SCORE 99 Install ups panel bypass switch to ats for emergency generator power only Date: April 23, 2007 Contractor: Dale Mather Permit type: Electrical permit | Permit status: Final | Completion date: June 4, 2007 | Expiration date: June 4, 2007 | Permit id: 2007-115753 Ep | |||||
SCORE 99 Interior nonstructural demo to existing commercial only 2nd floor Permit type: Building permit | Permit status: Active | Expiration date: March 20, 2017 | Permit id: 2016-111596 Bp | |||||
SCORE 100 Add eight amp circuits for computer server cabinets Date: January 27, 2015 Contractor: Robert Mclaughlin Permit type: Electrical permit | Permit status: Final | Completion date: February 11, 2015 | Expiration date: February 11, 2015 | Permit id: 2015-009625 Ep | |||||
SCORE 86 Install eight amp circuits with two data racks for computer server cabinets only Date: October 1, 2015 Contractor: Juan R Saucedo Permit type: Electrical permit | Permit status: Final | Completion date: October 28, 2015 | Expiration date: October 28, 2015 | Permit id: 2015-119166 Ep | |||||
SCORE 99 Interior remodel to existing admin office to create server room Applicant Phone: (512) 848-4538 | Permit type: Building permit | Permit status: Expired | Expiration date: January 27, 2016 | Permit id: 2015-079292 Bp | |||||
SCORE 86 Interior remodel to existing admin office to create server room all that was done was add power for a new liebert hvac unithyatt Date: July 7, 2015 Contractor: Juan R Saucedo Permit type: Electrical permit | Permit status: Final | Completion date: July 24, 2015 | Expiration date: July 24, 2015 | Permit id: 2015-079292 Ep | |||||
SCORE 93 Interior remodel to existing admin office to create server room Date: July 7, 2015 Contractor: John Mcrae Permit type: Mechanical permit | Permit status: Final | Completion date: July 31, 2015 | Expiration date: July 31, 2015 | Permit id: 2015-079292 Mp | |||||
SCORE 99 Interior remodel to existing admnbusprof office bldg b 1st floor Applicant: Bruce Moore | Applicant Phone: (512) 671-3473 | Permit type: Building permit | Permit status: Final | Completion date: December 20, 2012 | Expiration date: December 20, 2012 | Permit id: 2011-079109 Bp | |||||
SCORE 99 Interior remodel to existing admnbusprof office bldg b 2nd floor Applicant: Bruce Moore | Applicant Phone: (512) 671-3473 | Permit type: Building permit | Permit status: Final | Completion date: December 20, 2012 | Expiration date: December 20, 2012 | Permit id: 2011-0791 Bp | |||||
SCORE 99 Interior remodel to existing admnbusprof office bldg b 3rd floor Applicant: Bruce Moore | Applicant Phone: (512) 671-3473 | Permit type: Building permit | Permit status: Final | Completion date: December 20, 2012 | Expiration date: December 20, 2012 | Permit id: 2011-079111 Bp | |||||
SCORE 99 Interior remodel to existing admnbusprof office Date: September 14, 2011 Contractor: Robert Bowne Permit type: Electrical permit | Permit status: Final | Completion date: November 15, 2011 | Expiration date: November 15, 2011 | Permit id: 2011-079109 Ep | |||||
SCORE 99 Interior remodel to existing admnbusprof office Date: October 14, 2011 Contractor: David Schimsk Permit type: Mechanical permit | Permit status: Final | Completion date: January 4, 2012 | Expiration date: January 4, 2012 | Permit id: 2011-079109 Mp | |||||
SCORE 100 Interior remodel to existing admnbusprof office Date: November 14, 2011 Contractor: Bruce Bunge Permit type: Plumbing permit | Permit status: Final | Completion date: February 6, 2012 | Expiration date: February 6, 2012 | Permit id: 2011-079109 Pp | |||||
SCORE 99 Interior remodel to existing admnbusprof offices 1st floor phase 2 Applicant Phone: (512) 848-4538 | Permit type: Building permit | Permit status: Final | Completion date: July 5, 2012 | Expiration date: July 5, 2012 | Permit id: 2011-085614 Bp | |||||
SCORE 100 Interior remodel to existing admnbusprof offices 1st floor phase 2 Date: September 27, 2011 Contractor: Robert Mclaughlin Permit type: Electrical permit | Permit status: Final | Completion date: June 29, 2012 | Expiration date: June 29, 2012 | Permit id: 2011-085614 Ep | |||||
SCORE 100 Interior remodel to existing admnbusprof offices 1st floor phase 2 Date: September 27, 2011 Contractor: Richard Hasserd Jr Permit type: Mechanical permit | Permit status: Final | Completion date: May 22, 2012 | Expiration date: May 22, 2012 | Permit id: 2011-085614 Mp | |||||
SCORE 100 Interior remodel to existing admnbusprof offices 1st floor phase 2 Date: February 7, 2012 Contractor: David L Kinney Permit type: Plumbing permit | Permit status: Final | Completion date: March 5, 2012 | Expiration date: March 5, 2012 | Permit id: 2011-085614 Pp | |||||
SCORE 100 Adding 225a feed to new ups system to exsitng elec srv only Date: March 13, 2013 Contractor: Wesley Sunvison Permit type: Electrical permit | Permit status: Final | Completion date: September 9, 2013 | Expiration date: September 9, 2013 | Permit id: 2013-025081 Ep | |||||
SCORE 86 Install eight amp circuits with two data racks for computer server cabinets only Date: October 1, 2015 Contractor: Juan R Saucedo Permit type: Electrical permit | Permit status: Final | Completion date: October 28, 2015 | Expiration date: October 28, 2015 | Permit id: 2015-119166 Ep | |||||
SCORE 93 Interior remodel to existing admin office to create server room Date: July 7, 2015 Contractor: John Mcrae Permit type: Mechanical permit | Permit status: Final | Completion date: July 31, 2015 | Expiration date: July 31, 2015 | Permit id: 2015-079292 Mp | |||||
SCORE 86 Interior remodel to existing admin office to create server room all that was done was add power for a new liebert hvac unithyatt Date: July 7, 2015 Contractor: Juan R Saucedo Permit type: Electrical permit | Permit status: Final | Completion date: July 24, 2015 | Expiration date: July 24, 2015 | Permit id: 2015-079292 Ep | |||||
SCORE 100 Adding 225a feed to new ups system to exsitng elec srv only Date: March 13, 2013 Contractor: Wesley Sunvison Permit type: Electrical permit | Permit status: Final | Completion date: September 9, 2013 | Expiration date: September 9, 2013 | Permit id: 2013-025081 Ep | |||||
SCORE 99 Install power wiring at the 2nd floor only for 14 sets of modular furniture cubicles Date: May 23, 2017 Contractor: Robert Bowne Permit type: Electrical permit | Permit status: Final | Completion date: June 14, 2017 | Expiration date: June 14, 2017 | Permit id: 2017-051211 Ep | |||||
SCORE 100 Interior remodel to existing admnbusprof offices 1st floor phase 2 Date: September 27, 2011 Contractor: Richard Hasserd, Jr Permit type: Mechanical permit | Permit status: Final | Completion date: May 22, 2012 | Expiration date: May 22, 2012 | Permit id: 2011-085614 Mp | |||||
SCORE 100 Interior remodel to existing admnbusprof offices 1st floor phase 2 Date: February 7, 2012 Contractor: David L Kinney Permit type: Plumbing permit | Permit status: Final | Completion date: March 5, 2012 | Expiration date: March 5, 2012 | Permit id: 2011-085614 Pp | |||||
SCORE 100 Interior remodel to existing admnbus office Applicant Phone: (512) 832-1979 | Permit type: Building permit | Permit status: Final | Completion date: July 5, 2007 | Expiration date: July 5, 2007 | Permit id: 2007-128347 Bp | |||||
SCORE 100 Interior remodel to existing admnbus office Date: June 19, 2007 Contractor: Jesse Beckett Permit type: Electrical permit | Permit status: Final | Completion date: July 3, 2007 | Expiration date: January 1, 2008 | Permit id: 2007-128347 Ep | |||||
SCORE 99 Interior remodel to existing admnbus office Date: June 25, 2007 Contractor: David Schimsk Permit type: Mechanical permit | Permit status: Final | Completion date: July 3, 2007 | Expiration date: January 1, 2008 | Permit id: 2007-128347 Mp | |||||
SCORE 98 Interior remodel to existing admnbus office Date: June 25, 2007 Contractor: Rafael Garcia Permit type: Plumbing permit | Permit status: Final | Completion date: July 2, 2007 | Expiration date: January 1, 2008 | Permit id: 2007-128347 Pp | |||||
SCORE 100 Interior remodel to existing office paul 512 801 38 christy 512 466 0450 Applicant Phone: (512) 832-1979 | Permit type: Building permit | Permit status: Final | Completion date: April 9, 2015 | Expiration date: April 9, 2015 | Permit id: 2015-024796 Bp | |||||
SCORE 100 Interior remodel to existing office Date: March 12, 2015 Contractor: Bobby Sanford Permit type: Electrical permit | Permit status: Final | Completion date: April 7, 2015 | Expiration date: April 7, 2015 | Permit id: 2015-024796 Ep | |||||
SCORE 100 Interior remodel to existing office Date: March 18, 2015 Contractor: Juan Balderas Permit type: Mechanical permit | Permit status: Final | Completion date: March 31, 2015 | Expiration date: March 31, 2015 | Permit id: 2015-024796 Mp | |||||
SCORE 96 Interior remodel to existing admnbusprof offices corridor level 1 riata corridor Applicant Phone: (512) 312-6576 | Permit type: Building permit | Permit status: Final | Completion date: July 27, 2010 | Expiration date: July 27, 2010 | Permit id: 2010-061175 Bp | |||||
SCORE 99 Interior remodel to existing admnbusprof office to install new 10ton crac unit wductwork for server room Permit type: Building permit | Permit status: Final | Completion date: November 24, 2010 | Expiration date: November 24, 2010 | Permit id: 2010-075419 Bp | |||||
SCORE 100 Interior remodel to admnbus offices bldg 9 Permit type: Mechanical permit | Permit status: Final | Completion date: April 30, 2003 | Expiration date: April 30, 2003 | Permit id: 2003-000665 Mp | |||||
SCORE 100 Interior remodel to existing admnbusprof office to install new 10ton crac unit wductwork for server room Date: September 1, 2010 Contractor: Robert Mclaughlin Permit type: Electrical permit | Permit status: Final | Completion date: October 12, 2010 | Expiration date: October 12, 2010 | Permit id: 2010-075419 Ep | |||||
SCORE 100 Interior remodel to existing admnbusprof office to install new 10ton crac unit wductwork for server room Date: September 1, 2010 Contractor: Richard Hasserd Jr Permit type: Mechanical permit | Permit status: Final | Completion date: October 12, 2010 | Expiration date: October 12, 2010 | Permit id: 2010-075419 Mp | |||||
SCORE 99 Hvac like for like replacement to commercial building Date: November 14, 2016 Contractor: James Marek Permit type: Mechanical permit | Permit status: Expired | Expiration date: May 13, 2017 | Permit id: 2016-140115 Mp | |||||
SCORE 100 Interior remodel to existing office Date: March 12, 2015 Contractor: Bobby Sanford Permit type: Electrical permit | Permit status: Final | Completion date: April 7, 2015 | Expiration date: April 7, 2015 | Permit id: 2015-024796 Ep | |||||
SCORE 100 Interior remodel to existing office paul 512 801 38 christy 512 466 0450 Applicant Phone: (512) 832-1979 | Permit type: Building permit | Permit status: Final | Completion date: April 9, 2015 | Expiration date: April 9, 2015 | Permit id: 2015-024796 Bp | |||||
SCORE 100 Interior remodel to existing admnbusprof office to install new 10ton crac unit wductwork for server room Date: September 1, 2010 Contractor: Richard Hasserd, Jr Permit type: Mechanical permit | Permit status: Final | Completion date: October 12, 2010 | Expiration date: October 12, 2010 | Permit id: 2010-075419 Mp | |||||
SCORE 100 Interior remodel to existing office Date: March 12, 2015 Contractor: Bobby Sanford Permit type: Electrical permit | Permit status: Final | Completion date: April 7, 2015 | Expiration date: April 7, 2015 | Permit id: 2015-024796 Ep | |||||
New three stry office buildingshell and core Date: April 17, 1998 Value: $4,970,580 Permit type: Mechanical permit | Permit status: Final | Completion date: September 3, 1999 | Expiration date: September 3, 1999 | Permit id: 1998-008887 Mp | |||||
New construction shell bldg 9 Date: April 23, 1998 Value: $4,970,580 Permit type: Mechanical permit | Permit status: Final | Completion date: September 3, 1999 | Expiration date: September 3, 1999 | Permit id: 1998-011443 Mp | |||||
Tenant finishout for admin office2 300 Date: July 9, 1998 Value: $1,100,000 Permit type: Mechanical permit | Permit status: Final | Completion date: September 21, 1999 | Expiration date: September 21, 1999 | Permit id: 1998-004468 Mp | |||||
Finish out admin office floors 123 Date: July 2, 1998 Value: $2,465,000 Permit type: Mechanical permit | Permit status: Final | Completion date: October 16, 1998 | Expiration date: May 24, 1999 | Permit id: 1998-004495 Mp | |||||
Ht loop ug Date: July 21, 1998 Value: $100 Permit type: Mechanical permit | Permit status: Final | Completion date: July 24, 1998 | Expiration date: August 29, 2007 | Permit id: 1998-012912 Mp | |||||
New parking garage Date: October 7, 1998 Value: $1,233,904 Permit type: Mechanical permit | Permit status: Final | Completion date: April 30, 1999 | Expiration date: August 29, 2007 | Permit id: 1998-016672 Mp | |||||
Equipment permit only Date: October 8, 1998 Value: $2,000 Permit type: Mechanical permit | Permit status: Final | Completion date: November 6, 1998 | Expiration date: August 29, 2007 | Permit id: 1998-010849 Mp | |||||
Finish out for office eds Date: December 22, 1998 Value: $248,000 Permit type: Mechanical permit | Permit status: Final | Completion date: January 25, 1999 | Expiration date: July 28, 1999 | Permit id: 1998-002811 Mp | |||||
Tenant finish out 1st floor 2n fl west bl 9 Date: June 2, 1999 Value: $738,000 Permit type: Mechanical permit | Permit status: Final | Completion date: July 14, 1999 | Expiration date: July 14, 1999 | Permit id: 1999-013848 Mp | |||||
Interior remodel for existing office Date: June 7, 1999 Value: $126,745 Permit type: Mechanical permit | Permit status: Final | Completion date: August 10, 1999 | Expiration date: August 10, 1999 | Permit id: 1999-0169 Mp | |||||
Interior office remodel Date: December 9, 1999 Value: $10,000 Permit type: Mechanical permit | Permit status: Void | Completion date: June 6, 2000 | Expiration date: August 29, 2007 | Permit id: 1999-015023 Mp | |||||
SCORE 100 Remodel interior existing office only for janus Date: May 16, 2000 Contractor: Dpr Construction Permit type: Mechanical permit | Permit status: Final | Completion date: May 18, 2000 | Expiration date: May 18, 2000 | Permit id: 2000-011808 Mp | |||||
New permit 2010058810freestanding sign rcp Date: November 24, 2009 Permit type: Electrical permit | Permit status: Void | Expiration date: May 23, 2010 | Permit id: 2009-130107 Ep | |||||
Outside plumbing utilities firelines Date: May 4, 1998 Value: $19,500 Permit type: Plumbing permit | Permit status: Void | Completion date: October 31, 1998 | Expiration date: January 27, 1999 | Permit id: 1998-015519 Pp | |||||
Plumbing for outside utilities firelines Date: May 4, 1998 Value: $13,900 Permit type: Plumbing permit | Permit status: Void | Completion date: October 31, 1998 | Expiration date: January 18, 1999 | Permit id: 1998-015526 Pp | |||||
Sidewalk only for bldgs 8 9 Date: September 23, 1998 Value: $3,000 Permit type: Driveway / sidewalks | Permit status: Final | Completion date: April 28, 1999 | Expiration date: April 28, 1999 | Permit id: 1998-008408 Ds | |||||
Freestanding sign rcp Date: July 12, 2010 Permit type: Electrical permit | Permit status: Final | Completion date: July 13, 2010 | Expiration date: July 13, 2010 | Permit id: 2010-0588 Ep | |||||
Nonstructural interior demolition only Date: May 26, 1999 Value: $2,000 Permit type: Building permit | Permit status: Final | Completion date: August 26, 1999 | Expiration date: August 26, 1999 | Permit id: 1999-016607 Bp | |||||
SCORE 100 Remodel to enlarge data center eliminating some of the training rooms enlarging open office Permit type: Mechanical permit | Permit status: Final | Completion date: June 27, 2000 | Expiration date: June 27, 2000 | Permit id: 2000-008693 Mp |