Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 56 Renovate existing bath room, tiles,sink,toilet,bathtub for shower on the 3rd floor Permit type: Addition/alteration | Completion date: March 4, 2013 | Current use: Two-family | Parcel: 1093614 | |||||
SCORE 93 Demo entire kitchen including removing flooring. All removed debris will be disposed. Frame entire kitchen, framing includes all fire stopping, hangers and blocking. Spray foam entire kitchen with open cell insulation, install all new blueboard on all walls that were removed. Install tile in kitchen, install 6 recessed lights with fire hats, under cabinet lighting, outlets and switches. Rough to finish plumbing for 1 kitchen sink, d. W. Fridge and oven. Permit type: Addition/alteration | Completion date: March 2, 2016 | Current use: One-family | Parcel: 1093612 |