Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 73 X temporary tent to be used on july 9,18,23 and august 1,6,15,20,29 (8) events,temporary electrical Date: July 7, 2009 Contractor: Triple A Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 29, 2009 | Permit id: 0907070044 | |||||
SCORE 82 Temporary electrical power for sound for musical event july 17,22,31 aug. 5,14,19,28. On site person martin class cell 6268831627 Date: July 13, 2011 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: September 7, 2011 | Permit id: 1107130046 | |||||
SCORE 73 X temporary tent to be used on july 9,18,23 and august 1,6,15,20,29 (8) events Date: July 7, 2009 Contractor: Triple A Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 29, 2009 | Permit id: 0907070002 | |||||
SCORE 73 X temporary tent to be used on july 8,17,22,31 and august 5,14,19,28 (8) events Date: July 6, 2010 Contractor: Triple A Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 28, 2010 | Permit id: 1007060005 | |||||
SCORE 73 X temporary tent to be used on july 7,16,21, and august 4,13,18,27 (8) events Date: June 22, 2011 Contractor: Triple A Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: September 7, 2011 | Permit id: 1106220003 | |||||
SCORE 56 Temp electrical service boat show 5/15 thru 5/23/20 Date: May 12, 2000 Contractor: G E S Exposition Services Inc Applicant: G E S Exposition Services | Permit status: Finaled | Completion date: May 26, 2000 | Permit id: 0005120014 | |||||
SCORE 59 Outlet Date: June 2, 2004 Contractor: Ruder Electrical Contracting Applicant: Ruder Electrical Contracting* | Permit status: Permisud | Permit id: 0406020027 | |||||
SCORE 67 Summer concerts,install generator (1) 200a panel,120v single phase. Date: July 1, 2004 Contractor: Auntie Em Creative Consultants Applicant: Love Catrina M | Permit status: Permisud | Permit id: 0407010066 | |||||
SCORE 97 Electric generators for boat show Date: January 10, 2005 Contractor: Dolin Electric Inc Applicant: Dolin Electric* | Permit status: Finaled | Completion date: January 17, 2005 | Permit id: 0501100016 | |||||
SCORE 67 Summer concerts series - 30kw deisel powered generator,75 #2 guage entrmnt cable;breaker box w/(12)20amp breakers & duplex outlets;(2) amp circuits,12 guage stow Date: June 28, 2005 Contractor: Auntie Em Creative Consultants Applicant: Love Katrina M | Permit status: Finaled | Completion date: June 17, 2008 | Permit id: 0506230031 | |||||
SCORE 74 Temporary wiring for boat show Date: May 15, 2006 Contractor: Ges Exposition Services Applicant: Ges Exposition Services* | Permit status: Finaled | Completion date: June 17, 2008 | Permit id: 0605150026 | |||||
SCORE 98 Electrical for sound system Date: July 12, 2006 Contractor: William K Geist Applicant: Event Power Associates* | Permit status: Finaled | Completion date: June 17, 2008 | Permit id: 0607120022 | |||||
SCORE 74 Temp electrical services for mdr boat show Date: May 11, 2007 Contractor: Ges Exposition Services Applicant: Ges Exposition Services | Permit status: Finaled | Completion date: May 20, 2007 | Permit id: 0705100038 | |||||
SCORE 98 Electrical for sound system Date: July 9, 2007 Contractor: William K Geist Applicant: Event Power Associates* | Permit status: Finaled | Completion date: July 12, 2007 | Permit id: 0707090032 | |||||
SCORE 74 Temporary electrical service for mdr boat show 6/12 to 6/15 Date: June 5, 2008 Contractor: Ges Exposition Services Applicant: Ges Exposition Services Inc | Permit status: Finaled | Completion date: June 12, 2008 | Permit id: 0806050014 | |||||
SCORE 82 Temp. Power for sound for musical concert july 10th. Ok to issue per r. Itani. Date: July 7, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: July 10, 2008 | Permit id: 0807070041 | |||||
SCORE 82 Temporary power for sound for musical concerts july 19,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140055 | |||||
SCORE 82 Temporary power for sound for musical concerts july 24,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140056 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 2,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140057 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 7,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140058 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 16,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140059 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 21,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140060 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 30,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807140061 | |||||
SCORE 56 1 stage Date: June 15, 2000 Contractor: Shakespeare Festival Applicant: Shakespeare Festival | Permit status: Finaled | Completion date: June 20, 2000 | Permit id: 0006150001 | |||||
SCORE 70 Temporary tent 40x60x for nine weeks starting 7-8 to 8-29-04 Date: July 1, 2004 Contractor: American Rent All Applicant: Catrina Love | Permit status: Finaled | Completion date: June 28, 2010 | Permit id: 0407010001 | |||||
SCORE 65 Temporary tents - 1-120x 100,2-10x 20,2-20x Date: January 6, 2005 Contractor: A1 Events And Party Rentals Applicant: A-1 Events & Party Rentals* | Permit status: Finaled | Completion date: January 17, 2005 | Permit id: 0501040001 | |||||
SCORE 70 Tent for musicians Date: July 6, 2005 Contractor: Addco Party Rentals Applicant: Addco Party Rentals | Permit status: Finaled | Completion date: June 17, 2008 | Permit id: 0502240002 | |||||
SCORE 81 Temporary tent 40x 60for music concerts Date: July 16, 2008 Contractor: Aaa Rents And Events Inc Applicant: Aaa Rents* | Permit status: Finaled | Completion date: May 5, 2009 | Permit id: 0807160002 | |||||
SCORE 98 Electrical for tent to be used on july 10,19,24,2014; august 2,7,16,21, and 30, 2014; summer concert series. Date: July 3, 2014 Contractor: William K Geist Applicant: William K Geist | Permit status: Permisud | Expiration date: July 3, 2015 | Permit id: 1407030049 | |||||
SCORE 81 X temporary tent to be used on july 7, 2012 to sept. 1, 2012 summer concert series. Concert dates 7 12, 21,26, 8 4,9,18,23, & 9 1 12 Date: June 19, 2012 Contractor: Aaa Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: December 16, 2012 | Permit id: 1206190001 | |||||
SCORE 98 X temporary tent to be used on july 8,17,22,23,and august 5,14,19,& 28 (8 events), temp electrical power sound for musical concert. Date: July 6, 2010 Contractor: William K Geist Applicant: William K Geist | Permit status: Finaled | Completion date: August 28, 2010 | Expiration date: July 6, 2011 | Permit id: 1007060042 | |||||
SCORE 81 X temporary tent to be used on july 2,11,16,25,30; august 8,13,22, 2015; summer concert series. Date: June 29, 2015 Contractor: Aaa Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: December 26, 2015 | Permit id: 1506290002 | |||||
SCORE 81 X temporary tent to be used on july 10,19,24,2014; august 2,7,16,21, and 30, 2014; summer concert series. Date: July 2, 2014 Contractor: Aaa Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: December 29, 2014 | Permit id: 1407020001 | |||||
SCORE 81 X temporary tent to be used on july 11,20, 25,2013 august 3,8,17,22, and 31, 2013; summer concert series. Date: June 27, 2013 Contractor: Aaa Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: December 24, 2013 | Permit id: 1306270006 | |||||
SCORE 98 Special event - concert in the park (temporary)july 2,11,16, 25, & 30; august 8,13,& 22, 2015. Date: July 15, 2015 Contractor: William K Geist Applicant: William Geist | Permit status: Permisud | Expiration date: July 14, 2016 | Permit id: 1507150069 | |||||
SCORE 98 Electrical permit for temporary tent,july 11,20,25,2013 and august 3,8,17,22, and 31, 2013 summer concert series Date: July 16, 2013 Contractor: William K Geist Applicant: William K Geist | Permit status: Permisud | Expiration date: July 16, 2014 | Permit id: 1307160062 | |||||
SCORE 98 Electrical permit for temporary ten7,july 8,17,22, & 31,2012 and august 5,14,19, 28, 2012. Date: June 28, 2012 Contractor: William K Geist Applicant: William K Geist | Permit status: Finaled | Completion date: August 30, 2012 | Expiration date: June 28, 2013 | Permit id: 1206280053 | |||||
SCORE 82 Temporary electrical power for sound for musical event july 17,22,31 aug. 5,14,19,28. On site person martin class cell 6268831627 Date: July 13, 2011 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: September 7, 2011 | Expiration date: July 12, 2012 | Permit id: 1107130046 | |||||
SCORE 73 X temporary tent to be used on july 9,18,23 and august 1,6,15,20,29 (8) events, temporary electrical Date: July 7, 2009 Contractor: Triple A Rents And Events Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 29, 2009 | Expiration date: January 3, 2010 | Permit id: 907070044 | |||||
SCORE 81 Temporary tent 30x40x (subject to field inspection) permit for tent only. Applicant: Jimmy Paola | Permit status: Permisud | Expiration date: March 30, 2016 | Permit id: 1503310014 | |||||
SCORE 95 Transient dock replacement on both land and seaside. Guide piles, gangway/platform, and floating docks construction sha ll not begin until the deferral submittals for these items a Engineer: Noble Consultants, Inc. | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207260097 | |||||
SCORE 59 Outlet Date: June 2, 2004 Contractor: Ruder Electrical Contracting Applicant: Ruder Electrical Contracting | Permit status: Permisud | Expiration date: November 29, 2004 | Permit id: 406020027 | |||||
SCORE 67 Summer concerts, install generator + (1) 200a panel, 120v single phase. Date: July 1, 2004 Contractor: Auntie Em Creative Consultants Engineer: Martin Claes | Applicant: Love Catrina M | Permit status: Permisud | Expiration date: December 28, 2004 | Permit id: 407010066 | |||||
SCORE 82 Temp. Power for sound for musical concert july 10th. Ok to issue per r. Itani. Date: July 7, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: July 10, 2008 | Expiration date: January 3, 2009 | Permit id: 807070041 | |||||
SCORE 82 Temporary power for sound for musical concerts july 19,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140055 | |||||
SCORE 82 Temporary power for sound for musical concerts july 24,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140056 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 2,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140057 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 7, 2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140058 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 16,2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140059 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 21, 2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140060 | |||||
SCORE 82 Temporary power for sound for musical concerts aug 30, 2008 ok to issue per r. Itani. Date: July 14, 2008 Contractor: William Geist Applicant: Geist William K | Permit status: Finaled | Completion date: May 5, 2009 | Expiration date: January 10, 2009 | Permit id: 807140061 | |||||
SCORE 65 Temporary tents - 1-120x 100,2-10x 20, 2-20x Date: January 6, 2005 Contractor: A1 Events And Party Rentals Applicant: A-1 Events & Party Rentals | Permit status: Finaled | Completion date: January 17, 2005 | Expiration date: July 5, 2005 | Permit id: 501040001 | |||||
SCORE 70 Tent for musicians Date: July 6, 2005 Contractor: Addco Party Rentals Applicant: Addco Party Rentals | Permit status: Finaled | Completion date: June 17, 2008 | Expiration date: January 2, 2006 | Permit id: 502240002 | |||||
SCORE 100 Modification of existing gangway to meet ada compliance Engineer: X | Applicant: Ball Robert | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: May 1, 2004 | Permit id: 305070077 | |||||
SCORE 100 Modification of existing gangway to meet ada compliance Engineer: X | Applicant: Ball Robert | Permit status: Finaled | Completion date: January 24, 2011 | Expiration date: June 6, 2004 | Permit id: 306030022 | |||||
SCORE 95 X x temporary tent Applicant: Dunnigan Harold | Permit status: Finaled | Completion date: March 11, 2004 | Expiration date: July 10, 2004 | Permit id: 307090021 | |||||
SCORE 95 Ada upgrade and seismic retrofit to whole building. Engineer: Wayne C. Siu, Aia | Applicant: Siu Wayne | Permit status: Permisud | Expiration date: February 12, 2006 | Permit id: 407280075 | |||||
SCORE 95 Aluminum ramp system manufacturer Applicant: Noel Corpuz | Permit status: Finaled | Completion date: February 3, 2006 | Expiration date: July 23, 2006 | Permit id: 507280009 | |||||
SCORE 99 Convert existing store room to unisex toilet room. Applicant: Siu Wayne | Permit status: Finaled | Completion date: October 24, 2008 | Expiration date: March 8, 2009 | Permit id: 805270061 | |||||
SCORE 100 Beam and trellis removal Applicant: Puno, Macansantos Ferdinand | Permit status: Finaled | Completion date: November 2, 2010 | Expiration date: July 7, 2011 | Permit id: 1004210086 | |||||
SCORE 95 Ada upgrade & seismic retrofit Engineer: Gkkworks | Applicant: Tsang Thomas | Permit status: Permisud | Expiration date: June 12, 2013 | Permit id: 1010120009 | |||||
SCORE 56 Installation of 30kw diesel generator + (1) 200a panel, 120v single phase. Date: July 9, 2003 Contractor: Harold Dunnigan Applicant: Dunnigan Harold | Permit status: Finaled | Completion date: August 29, 2003 | Expiration date: January 5, 2004 | Permit id: 307090016 | |||||
SCORE 62 Install (1) 800amp, (1) 400amp & (3) 200amp panels, water heaters etc. Job no. B205103 Date: March 9, 2005 Contractor: A C U Electric Engineer: Wayne C. Siu, Aia | Applicant: Pak Moon | Permit status: Initiate | Expiration date: September 5, 2005 | Permit id: 503090006 | |||||
SCORE 99 Add sce meter and seperate building from docks Date: July 14, 2008 Contractor: Comet Electric Applicant: Toni Wright | Permit status: Finaled | Completion date: October 15, 2008 | Expiration date: January 10, 2009 | Permit id: 807140001 | |||||
SCORE 99 Convert existing store room to unisex toilet room. Date: September 17, 2008 Contractor: Comet Electric Applicant: Siu Wayne | Permit status: Finaled | Completion date: October 24, 2008 | Expiration date: March 16, 2009 | Permit id: 809170001 | |||||
SCORE 95 El for transient dock replacement Date: September 19, 2013 Contractor: Bellingham Marine Industries Inc Engineer: Intrinsic Engineering | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207300004 | |||||
SCORE 97 New hvac. Job no. B205103 Date: March 3, 2005 Contractor: Mek Air Tech Engineer: Wayne C. Siu, Aia | Applicant: Siu Wayne | Permit status: Finaled | Completion date: February 3, 2006 | Expiration date: August 30, 2005 | Permit id: 503030028 | |||||
SCORE 95 Me for ada upgrade & seismic retrofit Date: June 12, 2012 Contractor: New Creation Builders Engineer: Gkkworks | Applicant: Tsang Thomas | Permit status: Permisud | Expiration date: June 12, 2013 | Permit id: 1206070004 | |||||
SCORE 81 Water line repiping and fixture replacement. Job no. B205103 Date: March 3, 2005 Contractor: Line Tech Plumbing Engineer: Wayne C. Siu, Aia | Applicant: Siu Wayne | Permit status: Permisud | Expiration date: August 30, 2005 | Permit id: 503030031 | |||||
SCORE 99 Convert existing store room to unisex toilet room. Date: September 16, 2008 Contractor: Muirchase Plumbing Co Applicant: Siu Wayne | Permit status: Finaled | Completion date: October 24, 2008 | Expiration date: March 15, 2009 | Permit id: 809160038 | |||||
SCORE 95 Pl for transient dock replacement Date: September 19, 2013 Contractor: Bellingham Marine Industries Inc Engineer: Noble Consultants, Inc. | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207300003 | |||||
SCORE 56 Temp electrical service boat show 5 15 thru 5 23 20 Date: May 12, 2000 Contractor: G E S Exposition Services, Inc Applicant: G E S Exposition Services | Permit status: Finaled | Completion date: May 26, 2000 | Expiration date: November 8, 2000 | Permit id: 5120014 | |||||
SCORE 59 Electric generators for boat show Date: January 10, 2005 Contractor: Dolin Electric, Inc Applicant: Dolin Electric- | Permit status: Finaled | Completion date: January 17, 2005 | Expiration date: July 9, 2005 | Permit id: 501100016 | |||||
SCORE 74 Temporary electrical service for mdr boat show 6 12 to 6 15 Date: June 5, 2008 Contractor: Ges Exposition Services Applicant: Ges Exposition Services Inc | Permit status: Finaled | Completion date: June 12, 2008 | Expiration date: December 2, 2008 | Permit id: 806050014 | |||||
SCORE 70 Tent for musicians Date: July 6, 2005 Contractor: Addco Party Rentals Applicant: Addco Party Rentals | Permit status: Finaled | Completion date: June 17, 2008 | Expiration date: January 2, 2006 | Permit id: 502240002 | |||||
SCORE 98 X x temporary tent Applicant: Dunnigan Harold | Permit status: Finaled | Completion date: March 11, 2004 | Expiration date: July 10, 2004 | Permit id: 307090021 | |||||
SCORE 100 Ada upgrade and seismic retrofit to whole building. Engineer: Wayne C. Siu, Aia | Applicant: Siu Wayne | Permit status: Permisud | Expiration date: February 12, 2006 | Permit id: 407280075 | |||||
SCORE 100 Aluminum ramp system manufacturer Applicant: Noel Corpuz | Permit status: Finaled | Completion date: February 3, 2006 | Expiration date: July 23, 2006 | Permit id: 507280009 | |||||
SCORE 99 Beam and trellis removal Applicant: Puno, Macansantos Ferdinand | Permit status: Finaled | Completion date: November 2, 2010 | Expiration date: July 7, 2011 | Permit id: 1004210086 | |||||
SCORE 98 El for transient dock replacement Date: September 19, 2013 Contractor: Bellingham Marine Industries, Inc Engineer: Intrinsic Engineering | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207300004 | |||||
SCORE 98 Pl for transient dock replacement Date: September 19, 2013 Contractor: Bellingham Marine Industries, Inc Engineer: Noble Consultants, Inc. | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207300003 | |||||
SCORE 98 Transient dock replacement on both land and seaside. Guide piles, gangway platform, and floating docks construction sha ll not begin until the deferral submittals for these items a Engineer: Noble Consultants, Inc. | Applicant: Wong Paul | Permit status: Finaled | Completion date: May 1, 2014 | Expiration date: September 19, 2014 | Permit id: 1207260097 | |||||
SCORE 65 Temporary tent 30x40x (subject to field inspection) permit for tent only. Applicant: Jimmy Paola | Permit status: Permisud | Expiration date: March 30, 2016 | Permit id: 1503310014 | |||||
SCORE 71 X temporary tent to be used on july 9,18,23 and august 1,6,15,20,29 (8) events, temporary electrical Date: July 7, 2009 Contractor: Triple A Rents And Events, Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 29, 2009 | Expiration date: January 3, 2010 | Permit id: 907070044 | |||||
SCORE 71 X temporary tent to be used on july 9,18,23 and august 1,6,15,20,29 (8) events Date: July 7, 2009 Contractor: Triple A Rents And Events, Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 29, 2009 | Expiration date: January 3, 2010 | Permit id: 907070002 | |||||
SCORE 71 X temporary tent to be used on july 8,17,22,31 and august 5,14,19,28 (8) events Date: July 6, 2010 Contractor: Triple A Rents And Events, Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: August 28, 2010 | Expiration date: January 2, 2011 | Permit id: 1007060005 | |||||
SCORE 71 X temporary tent to be used on july 7,16,21, and august 4,13,18,27 (8) events Date: June 22, 2011 Contractor: Triple A Rents And Events, Inc Applicant: Ramiro Beltran | Permit status: Finaled | Completion date: September 7, 2011 | Expiration date: December 19, 2011 | Permit id: 1106220003 | |||||
SCORE 65 X temporary tent to be used on july 2,11,16,25,30; august 8,13,22, 2015; summer concert series. Date: June 29, 2015 Contractor: Aaa Rents And Events, Inc Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: December 26, 2015 | Permit id: 1506290002 | |||||
SCORE 67 Summer concerts series - 30kw deisel powered generator, 75 #2 guage entrmnt cable;breaker box w/(12)20amp breakers & duplex outlets;(2) amp circuits, 12 guage stow Date: June 28, 2005 Contractor: Auntie Em Creative Consultants Engineer: Martin Claes | Applicant: Love Katrina M | Permit status: Finaled | Completion date: June 17, 2008 | Expiration date: December 25, 2005 | Permit id: 506230031 | |||||
SCORE 86 Ada upgrade to existing office/training facility including elevator addition, restroom/shower upgrade, and shear wall upgrade. Engineer: Wayne C. Siu | Applicant: Wayne C. Siu | Permit status: Permisud | Expiration date: August 3, 2008 | Permit id: 802050024 | |||||
SCORE 93 Generator for temporary special event on 4/10/2015. Date: April 7, 2015 Contractor: Chester Wayne Zahn Applicant: Chet Zahn | Permit status: Finaled | Completion date: April 10, 2015 | Expiration date: April 6, 2016 | Permit id: 1504070004 | |||||
SCORE 86 Ada upgrade to existing office/training facility including elevator addition, restroom/shower upgrade, and shear wall upgrade. Date: February 5, 2008 Contractor: Sbs Corporation Engineer: Wayne C. Siu | Applicant: Wayne C. Siu | Permit status: Permisud | Expiration date: August 3, 2008 | Permit id: 802050011 | |||||
SCORE 95 New feeder cables to new elevator & sump pump. Additional branch circuits to new lighting & receptacle. Date: June 12, 2012 Contractor: New Creation Builders Engineer: Gkkworks | Applicant: Tsang Thomas | Permit status: Permisud | Expiration date: June 12, 2013 | Permit id: 1206070003 | |||||
SCORE 100 Special event - concert in the park (temporary)july 16,21, 30, august 4,13,16,18,and 27. Date: July 12, 2016 Contractor: D S J Electric Applicant: Estrada, David | Permit status: Permisud | Expiration date: July 12, 2017 | Permit id: 1607120064 | |||||
SCORE 65 X temporary tent with ada ramp for july 7,16,21,30, to august 4,13,18,27,2016 for summer concert series. Date: July 6, 2016 Contractor: Aaa Rents And Events, Inc Engineer: Aaa Rents And Events, Inc. | Applicant: Ramiro Beltran | Permit status: Permisud | Expiration date: January 2, 2017 | Permit id: 1607060001 | |||||
SCORE 98 T. I. To restrooms & change partial office to assembly occupa ncy (view deck). Finish installation of elevator. Engineer: Bob Freeman Ids Group | Applicant: Moon John | Permit status: Permisud | Expiration date: April 18, 2017 | Permit id: 1502030080 | |||||
SCORE 98 El for t. I. - remove existing power & electrical work. Install new power, lighting controls, conduits, wires, fused disconnect switches, and support hardware. Date: April 18, 2016 Contractor: Mtm Construction, Inc Engineer: Alberto De La Merced | Applicant: Moon John | Permit status: Permisud | Expiration date: April 18, 2017 | Permit id: 1406260075 | |||||
SCORE 98 Me for t. I. (office remodel) Date: April 18, 2016 Contractor: Mtm Construction, Inc Engineer: Peter Chen Spirit Engineering | Applicant: Moon John | Permit status: Permisud | Expiration date: April 18, 2017 | Permit id: 1406260040 | |||||
SCORE 98 Pl for t. I. (office remodel) Date: April 18, 2016 Contractor: Mtm Construction, Inc Engineer: Peter Chen Spirit Engineering | Applicant: Moon John | Permit status: Permisud | Expiration date: April 18, 2017 | Permit id: 1502100014 |