Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 87 Build new 2-story sfr with 2 bedrooms and 3 baths-3472 s. F. And attached garage-5 s. F.,porch-2 s. F.,patio-4 s. F., and deck-184 s. F. Applicant: Eide Steve | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 0901280007 | |||||
SCORE 87 Demolotion of existing sfr - 12 s. F. Applicant: Clearwater Building Corp | Permit status: Finaled | Completion date: December 23, 2009 | Permit id: 0912100019 | |||||
SCORE 87 New retaining wall 48" x 3 Applicant: Clearwater Building Corp | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 1001070002 | |||||
SCORE 95 Install roof mounted photovoltaic system. Applicant: Solano Nicole | Permit status: Finaled | Completion date: November 10, 2014 | Permit id: 1409040068 | |||||
SCORE 100 Build new pool and spa per l. A. County standard plan no. 26077-14. Applicant: Arce David | Permit status: Finaled | Completion date: November 7, 2014 | Permit id: 1401240002 | |||||
SCORE 99 Up-grade to 1 amp. Service Date: May 14, 2002 Contractor: Faultless Electric Applicant: Faultless Electric | Permit status: Finaled | Completion date: May 16, 2002 | Permit id: 0205140037 | |||||
SCORE 87 Temporary power pole Date: January 4, 2010 Contractor: Clearwater Building Corp Applicant: Clearwater Building Corp | Permit status: Finaled | Completion date: January 5, 2010 | Permit id: 1001040022 | |||||
SCORE 87 Electrical for new residence Date: April 26, 2010 Contractor: Clearwater Building Corp Applicant: Eide Steve | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 1004260016 | |||||
SCORE 95 Electrical for roof mounted photovoltaic system and 1 subpanel. Date: October 21, 2014 Contractor: Solarcity Corporation Applicant: Solano Nicole | Permit status: Finaled | Completion date: November 10, 2014 | Permit id: 1409040060 | |||||
SCORE 87 Grading for new 2 story sfr. Date: December 10, 2009 Contractor: Clearwater Building Corp Applicant: Ronnebeck Jerry | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 0904220001 | |||||
SCORE 87 Heating and cooling for new residence Date: April 26, 2010 Contractor: Clearwater Building Corp Applicant: Eide Steve | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 1004260008 | |||||
SCORE 87 Plumbing for new 2 story sfr. Date: January 28, 2010 Contractor: Clearwater Building Corp Applicant: Clearwater Building Corp | Permit status: Finaled | Completion date: September 15, 2010 | Permit id: 1001280007 | |||||
SCORE 87 Connect new residence to public sewer Date: April 26, 2010 Contractor: Clearwater Building Corp Applicant: Eide Steve | Permit status: Finaled | Completion date: August 12, 2010 | Permit id: 1004260003 |