SCORE 100 14-1067: add escape hatch from 2nd floor to 1st floor. Date: March 3, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00133 | |||||
SCORE 100 14-1067: revised trash enclosure construction design clarification Date: March 3, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00130 | |||||
SCORE 100 14-1068: revised plans for trash enclosure drawing clarification Date: March 3, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00129 | |||||
14000-01067: deferred submittal for stairway #4 Date: September 12, 2017 Permit status: Permit issued | Permit id: 17rev-00572 | |||||
SCORE 93 Ti and u&o for tenant "machine zone" to occupy the entire 76,548 sf two story building (building # 3). No exterior work, no landscaping Permit status: Permit issued | Permit id: 17000-00537 | |||||
SCORE 100 Building 3: 54,134 sq ft foundation and basement garage for future 2 story office building. Above grade portion of structure reviewed under 15rev-00755 Permit status: Permit issued | Permit id: 14000-01067 | |||||
14000-01067: revision relocated building 3 trash enclosure to accommodate new generator enclosure (17rev-00500). Date: September 26, 2017 Permit id: 17rev-00607 | |||||
SCORE 100 14000-01067: building 3 deferred submittal for exterior metal stud and drywall. Date: September 13, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00579 | |||||
SCORE 100 14-1067: deferred glass for building #3. Date: January 3, 2017 Contractor: Devcon Construction Incorporated Permit status: In plan check | Permit id: 17rev-00002 | |||||
SCORE 100 Building 3: 54,134 sq ft foundation and basement garage for future 2 story office building. Above grade portion of structure reviewed under 15rev-00755 Date: May 15, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00285 | |||||
14000-01067: building #3 revision inlcudes bathroom finishes and lighting (all bathrooms) Date: June 28, 2017 Permit status: Permit issued | Permit id: 17rev-00388 | |||||
SCORE 100 Building 4: 54,234 sq ft foundation and basement garage for future 2 story office building. Above grade portion of structure reviewed under 15rev-00756 Permit status: Permit issued | Permit id: 14000-01068 | |||||
SCORE 96 Building 3: install (377) solar modules, (15) 8w inverters on roof Date: November 9, 2016 Contractor: Sun Light And Power Permit status: Permit issued | Permit id: 16000-02823 | |||||
SCORE 100 14-1067: deferred building #3 stair #3 Date: August 4, 2017 Contractor: Devcon Construction Incorporated Permit status: Permit issued | Permit id: 17rev-00480 | |||||
SCORE 100 14-1067: deferred building #3 balcony and bridge guardrails. Date: August 4, 2017 Contractor: Devcon Construction Incorporated Permit status: Completed | Permit id: 17rev-00481 |