paint spray booth. Date: May 1, 2001 Value: $25,000 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0105010047 | |||||
Supports for (2) new fans on roof. Date: September 6, 2001 Value: $2,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: September 26, 2002 | Permit id: 0109060021 | |||||
SCORE 93 Install pallet racks. Applicant: Davis Bacon Material Handling | Permit status: Finaled | Completion date: November 18, 2005 | Permit id: 0410070084 | |||||
SCORE 98 New 13,974 sq ft office/warehouse/mezzanine,v-n,b,s-1/f-2. Applicant: Jack Lovell / Michael Johnson | Permit status: Finaled | Completion date: November 26, 2008 | Permit id: 0607070059 | |||||
Demolish exist commercial bldgs Date: October 25, 2006 Value: $500 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0610250090 | |||||
SCORE 98 T. I. 1st floor office and mezzanine office above 5,0 sq ft 1st floor,5,0 sq ft mezzanine Applicant: Mike Avalos | Permit status: Finaled | Completion date: November 26, 2008 | Permit id: 0803070029 | |||||
SCORE 98 Convert 2nd floor mezz area to light storage; retrofit ten dock levelers & leveling pits Applicant: Avalos,Mike | Permit status: Finaled | Completion date: December 3, 2008 | Permit id: 0810140030 | |||||
SCORE 80 Installation of storage racks. Applicant: Robert Gefring | Permit status: Finaled | Completion date: December 3, 2008 | Permit id: 0811060031 | |||||
SCORE 70 Install 30. 24 kw (dc) pv solar system on a commerical bldg. (roof top). Applicant: Jing Chen | Permit status: Permisud | Permit id: 1012290040 | |||||
SCORE 96 Install 76. 6 kw (dc) pv solar system on a commerical bldg. (roof top). Applicant: Jing Chen | Permit status: Permisud | Permit id: 1204030056 | |||||
SCORE 67 T. I. For adding storage,cubicle,restrooms inside of (e) warehouse. No mep work at new storage cubicle Applicant: Sungrub Jung | Permit status: Finaled | Completion date: December 24, 2014 | Permit id: 1411040016 | |||||
SCORE 98 Electrical fixtures Date: November 30, 2000 Contractor: Coast Electric Applicant: Coast Electric | Permit status: Finaled | Completion date: January 17, 2001 | Permit id: 0011300027 | |||||
SCORE 100 Electrical permit Date: November 19, 2001 Contractor: Advanced Contractors Applicant: Advanced Contractors | Permit status: Finaled | Completion date: November 21, 2001 | Permit id: 0111190021 | |||||
SCORE 100 Install temporary power pole. Date: March 21, 2007 Contractor: Power Plus Applicant: Power Plus | Permit status: Finaled | Completion date: June 7, 2007 | Permit id: 0703210044 | |||||
SCORE 98 Electrical permit. Date: September 21, 2007 Contractor: Mammoth Electric Inc Applicant: Jimenez Art | Permit status: Permisud | Permit id: 0709210007 | |||||
SCORE 82 T. I. 1st floor office and mezzanine office above 5,0 sq ft 1st floor,5,0 sq ft mezzanine Date: October 6, 2008 Contractor: Mammoth Electric Applicant: Rodriguez,Ronald | Permit status: Finaled | Completion date: November 26, 2008 | Permit id: 0810060029 | |||||
SCORE 82 Electrical permit. Date: December 8, 2008 Contractor: Mammoth Electric Applicant: Rodriguez,Ronald | Permit status: Permisud | Permit id: 0812080027 | |||||
SCORE 70 Install roof mounted solar pv at 30. 24 kw Date: February 10, 2011 Contractor: Aca Technology Inc Applicant: Song Kailin | Permit status: Permisud | Permit id: 1011220027 | |||||
SCORE 96 Install 76. 6 kw (dc) pv solar system on a commerical bldg. (roof top). Date: April 3, 2012 Contractor: Abc Solar Inc Applicant: Jing Chen | Permit status: Permisud | Permit id: 1201120045 | |||||
SCORE 93 Install 2 new panels,transformers,outlets Date: December 10, 2014 Contractor: 2 And 3 Electric Applicant: Chon Phil | Permit status: Finaled | Completion date: December 24, 2014 | Permit id: 1412080023 | |||||
SCORE 76 Conveyor motors wiring Date: December 16, 2014 Contractor: Ingalls Conveyors Applicant: Ingalls,Steve | Permit status: Finaled | Completion date: December 24, 2014 | Permit id: 1412160004 | |||||
SCORE 98 Grading permit,39,394 cubic yards. Date: February 9, 2007 Contractor: Norm Wilson And Sons Inc Applicant: Thienes Engineering | Permit status: Finaled | Completion date: September 9, 2008 | Permit id: 0606210001 | |||||
SCORE 87 Mechanical permit Date: February 9, 2000 Contractor: Modern Air Conditioning Co Applicant: Modern Air Conditioning | Permit status: Finaled | Completion date: February 10, 2000 | Permit id: 0002090014 | |||||
SCORE 98 Mechanical permit. Date: June 27, 2006 Contractor: Thermalair Inc Applicant: Sanders Bill B | Permit status: Permisud | Permit id: 0606270015 | |||||
SCORE 86 Mechanical permit Date: June 14, 2007 Contractor: Thermal Air Inc Applicant: Bill Sanders | Permit status: Finaled | Completion date: December 3, 2008 | Permit id: 0706140035 | |||||
SCORE 86 Mechanical permit. Date: November 12, 2008 Contractor: Thermal Air Inc Applicant: Bill Sanders | Permit status: Finaled | Completion date: December 3, 2008 | Permit id: 0811120006 | |||||
SCORE 100 Plumbing permit,(roof drain) 6". Date: September 13, 2007 Contractor: American Contractors Applicant: American Contractors | Permit status: Finaled | Completion date: November 26, 2008 | Permit id: 0709130028 | |||||
SCORE 98 New restrooms for bl 0803080029 Date: October 9, 2008 Contractor: Norm Wilson And Sons Inc Applicant: Mike Avalos | Permit status: Finaled | Completion date: November 26, 2008 | Permit id: 0810090012 | |||||
SCORE 99 New mens and womens ada restrooms Date: November 26, 2014 Contractor: Min Lee Applicant: Lee,Min | Permit status: Finaled | Completion date: December 24, 2014 | Permit id: 1411260017 | |||||
SCORE 100 Sewer permit. Date: September 13, 2007 Contractor: American Contractors Applicant: American Contractors | Permit status: Finaled | Completion date: October 23, 2008 | Permit id: 0709130011 | |||||
SCORE 100 Tap and saddle. Date: September 24, 2007 Contractor: American Contractors Applicant: American Contractors | Permit status: Finaled | Completion date: October 23, 2008 | Permit id: 0709240006 |