Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 56 Foundation for state approved commercial coach (temporary us Applicant: Space Leasing Co | Permit status: Finaled | Completion date: April 13, 2001 | Permit id: 0008230012 | |||||
SCORE 95 New partitions,ceilings,and floor finish materials Applicant: Sturm Jerry | Permit status: Finaled | Completion date: October 4, 2001 | Permit id: 0010230001 | |||||
SCORE 88 New floor finish,new ceiling finish,new partitions Applicant: Sturm Jerry | Permit status: Finaled | Completion date: October 23, 2002 | Permit id: 0108270019 | |||||
SCORE 74 Relocate 4 section of 4" fire standpipe Applicant: Kimble And Company | Permit status: Finaled | Completion date: September 23, 2002 | Permit id: 0202210023 | |||||
SCORE 95 Keystone retaining wall o. K. To issue permit per mr. Ed alexanians info relayed by mr. Jesse arenas Applicant: Mackone Development Inc Jerry | Permit status: Finaled | Completion date: January 21, 2003 | Permit id: 0301210010 | |||||
SCORE 89 Replacing ckt breaker and disconnect switch,conduits Date: February 14, 2001 Contractor: Power Line Electric Inc Applicant: Han Paul | Permit status: Finaled | Completion date: April 13, 2001 | Permit id: 0009220030 | |||||
SCORE 82 Power for modular building,install (10) 100a,(1) 600a service panels,and (1) transformers,225kva. Date: November 21, 2000 Contractor: Dc Systems Applicant: Dave Tjernagel | Permit status: Finaled | Completion date: April 13, 2001 | Permit id: 0011160036 | |||||
SCORE 100 Install new 250amps service panel to feed in existing load. No fee permit per lloyd moore. Date: June 13, 2001 Contractor: Precision Electric Applicant: Dennis Geltner | Permit status: Permisud | Permit id: 0106130014 | |||||
SCORE 89 7 outlets,59 light fixtures Date: July 12, 2001 Contractor: Power Line Electric Inc Applicant: Power Line Electric Inc | Permit status: Finaled | Completion date: October 4, 2001 | Permit id: 0107120042 | |||||
SCORE 89 Branch circuits Date: September 20, 2001 Contractor: Power Line Electric Inc Applicant: Kim,Soo | Permit status: Finaled | Completion date: December 12, 2001 | Permit id: 0109200008 | |||||
SCORE 56 Install 1 v ac smoke detectors to shut down fire smoke dampers. Date: October 4, 2001 Contractor: Fire Call Inc Applicant: Alex Guerrero | Permit status: Permisud | Permit id: 0110040024 | |||||
SCORE 97 Office t. I.,install branch circuits. Date: October 29, 2001 Contractor: Comet Electric Inc Applicant: Barry Levin | Permit status: Finaled | Completion date: October 23, 2002 | Permit id: 0110290008 | |||||
SCORE 56 Remove fixtures & install t5 fl. Fixtures Date: December 18, 2003 Contractor: Lighting Technology Services Applicant: Parada,Ivis | Permit status: Permisud | Permit id: 0312180042 | |||||
SCORE 95 Addition on parking lot & key excavation for wall at slope area Date: June 12, 2002 Contractor: Mackone Development Inc Applicant: Mackone Development Inc Jerry | Permit status: Permisud | Permit id: 0109170001 | |||||
SCORE 97 Replacing and relocate air inlets/outlets. Date: March 1, 2001 Contractor: Mek Air Tech Applicant: Jong Lee | Permit status: Finaled | Completion date: October 4, 2001 | Permit id: 0103010011 | |||||
SCORE 99 Install (48) units air inlets/outlets,(4) fire dampers and (1) alteration of exist duct system. Date: October 4, 2001 Contractor: Xcel Mechanical Systems Inc Applicant: Xcel Mechanical Systems,Inc. | Permit status: Finaled | Completion date: October 23, 2002 | Permit id: 0110040003 | |||||
SCORE 99 Install (1) lavatories/sinks Date: October 4, 2001 Contractor: Xcel Mechanical Systems Inc Applicant: Xcel Mechanical Systems,Inc. | Permit status: Finaled | Completion date: October 23, 2002 | Permit id: 0110040002 | |||||
SCORE 77 Plumbing for 2 toilets & 2 sinks Date: November 30, 2001 Contractor: Blue Line Inc Applicant: Choi | Permit status: Finaled | Completion date: December 12, 2001 | Permit id: 0111300032 | |||||
SCORE 77 Gas line (low pressure) Date: December 3, 2001 Contractor: Blue Line Inc Applicant: Choi | Permit status: Permisud | Permit id: 0112030016 | |||||
SCORE 70 Connect sewer to existing building sewer Date: September 22, 2000 Contractor: Blue Line Plumbing Co Applicant: Blue Line Inc | Permit status: Finaled | Completion date: April 13, 2001 | Permit id: 0009220045 | |||||
SCORE 95 New partitions, ceilings, and floor finish materials Engineer: Jsa | Applicant: Sturm Jerry | Permit status: Finaled | Completion date: October 4, 2001 | Expiration date: August 27, 2001 | Permit id: 10230001 | |||||
SCORE 88 New floor finish, new ceiling finish, new partitions Engineer: Jsa Architecture | Applicant: Sturm Jerry | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 27, 2002 | Permit id: 108270019 | |||||
SCORE 89 Replacing ckt breaker and disconnect switch, conduits Date: February 14, 2001 Contractor: Power Line Electric Inc Applicant: Han Paul | Permit status: Finaled | Completion date: April 13, 2001 | Expiration date: March 22, 2001 | Permit id: 9220030 | |||||
SCORE 82 Power for modular building, install (10) 100a, (1) 600a service panels, and (1) transformers, 225kva. Date: November 21, 2000 Contractor: Dc Systems Applicant: Dave Tjernagel | Permit status: Finaled | Completion date: April 13, 2001 | Expiration date: May 21, 2001 | Permit id: 11160036 | |||||
SCORE 100 Install new 250amps service panel to feed in existing load. No fee permit per lloyd moore. Date: June 13, 2001 Contractor: Precision Electric Applicant: Dennis Geltner | Permit status: Permisud | Expiration date: December 10, 2001 | Permit id: 106130014 | |||||
SCORE 89 7 outlets, 59 light fixtures Date: July 12, 2001 Contractor: Power Line Electric Inc Applicant: Power Line Electric Inc | Permit status: Finaled | Completion date: October 4, 2001 | Expiration date: January 8, 2002 | Permit id: 107120042 | |||||
SCORE 89 Branch circuits Date: September 20, 2001 Contractor: Power Line Electric Inc Applicant: Kim, Soo | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: March 19, 2002 | Permit id: 109200008 | |||||
SCORE 97 Office t. I., install branch circuits. Date: October 29, 2001 Contractor: Comet Electric Inc Engineer: Jsa Architecture | Applicant: Barry Levin | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 27, 2002 | Permit id: 110290008 | |||||
SCORE 99 Install (48) units air inlets/outlets, (4) fire dampers and (1) alteration of exist duct system. Date: October 4, 2001 Contractor: Xcel Mechanical Systems Inc Engineer: Jsa | Applicant: Xcel Mechanical Systems, Inc. | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 2, 2002 | Permit id: 110040003 | |||||
SCORE 95 Ti/new tele room, wall furring, ceiling tile, acc-men&woman toilet Engineer: Jsa Architecture | Applicant: Mackone Development Inc | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: March 11, 2002 | Permit id: 105220002 | |||||
SCORE 88 Ada upgrade to first floor restrooms. Engineer: Jsa Architects* | Applicant: Jsa Architects | Permit status: Finaled | Completion date: September 23, 2002 | Expiration date: October 22, 2002 | Permit id: 203120048 | |||||
SCORE 99 New lights in rest room & down lights in hall. Date: April 15, 2002 Contractor: Comet Electric Engineer: Jsa Architects* | Applicant: Comet Electric Inc. 8183400965 | Permit status: Permisud | Expiration date: October 12, 2002 | Permit id: 204150005 | |||||
SCORE 59 Provide lighting for new parking lot. Replace high bay fixt ures in welding shop. Date: February 27, 2003 Contractor: Vista Universal Engineer: Jsa Architects* | Applicant: Vista Universal Inc 8183400965 | Permit status: Finaled | Completion date: April 10, 2003 | Expiration date: August 26, 2003 | Permit id: 302270026 | |||||
SCORE 59 Replace (14) lighting fixtures. Date: June 12, 2003 Contractor: Vista Universal Engineer: Jsa Architects* | Applicant: Vista Universal Inc 8183400965 | Permit status: Finaled | Completion date: July 27, 2011 | Expiration date: December 9, 2003 | Permit id: 306120024 | |||||
SCORE 86 Install (6) 225 amps panels. Date: June 18, 2003 Contractor: A. R. C. Electric Applicant: Russell Whitehead 8183400965 | Permit status: Finaled | Completion date: January 21, 2004 | Expiration date: December 15, 2003 | Permit id: 306180015 | |||||
SCORE 59 Ada upgrade to first floor restrooms. Date: March 27, 2002 Contractor: 8183461314 Capri Construction Engineer: Jsa Architects* | Applicant: Xcel Mech | Permit status: Permisud | Expiration date: September 23, 2002 | Permit id: 203270029 | |||||
SCORE 88 Ada upgrade to first floor restrooms. Date: March 27, 2002 Contractor: Capri Construction Engineer: Jsa Architects* | Applicant: Xcel Mechanical Systems 3106600090 | Permit status: Initiate | Expiration date: September 23, 2002 | Permit id: 203270044 | |||||
SCORE 87 Chiller retrofit Applicant: Norecco, Llc. | Permit status: Finaled | Completion date: October 17, 2005 | Expiration date: July 30, 2006 | Permit id: 506160149 | |||||
SCORE 59 Build 20x freestanding metal canopy Applicant: Kluba Mike | Permit status: Finaled | Completion date: March 23, 2009 | Expiration date: June 8, 2009 | Permit id: 809180027 | |||||
SCORE 59 Build 16 x 124 metal canopy w/heavy duty over head hanger Applicant: Kluba Mike | Permit status: Finaled | Completion date: December 12, 2008 | Expiration date: May 2, 2009 | Permit id: 811030051 | |||||
SCORE 95 Demo / fire proofing Applicant: Bryan Gay | Permit status: Finaled | Completion date: August 14, 2009 | Expiration date: August 25, 2009 | Permit id: 902260021 | |||||
SCORE 100 Change out chiller and boiler on roof Applicant: Wright, D. Russell | Permit status: Finaled | Completion date: July 9, 2010 | Expiration date: June 30, 2011 | Permit id: 1004190054 | |||||
SCORE 95 T. I. Of 6 sqft of existing office space Engineer: And Planning Wayne C. Siu Architects | Applicant: Kim Hee Yong | Permit status: Finaled | Completion date: January 13, 2011 | Expiration date: October 12, 2011 | Permit id: 1009210068 | |||||
SCORE 96 Convert existing mens locker room to womenss restroom Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: November 20, 2012 | Expiration date: April 10, 2013 | Permit id: 1201090091 | |||||
SCORE 96 Replace existing emergency generator w/ a larger generator (5 kw) Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1202210039 | |||||
SCORE 96 Retaining wall w/ fence 76"high x long Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1202210040 | |||||
SCORE 95 Add kitchen counter & replace floor covering Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: August 29, 2014 | Permit id: 1306100026 | |||||
SCORE 96 Minor t. I. - repair of return air ducting for 4 stories; new penetration of rated walls Engineer: Raw International Inc. | Applicant: Kim David | Permit status: Permisud | Expiration date: October 14, 2016 | Permit id: 1312300014 | |||||
SCORE 95 Renovate existing mens restroom for accessible compiance Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1402240018 | |||||
SCORE 87 Chiller retrofit Date: August 4, 2005 Contractor: Noresco Llc Applicant: Norecco, Llc. | Permit status: Finaled | Completion date: December 7, 2005 | Expiration date: January 31, 2006 | Permit id: 508040026 | |||||
SCORE 98 Install 2 ufds 1 20hp and 1 60hp Date: September 9, 2008 Contractor: Barr Engineering Inc Applicant: Ed Freeman | Permit status: Finaled | Completion date: October 23, 2008 | Expiration date: March 8, 2009 | Permit id: 809090019 | |||||
SCORE 89 Electrical permit: install (1) circuit. Date: March 17, 2009 Contractor: Jam Fire Protection Applicant: Paul Brown | Permit status: Finaled | Completion date: May 26, 2011 | Expiration date: September 13, 2009 | Permit id: 903170020 | |||||
SCORE 100 El for chiller and boiler on roof Date: June 30, 2010 Contractor: Acco Engineered Systems Applicant: Wright D. Russell | Permit status: Finaled | Completion date: July 9, 2010 | Expiration date: June 30, 2011 | Permit id: 1004190034 | |||||
SCORE 96 El for womenss restroom Date: April 10, 2012 Contractor: M T M Construction Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: November 20, 2012 | Expiration date: April 10, 2013 | Permit id: 1204090054 | |||||
SCORE 96 El for emergency generator w/ a larger generator (5 kw) Date: May 16, 2012 Contractor: M T M Construction Inc Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1204260044 | |||||
SCORE 95 Electrical for restroom ada upgrade Date: April 8, 2014 Contractor: Harry H Joh Construction Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1404080006 | |||||
SCORE 95 Grading for slope repair.(job #pw004f0012-31-07) Date: May 16, 2007 Contractor: New Creation Builders Applicant: Ganjian Fred | Permit status: Finaled | Completion date: June 22, 2007 | Expiration date: November 12, 2007 | Permit id: 612180002 | |||||
SCORE 100 Me for chiller and boiler on roof Date: June 30, 2010 Contractor: Acco Engineered Systems Applicant: Wright D. Russell | Permit status: Finaled | Completion date: July 9, 2010 | Expiration date: June 30, 2011 | Permit id: 1004190021 | |||||
SCORE 96 Me for womenss restroom Date: April 10, 2012 Contractor: M T M Construction Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: April 10, 2013 | Permit id: 1204090021 | |||||
SCORE 96 Repair return air ducting - remove (e) damper & install (n) combination fire smoke dampers, install (n) return & exhaust fans Date: October 15, 2015 Contractor: M T M Construction Inc Engineer: Raw International Inc. | Applicant: Kim David | Permit status: Permisud | Expiration date: October 14, 2016 | Permit id: 1312300002 | |||||
SCORE 100 Pl for chiller and boiler on roof Date: June 30, 2010 Contractor: Acco Engineered Systems Applicant: Wright D. Russell | Permit status: Finaled | Completion date: July 9, 2010 | Expiration date: June 30, 2011 | Permit id: 1006290037 | |||||
SCORE 96 Pl for convert existing mens locker rm to womenss restroom Date: April 10, 2012 Contractor: M T M Construction Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: April 10, 2013 | Permit id: 1201090032 | |||||
SCORE 95 Pl for t. I for breakroom area Date: August 29, 2013 Contractor: Mackone Development Inc Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: January 25, 2014 | Expiration date: August 29, 2014 | Permit id: 1308290030 | |||||
SCORE 95 Plumbing for upgrade to restroom Date: April 8, 2014 Contractor: Harry H Joh Construction Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1404080004 | |||||
SCORE 100 Ti new tele room, wall furring, ceiling tile, acc-men&woman toilet Engineer: Jsa Architecture | Applicant: Mackone Development Inc | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: March 11, 2002 | Permit id: 105220002 | |||||
SCORE 64 Chiller retrofit Applicant: Norecco, Llc. | Permit status: Finaled | Completion date: October 17, 2005 | Expiration date: July 30, 2006 | Permit id: 506160149 | |||||
SCORE 59 Build 20x freestanding metal canopy Applicant: Kluba Mike | Permit status: Finaled | Completion date: March 23, 2009 | Expiration date: June 8, 2009 | Permit id: 809180027 | |||||
SCORE 59 Build 16 x 124 metal canopy w heavy duty over head hanger Applicant: Kluba Mike | Permit status: Finaled | Completion date: December 12, 2008 | Expiration date: May 2, 2009 | Permit id: 811030051 | |||||
SCORE 100 Demo fire proofing Applicant: Bryan Gay | Permit status: Finaled | Completion date: August 14, 2009 | Expiration date: August 25, 2009 | Permit id: 902260021 | |||||
SCORE 100 Convert existing mens locker room to womenss restroom Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: November 20, 2012 | Expiration date: April 10, 2013 | Permit id: 1201090091 | |||||
SCORE 100 Replace existing emergency generator w a larger generator (5 kw) Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1202210039 | |||||
SCORE 100 Retaining wall w fence 76"high x long Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1202210040 | |||||
SCORE 100 Add kitchen counter & replace floor covering Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: August 29, 2014 | Permit id: 1306100026 | |||||
SCORE 100 Minor t. I. - repair of return air ducting for 4 stories; new penetration of rated walls Engineer: Raw International Inc. | Applicant: Kim David | Permit status: Permisud | Expiration date: October 14, 2016 | Permit id: 1312300014 | |||||
SCORE 98 Renovate existing mens restroom for accessible compiance Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1402240018 | |||||
SCORE 64 Chiller retrofit Date: August 4, 2005 Contractor: Noresco, Llc Applicant: Norecco, Llc. | Permit status: Finaled | Completion date: December 7, 2005 | Expiration date: January 31, 2006 | Permit id: 508040026 | |||||
SCORE 100 El for womenss restroom Date: April 10, 2012 Contractor: M T M Construction, Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: November 20, 2012 | Expiration date: April 10, 2013 | Permit id: 1204090054 | |||||
SCORE 100 El for emergency generator w a larger generator (5 kw) Date: May 16, 2012 Contractor: M T M Construction, Inc Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 16, 2013 | Permit id: 1204260044 | |||||
SCORE 98 Electrical for restroom ada upgrade Date: April 8, 2014 Contractor: Harry H Joh Construction, Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1404080006 | |||||
SCORE 100 Me for womenss restroom Date: April 10, 2012 Contractor: M T M Construction, Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: April 10, 2013 | Permit id: 1204090021 | |||||
SCORE 100 Repair return air ducting - remove (e) damper & install (n) combination fire smoke dampers, install (n) return & exhaust fans Date: October 15, 2015 Contractor: M T M Construction, Inc Engineer: Raw International Inc. | Applicant: Kim David | Permit status: Permisud | Expiration date: October 14, 2016 | Permit id: 1312300002 | |||||
SCORE 100 Pl for convert existing mens locker rm to womenss restroom Date: April 10, 2012 Contractor: M T M Construction, Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Permisud | Expiration date: April 10, 2013 | Permit id: 1201090032 | |||||
SCORE 100 Pl for t. I for breakroom area Date: August 29, 2013 Contractor: Mackone Development, Inc Engineer: Wayne C. Siu Architects | Applicant: Siu Wayne C | Permit status: Finaled | Completion date: January 25, 2014 | Expiration date: August 29, 2014 | Permit id: 1308290030 | |||||
SCORE 98 Plumbing for upgrade to restroom Date: April 8, 2014 Contractor: Harry H Joh Construction, Inc Engineer: And Planning Wayne C. Siu Architects | Applicant: Alfredo Lopez | Permit status: Permisud | Expiration date: April 8, 2015 | Permit id: 1404080004 | |||||
SCORE 100 New partitions, ceilings, and floor finish materials Engineer: Jsa | Applicant: Sturm Jerry | Permit status: Finaled | Completion date: October 4, 2001 | Expiration date: August 27, 2001 | Permit id: 10230001 | |||||
SCORE 100 Keystone retaining wall o. K. To issue permit per mr. Ed alexanians info relayed by mr. Jesse arenas Engineer: Mayon Engineering | Applicant: Mackone Development Inc Jerry | Permit status: Finaled | Completion date: January 21, 2003 | Expiration date: January 16, 2004 | Permit id: 301210010 | |||||
SCORE 89 Replacing ckt breaker and disconnect switch, conduits Date: February 14, 2001 Contractor: Power Line Electric, Inc Applicant: Han Paul | Permit status: Finaled | Completion date: April 13, 2001 | Expiration date: March 22, 2001 | Permit id: 9220030 | |||||
SCORE 100 Install new 250amps service panel to feed in existing load. No fee permit per lloyd moore. Date: June 13, 2001 Contractor: Precision Electric Applicant: Dennis Geltner | Permit status: Permisud | Expiration date: December 10, 2001 | Permit id: 106130014 | |||||
SCORE 89 7 outlets, 59 light fixtures Date: July 12, 2001 Contractor: Power Line Electric, Inc Applicant: Power Line Electric Inc | Permit status: Finaled | Completion date: October 4, 2001 | Expiration date: January 8, 2002 | Permit id: 107120042 | |||||
SCORE 89 Branch circuits Date: September 20, 2001 Contractor: Power Line Electric, Inc Applicant: Kim, Soo | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: March 19, 2002 | Permit id: 109200008 | |||||
SCORE 56 Install 1 v ac smoke detectors to shut down fire smoke dampers. Date: October 4, 2001 Contractor: Fire Call, Inc Applicant: Alex Guerrero | Permit status: Permisud | Expiration date: April 2, 2002 | Permit id: 110040024 | |||||
SCORE 87 Office t. I., install branch circuits. Date: October 29, 2001 Contractor: Comet Electric, Inc Engineer: Jsa Architecture | Applicant: Barry Levin | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 27, 2002 | Permit id: 110290008 | |||||
SCORE 100 Addition on parking lot & key excavation for wall at slope area Date: June 12, 2002 Contractor: Mackone Development, Inc Engineer: Mayon Engineering | Applicant: Mackone Development Inc Jerry | Permit status: Permisud | Expiration date: December 9, 2002 | Permit id: 109170001 | |||||
SCORE 97 Replacing and relocate air inlets outlets. Date: March 1, 2001 Contractor: Mek Air Tech Engineer: Jsa | Applicant: Jong Lee | Permit status: Finaled | Completion date: October 4, 2001 | Expiration date: August 28, 2001 | Permit id: 103010011 | |||||
SCORE 75 Install (48) units air inlets outlets, (4) fire dampers and (1) alteration of exist duct system. Date: October 4, 2001 Contractor: Xcel Mechanical Systems, Inc Engineer: Jsa | Applicant: Xcel Mechanical Systems, Inc. | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 2, 2002 | Permit id: 110040003 | |||||
SCORE 75 Install (1) lavatories sinks Date: October 4, 2001 Contractor: Xcel Mechanical Systems, Inc Engineer: Jsa | Applicant: Xcel Mechanical Systems, Inc. | Permit status: Finaled | Completion date: October 23, 2002 | Expiration date: April 2, 2002 | Permit id: 110040002 | |||||
SCORE 67 Plumbing for 2 toilets & 2 sinks Date: November 30, 2001 Contractor: Blue Line, Inc Applicant: Choi | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: May 29, 2002 | Permit id: 111300032 | |||||
SCORE 67 Gas line (low pressure) Date: December 3, 2001 Contractor: Blue Line, Inc Applicant: Choi | Permit status: Permisud | Expiration date: June 1, 2002 | Permit id: 112030016 | |||||
SCORE 65 Compressors, furnace/heater, air inlets. Date: September 10, 2001 Contractor: Ace Cooling And Heating Corp Engineer: Jsa Architecture | Applicant: Ace Cooling & Heating Corp. | Permit status: Finaled | Completion date: December 12, 2001 | Expiration date: March 9, 2002 | Permit id: 109100007 | |||||
SCORE 95 Re-roof: tear off existing & replace w/2 ply app modified roofing system. Complete w/insulation & cap sheet. Refurbish 20x platform Applicant: Arthur Magtibay | Permit status: Finaled | Completion date: April 21, 2011 | Expiration date: September 21, 2011 | Permit id: 1009210060 | |||||
SCORE 99 Connect new boiler to existing service Date: October 6, 2005 Contractor: Southern California Boiler Applicant: Sandero John | Permit status: Finaled | Completion date: November 15, 2005 | Expiration date: April 4, 2006 | Permit id: 510060001 | |||||
SCORE 100 C/o (8) mbh radiant heaters/refrig comp & a/c handling unit. Date: September 15, 2010 Contractor: Acco Engineered Systems Applicant: Wright, Russell | Permit status: Finaled | Completion date: September 24, 2010 | Expiration date: September 15, 2011 | Permit id: 1009150007 | |||||
SCORE 67 Fire sprinkler installation for 1,8 sf on 1st floor - 2. 5" branch line, 6 heads Applicant: Chairez Juan | Permit status: Permisud | Expiration date: March 29, 2017 | Permit id: 1603290098 | |||||
SCORE 67 Install electrical branch circuit for fire alarm Date: August 3, 2016 Contractor: Diversified Protection Systems, Inc Applicant: Lemasters Thomas J | Permit status: Permisud | Expiration date: August 3, 2017 | Permit id: 1608030002 |