Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 93 Elevator Date: August 1, 2012 Contractor: Tito Centeno Permit status: Permit finaled | Current use: Commercial | Permit id: 12046-90000-008 | |||||
SCORE 99 Hvac Date: August 23, 2010 Contractor: Yaroslav Panivskyy Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-90000-081 | |||||
Install new susp. Gyp. Bd. Ceiling @ 2nd floor enclosed elevator lobby. Date: January 21, 2010 Value: $2,500 Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 10016-10000-011 | |||||
SCORE 96 Plumbing Date: February 22, 2010 Contractor: Alex Dekadokh Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-90000-028 | |||||
Electrical Date: August 12, 2010 Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-157 | |||||
SCORE 99 Fire sprinkler Date: January 4, 2010 Contractor: Aleksey Dekadokh Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-90000-000 | |||||
SCORE 91 Electrical Date: February 5, 2010 Contractor: Amir Peleg Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-020 | |||||
Supplemental permit to app # 10016-10000-11316; add two conference roo Date: August 17, 2010 Value: $60,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10001-113 | |||||
T/i work. Add sprinklers @ 2nd. Floor. Date: August 20, 2010 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-018 | |||||
Non-structural t. I.; demo new partitions, re-use existing suspended ce Date: July 20, 2010 Value: $320,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-113 | |||||
SCORE 100 Electrical Date: January 14, 2010 Contractor: Joe Marquez Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-006 | |||||
SCORE 56 Electrical Date: January 14, 2010 Contractor: Isaas Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-007 | |||||
SCORE 95 Electrical Date: January 6, 2016 Contractor: Luis Flores Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-362 | |||||
SCORE 89 Tenant improvement on basement level of existing 5 story commercial bu Date: February 5, 2016 Contractor: Mihai Gavan Permit type: Hvac | Permit status: Issued | Current use: Commercial | Permit id: 16044-10000-002 | |||||
SCORE 86 Change of use from office to gymnasium at basement level (n) partitio Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-244 | |||||
SCORE 86 Electrical Date: December 18, 2015 Contractor: Ata Nejad Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-428 | |||||
SCORE 100 Fire sprinkler Date: January 20, 2016 Contractor: Viggen Garibian Permit status: Refund completed | Current use: Commercial | Permit id: 16043-90000-002 | |||||
SCORE 89 Tenant improvement: increase number of water closets and lavatories. Date: February 5, 2016 Contractor: Mihai Gavan Permit type: Plumbing | Permit status: Issued | Current use: Commercial | Permit id: 16042-10000-018 | |||||
SCORE 80 Elevator Date: February 26, 2014 Contractor: Marciela Estrada Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-002 | |||||
Elevator Date: November 20, 2014 Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-017 | |||||
SCORE 84 Electrical Date: January 13, 2016 Contractor: John Shull Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-012 | |||||
SCORE 67 Tenant improvement on fifth floor of existing six story commercial bui Date: February 4, 2016 Contractor: Sarkis Mooshidian Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-005 | |||||
SCORE 100 Elevator Date: May 25, 2016 Contractor: Annette Couts Permit status: Permit finaled | Current use: Commercial | Permit id: 16046-90000-007 | |||||
SCORE 86 Plan check for temporary power. Service size is 3,0 amps. Date: July 22, 2016 Contractor: David Gushyan Permit type: Electrical | Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-077 | |||||
Plumbing Date: July 28, 2016 Permit status: Issued | Current use: Commercial | Permit id: 16042-90000-154 | |||||
SCORE 97 Reroute underground fire service for existing 6 story commercial build Date: August 1, 2016 Contractor: Mike Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-20000-035 | |||||
SCORE 69 Plumbing Date: August 9, 2016 Contractor: E T Plumbing Permit status: Issued | Current use: Commercial | Permit id: 16042-20000-164 | |||||
SCORE 86 (n) 2-hr enclosure for electrical equipment between ground & basement Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-240 | |||||
SCORE 86 Elevator Date: November 20, 2014 Contractor: Sterling Corporate Custom Elevator Interiors Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-017 | |||||
SCORE 64 Plumbing Date: July 28, 2016 Contractor: Ed Taymoorian Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-90000-154 | |||||
SCORE 96 Ti - fifth floor Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-222 | |||||
SCORE 95 Date: January 6, 2016 Contractor: Luis Flores Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-362 | |||||
SCORE 86 Date: November 20, 2014 Contractor: Sterling Corporate Custom Elevator Interiors Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-017 | |||||
SCORE 100 Date: May 25, 2016 Contractor: Annette Couts Permit status: Permit finaled | Current use: Commercial | Permit id: 16046-90000-007 | |||||
SCORE 84 Date: January 13, 2016 Contractor: John Shull Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-012 | |||||
SCORE 96 Ti - fifth floor Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-222 | |||||
SCORE 69 Date: August 9, 2016 Contractor: E T Plumbing Permit status: Issued | Current use: Commercial | Permit id: 16042-20000-164 | |||||
SCORE 67 Tenant improvement on fifth floor of existing six story commercial bui Date: February 4, 2016 Contractor: Sarkis Mooshidian Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-005 | |||||
SCORE 64 Date: July 28, 2016 Contractor: Ed Taymoorian Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-90000-154 | |||||
SCORE 86 (n) 2-hr enclosure for electrical equipment between ground & basement Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-240 | |||||
SCORE 86 Plan check for temporary power. Service size is 3,0 amps. Date: July 22, 2016 Contractor: David Gushyan Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-077 | |||||
SCORE 89 Tenant improvement on basement level of existing 5 story commercial bu Date: February 5, 2016 Contractor: Mihai Gavan Permit status: Issued | Current use: Commercial | Permit id: 16044-10000-002 | |||||
SCORE 86 Change of use from office to gymnasium at basement level (n) partitio Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-244 | |||||
SCORE 97 Reroute underground fire service for existing 6 story commercial build Date: August 1, 2016 Contractor: Mike Permit status: Issued | Current use: Commercial | Permit id: 16043-20000-035 | |||||
SCORE 86 Date: December 18, 2015 Contractor: Ata Nejad Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-428 | |||||
SCORE 100 Date: January 20, 2016 Contractor: Viggen Garibian Permit status: Refund completed | Current use: Commercial | Permit id: 16043-90000-002 | |||||
SCORE 89 Tenant improvement: increase number of water closets and lavatories. Date: February 5, 2016 Contractor: Mihai Gavan Permit status: Issued | Current use: Commercial | Permit id: 16042-10000-018 | |||||
SCORE 80 Date: February 26, 2014 Contractor: Marciela Estrada Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-002 |