SCORE 96 New 35 sq. Ft. Building; 5m emc chamber project. Date: May 1, 2013 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B13-0713 | |||||
SCORE 96 Install clean room within existing building (4) lower. Date: March 27, 2013 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B13-0294 | |||||
SCORE 99 Bldg 4 upgrades - conference room remodel, additional training room, coffee stations & restroom upgrade in upper & lower. Date: May 15, 2012 Contractor: Rudolph And Sletten Inc Permit status: Finaled | Permit id: B12-0676 | |||||
SCORE 96 Remodel existing conference room for new tenant Date: November 3, 2014 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B14-3540 | |||||
SCORE 100 Demolition and replacement of existing gravity drain process waste stream piping to the facility waste treatment plant, utilized for neutralization prior to discharge to the potw. Two new waste treatment tanks will be installed three existing waste treat Date: January 6, 2015 Contractor: Peterson Mechanical Inc Permit status: Issued | Permit id: B14-4441 | |||||
SCORE 56 Seismic upgrades of equipment and chemical tanks per cupa. ( central plant bdlg & bldg "2 doc" area) Date: March 12, 2015 Contractor: Buff Jacob Permit status: Issued | Permit id: B15-0484 | |||||
SCORE 96 Remove existing and construct sheet rocked separation wall. Date: August 8, 2012 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B12-2680 | |||||
SCORE 96 Dining room beautification - per plan - accessibility compliant per randy everson - plan approval per randy everson Date: November 25, 2014 Contractor: Kirby Construction Company Inc Permit status: Issued | Permit id: B14-4765 | |||||
SCORE 96 Remove 3 existing receptacles/breakers and replace with new ev charging stations and add 7 new additional including (1) handicap accessible - all in main parking lot Date: March 2, 2015 Contractor: Joe Lunardi Electric Inc Permit status: Issued | Permit id: B15-0833 | |||||
SCORE 56 Replace entry sign with new logo name keysight technologies. Date: June 5, 2014 Contractor: Kirby Construction Company Inc Johnson Jared Permit status: Issued | Permit id: B14-2106 | |||||
SCORE 96 Install solvent waste tank and exit door in central plant. Date: October 17, 2013 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B13-3805 | |||||
SCORE 96 Seismic upgrades of equipment and chemical tanks per cupa. ( central plant bdlg & bldg "2 doc" area) Date: February 5, 2015 Contractor: Kirby Construction Company Inc Permit type: Non-residential addition-alteration | Permit status: Finaled | Current use: Non-residential | Permit id: B15-0484 | Parcel: 173010001 | |||||
SCORE 100 Replacing storage tank Permit type: Non-residential addition-alteration | Permit status: Issued | Current use: Non-residential | Permit id: B15-1332 | Parcel: 173010001 | |||||
SCORE 96 Interior remodel of 1 mens and 1 womens restroom facilities at the 2-3 link of keysight technologies (located on lower floor of bldg 2 and upper floor of bldg 3) Date: April 14, 2015 Contractor: Kirby Construction Company Inc Permit type: Non-residential addition-alteration | Permit status: Finaled | Current use: Non-residential | Permit id: B15-1535 | Parcel: 173010001 | |||||
SCORE 96 Remove 3 existing receptacles breakers and replace with new ev charging stations and add 7 new additional including (1) handicap accessible - all in main parking lot Date: March 2, 2015 Contractor: Joe Lunardi Electric Inc Permit type: Non-residential addition-alteration | Permit status: Finaled | Current use: Non-residential | Permit id: B15-0833 | Parcel: 173670022 | |||||
SCORE 56 Repair wiring to water heater element. Date: October 2, 2014 Contractor: Lafrancois Scott Permit status: Finaled | Permit id: B14-3974 | |||||
SCORE 96 Convert existing two offices into one new. Applicant indicates pot is compliant with current accessibility requirements. No hardship document needed. Permit type: Non-residential addition-alteration | Permit status: Finaled | Current use: Non-residential | Permit id: B15-1416 | Parcel: 173010001 | |||||
SCORE 96 Convert open office to exec suite, private offices and conference rooms. Date: January 14, 2014 Contractor: Kirby Construction Company Inc Permit status: Issued | Permit id: B14-0151 | |||||
SCORE 96 Interior commercial improvements. Converting office area to board rm, dinning rm, kitchen and meeting rms. - architect is claiming all required accessibility elements serving this area of renovation meet, or will be upgraded to meet current accessibility Date: April 21, 2014 Contractor: Kirby Construction Company Inc Permit status: Finaled | Permit id: B14-0780 |