Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: November 24, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 248437 | |||||
Suppression permit Date: July 6, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Active | Permit id: 705246 | |||||
Operations permit Date: September 23, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 23778 | |||||
Zoning/use permit Date: September 6, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 490408 | |||||
New construction permit Date: December 4, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 245090 | |||||
Electrical permit Date: July 28, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 353109 | |||||
Electrical permit Date: June 8, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 274656 | |||||
Administrative permit Date: August 26, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 297977 | |||||
Administrative permit Date: March 21, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 659473 | |||||
Zoning/use permit Date: May 2, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 646436 | |||||
Administrative permit Date: May 29, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 537032 | |||||
New construction permit Date: October 7, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 559761 | |||||
Zoning/use permit Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 119990 | |||||
Suppression permit Date: October 29, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 560736 | |||||
Addition permit Date: September 9, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 556730 | |||||
Mechanical permit Date: November 16, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 649007 | |||||
Alteration permit Date: August 17, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 353156 | |||||
Electrical permit Date: November 10, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 187153 | |||||
Suppression permit Date: November 24, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 654130 | |||||
Electrical permit Date: November 8, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 499743 | |||||
Sign permit Date: September 13, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 296799 | |||||
Operations permit Date: April 19, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Expired | Permit id: 24136 | |||||
Operations permit Date: November 27, 2012 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 22043 | |||||
Plumbing permit Date: December 4, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 501162 | |||||
Suppression permit Date: August 20, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 282855 | |||||
Plumbing permit Date: February 10, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 586057 | |||||
Mechanical permit Date: August 6, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 284713 | |||||
Plumbing permit Date: August 10, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Active | Permit id: 707289 | |||||
Operations permit Date: September 27, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 21163 | |||||
Mechanical permit Date: August 10, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 705743 | |||||
Zoning permit Date: September 12, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 555440 | |||||
Zoning/use permit Date: September 23, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 562949 | |||||
Operations permit Date: October 7, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 19922 | |||||
Mechanical permit Date: November 20, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 501152 | |||||
Mechanical permit Date: September 19, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 360969 | |||||
Zoning/use permit Date: July 8, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 287929 | |||||
Electrical permit Date: October 23, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 636545 | |||||
New construction permit Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 124758 | |||||
Zoning permit Date: January 2, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 124218 | |||||
Alteration permit Date: October 3, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 496317 | |||||
Sign permit Date: September 15, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Active | Permit id: 716318 | |||||
Zoning/use permit Date: September 3, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 235284 | |||||
Electrical permit Date: March 4, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 665781 | |||||
Administrative permit Date: April 29, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 210025 | |||||
Operations permit Date: July 1, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 22434 | |||||
Alteration permit Date: July 26, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Active | Permit id: 693884 | |||||
Electrical permit Date: October 3, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 562783 | |||||
Addition permit Date: September 23, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 492070 | |||||
Operations permit Date: December 30, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 20875 | |||||
Suppression permit Date: October 10, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 499734 | |||||
On may 3, 2010, the department of license & inspections issued a notice of refusal for application #269698. Date: May 18, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Applicant: Sugarhouse Hsp Gaming, L.P. | Permit type: Appeal | Permit status: Approved | Permit id: 11748 | |||||
Operations permit Date: June 20, 2013 Client: Sugarhouse Hsp Gaming Lp | Permit status: Completed | Permit id: 22415 | |||||
Operations permit Date: July 21, 2014 Client: Sugarhouse Hsp Gaming Lp | Permit status: Completed | Permit id: 23029 | |||||
Mechanical permit Date: September 19, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 360969 | |||||
Suppression permit Date: November 24, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 654130 | |||||
Administrative permit Date: May 17, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 692566 | |||||
Administrative permit Date: August 18, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 296352 | |||||
Mechanical permit Date: April 7, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 593062 | |||||
Electrical permit Date: July 28, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 353109 | |||||
Suppression permit Date: February 19, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 259032 | |||||
Operations permit Date: May 2, 2012 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 21571 | |||||
New construction permit Date: December 4, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 245090 | |||||
New construction permit Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 124758 | |||||
Alteration permit Date: October 3, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 496317 | |||||
Suppression permit Date: January 6, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 506354 | |||||
Zoning use permit Date: May 2, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 646436 | |||||
Alteration permit Date: August 17, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 353156 | |||||
Plumbing permit Date: February 10, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 586057 | |||||
Alteration permit Date: July 26, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 693884 | |||||
Plumbing permit Date: December 4, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 501162 | |||||
Electrical permit Date: August 2, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Expired | Permit id: 287839 | |||||
Mechanical permit Date: August 10, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 705743 | |||||
Zoning permit Date: September 12, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 555440 | |||||
Sign permit Date: August 26, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 687657 | |||||
Mechanical permit Date: August 6, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 284713 | |||||
Operations permit Date: October 7, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 19922 | |||||
Electrical permit Date: November 10, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 187153 | |||||
Operations permit Date: September 27, 2011 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 21163 | |||||
Electrical permit Date: October 3, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 562783 | |||||
Zoning use permit Date: July 8, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 287929 | |||||
New construction permit Date: October 7, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 559761 | |||||
Operations permit Date: July 1, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 22434 | |||||
Suppression permit Date: September 2, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 719480 | |||||
Operations permit Date: September 23, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 23778 | |||||
Administrative permit Date: December 31, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 653749 | |||||
Zoning permit Date: January 2, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 124218 | |||||
Electrical permit Date: March 4, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 665781 | |||||
Operations permit Date: December 30, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 20875 | |||||
Electrical permit Date: October 23, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 636545 | |||||
Operations permit Date: April 19, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Expired | Permit id: 24136 | |||||
Suppression permit Date: October 10, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 499734 | |||||
Plumbing permit Date: December 3, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 249026 | |||||
Zoning use permit Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 119990 | |||||
Plumbing permit Date: August 10, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 707289 | |||||
Electrical permit Date: November 8, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 499743 | |||||
Addition permit Date: September 23, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 492070 | |||||
Addition permit Date: September 9, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 556730 | |||||
Mechanical permit Date: November 20, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 501152 | |||||
Sign permit Date: September 13, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 296799 | |||||
Administrative permit Date: April 29, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 210025 | |||||
Zoning use permit Date: September 3, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 555430 | |||||
Zoning use permit Date: September 6, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 490408 | |||||
Zoning use permit Date: September 3, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit status: Completed | Permit id: 235284 | |||||
On may 3, 2010, the department of license & inspections issued a notice of refusal for application #269698. Date: May 18, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Applicant: Sugarhouse Hsp Gaming, L.P. | Permit type: Appeal | Permit status: Approved | Permit id: 11748 | |||||
The department of licenses and inspections findings must be reversed and the violation must be vacated. Date: December 8, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Applicant: James D. Schultz, Esq. | Permit type: Appeal | Permit id: 29360 | |||||
Expansion of the existing steel framed casino building with a two story (plus penthouse). Steel framed addition and a seven story , precast parking garage. Associated sitework, landscaping, flatwork and roadway work will also be performed. Date: December 2, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Addition permit | Permit status: Completed | Completion date: August 29, 2016 | Permit id: 566234 | |||||
SCORE 100 Installation of audio visual per plans. Installation to comply with 2005 nec articles 300. 21 & 725. 3. Date: June 8, 2010 Contractor: M Gitlin Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2015 | Permit id: 274656 | |||||
SCORE 100 Amend permit# 2450 to reflect new changes as per plans. Date: July 15, 2010 Contractor: Keating Building Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 269698 | |||||
SCORE 100 Install temporary service per single line diagram. Date: July 9, 2010 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: August 20, 2016 | Permit id: 274094 | |||||
SCORE 99 For the installation of a fire supression system in interim poker room space, proposed fire supression system to tie into existing six (6) inch fire main with an existing back flow preventer assebmly. All work to be done per approved plans, if field conditions vary contact design engineer prior to the start of any work. Fire supression system installed in accordance with nfpa 13. Date: October 29, 2014 Contractor: Wayman Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: October 31, 2014 | Permit id: 560736 | |||||
SCORE 100 Phila fire dept - fire code unit -outdoor fireworks approval 11 27 2012 . Update pfd submitted a date change due to rain from 11 27 2012 to 11 29 2012 Date: November 27, 2012 Contractor: Pyrotecnico Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 22043 | |||||
SCORE 100 Phila fire dept - fire code unit - outdoor fireworks approval 05 26 2012 various Date: May 2, 2012 Contractor: Pyrotecnico Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 21571 | |||||
SCORE 100 Temporary certificate of occupancy for casino. Date: August 26, 2010 Contractor: Keating Building Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: August 30, 2010 | Permit id: 297977 | |||||
SCORE 99 Adding a new kitchen exhaust system scope of work includes the new ductwork and 3 add. Exhaust fans as per plans. Date: July 20, 2010 Contractor: A.T. Chadwick Company Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 284757 | |||||
SCORE 95 Temporary c. O. Date: March 23, 2016 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: March 24, 2016 | Permit id: 678696 | |||||
SCORE 99 Erection of two (2) flatwall (signs 1 and 2) and two (2) freestanding signs (sign 4). Date: September 13, 2010 Contractor: Urban Sign And Crane Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Sign permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 296799 | |||||
For the enclosure of a "open" terrace, the erection of a one (1) story addition (modular office), additional roof top mechanicals penthouses and the erection of five (5) signs, size and location as shown in application. All accessory to an existing casino complex to include 1,7 slot machines and a nite club on the first floor with accessory offices on the second floor (mezzanine) with accessory storage and food prep throughout, revise parking to 1081 total, 37 accessible and 317 compact spaces. ( total accessory parking on ap # 269718 , 1516 spaces ). Date: July 8, 2010 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 287929 | |||||
Rough grading site work permit only. Excavation grading of the site (uplands only) to support the construction of phase i improvements, as noted in the attached earthwork package of plans. Work shall include, but not be limited to, excavation, removal of existing surface and subsurface features, and installation of erosion and sedimentation controls, pursuant to the approved dep e&s plans. Work shall not commence in the remaining areas of archeological concern until clearance is obtained from the phmc and usace. Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: New construction permit | Permit status: Completed | Completion date: August 31, 2010 | Permit id: 124758 | |||||
For the relocation of lot lines to create one (1) lot from seven (7) lots. Size and location as shown in the application. Date: January 2, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 124218 | |||||
SCORE 100 09 23 2011 erection of (1) assembly use tent Date: September 27, 2011 Contractor: Select Event Rentals Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 21163 | |||||
Preliminary plan review for original casino plan Date: April 29, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: April 29, 2009 | Permit id: 210025 | |||||
SCORE 100 12 29 10-erection of (1)-assembly use tent to be used as weather protection Date: December 30, 2010 Contractor: Knight Enterprises Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 20875 | |||||
SCORE 95 Installation of an automatic sprinkler system. Date: February 19, 2010 Contractor: S A Comunale Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 259032 | |||||
SCORE 95 Tco Date: January 15, 2016 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: February 1, 2016 | Permit id: 663933 | |||||
SCORE 95 Temporary t. C. O. Date: December 31, 2015 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: December 31, 2015 | Permit id: 653749 | |||||
SCORE 100 Install 4 ansul r-102 wet chemical commercial kitchen fire suppression system ez standard kitchen fire suppression- for the installation of new wet chemical kitchen hood fire suppression system as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: November 24, 2015 Contractor: Atlantic Fire Equipment Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: April 8, 2016 | Permit id: 654130 | |||||
Temporary certificate of occupancy for the precast parking structure. The tco will apply to only floors 3-7, as well as the full length of the garage ramps. Occpancy of floors 3-7 will be phased. Date: November 6, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: December 30, 2015 | Permit id: 646318 | |||||
Application for signs only as part of casino. Date: May 2, 2016 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 8, 2016 | Permit id: 646436 | |||||
SCORE 100 Install of power, feeder, conduit, lighting & security & low voltage cabling as per nec 2008 & fire alarm as per nfpa 72 east district Date: August 12, 2015 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: August 24, 2016 | Permit id: 606782 | |||||
SCORE 100 Extend existing nfpa 13 sprinkler system into addition. Date: January 6, 2014 Contractor: Majek Fire Protection, Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 506354 | |||||
SCORE 100 Installation of (3) ansul r-102 comml kitchen fire suppression systems Date: July 15, 2010 Contractor: Atlantic Fire Equipment Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 284706 | |||||
SCORE 100 Install exhaust hoods and ductwork as per plan. Date: August 6, 2010 Contractor: Atlantic Fire Equipment Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 284713 | |||||
SCORE 100 Hvac installation includes 2-new van boxes. Relocate 2 existing van boxes, 55-diffuseers, install new ductwork as per plan. Date: October 12, 2017 Contractor: Elliott Lewis Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Active | Completion date: November 30, 2017 | Permit id: 818361 | |||||
SCORE 100 Interior mechanical alterations on first level to include a rooftop unit as per approved plans. Date: November 20, 2013 Contractor: Devine Brothers Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 501152 | |||||
SCORE 100 Install 400a service 1-phase service to office trailer. Date: November 10, 2008 Contractor: Harry B Miller Iii Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: January 13, 2009 | Permit id: 187153 | |||||
SCORE 100 10 8 09-erection of (1)-30x assembly use tent for sugar house casino ground breaking ceremony Date: October 7, 2009 Contractor: Jefmar Party Rentals Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 19922 | |||||
Foundation permit only. Construction of the foundation systems for the parking garage and casino structure, including but not limited to excavation, installation of piles and installation of cast-in-place concrete. Other clearance from usace required. Date: March 27, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: New construction permit | Permit status: Abandoned | Completion date: December 2, 2009 | Permit id: 199642 | |||||
SCORE 86 Installation of one (1), 11-3" wide ul 7 listed, type i commercial kitchen exhaust hood in accordance with the 2009 international mechanical code. Work includes connection to ductwork previously installed under mechanical permit # 707285. Separate permits required for all fire suppression and electrical work. Date: September 2, 2016 Contractor: J And S Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 25, 2016 | Permit id: 712442 | |||||
SCORE 95 Day t. C. O. Date: March 21, 2016 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: March 21, 2016 | Permit id: 659473 | |||||
SCORE 100 Install complete electrical power,lighting,communications,voice data,security,cctv,catv for the sugarhouse casino as per 2005 nec (east district) fire alarm as per nfpa 72 Date: February 18, 2010 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: February 23, 2011 | Permit id: 255397 | |||||
For the erection of a two (2) story structure (34 high) with rooftop mechanicals, penthouses, canopies and architectural embellishments and for the erection of fences (48"- high) and an emergency generator. Size and location as shown in the application. For use as a casino complex to include 17 slot machines and a night club on the first floor and accessory offices on the second floor (mezzanine) with accessory storage and food prep throughout. And for the creation of 1,105 open-air accessory off-street parking spaces (including 25 handicap spaces and 4 van spaces), 28 reservoir spaces and 4 loading spaces. No signs this permit. Date: September 3, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 235284 | |||||
SCORE 100 07 05 2013 phila fire dept - fire code unit - outdoor fireworks approval various 1. 3g. Class b aerial shells 1388 Date: July 1, 2013 Contractor: Pyrotecnico Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 22434 | |||||
Foundation permit only. Construction of the foundation systems for the interim casino structure, including but not limited to excavation, installation of piles and installation of cast-in-place concrete. Date: September 4, 2009 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: New construction permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 235157 | |||||
SCORE 100 Amending mechanical permit #2490 to add (7) energy recovery units to be installed on the roof top in conjunction with the air handing units. Date: August 5, 2010 Contractor: A T Chadwick Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 286501 | |||||
SCORE 100 Install pre action for mechanical equipment 12 control panels, smoke detectors, 7 low air sensors, 11 heat detectors, 7 tamper switches, 3 pull stations 3 horns strobes, 7 water flow as per 2005 nec (east district) Date: August 2, 2010 Contractor: Aubrey Green Elect Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Expired | Completion date: August 2, 2010 | Permit id: 287839 | |||||
SCORE 100 Amend mechanical permit # 2490 as per plan. Date: August 18, 2010 Contractor: Keating Building Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: June 2, 2014 | Permit id: 296352 | |||||
For the erection of an addition, including a private parking garage, to an exist. Detached building w. Off-street private parking lot; size & location as shown in approved plans w. Lowest floor elevation (18) inches min. Above base flood elevation. For use as assembly & entertainment casino, nightclub & private club, sit-down restaurant, & personal services (spa w. No activity as defined in 14-601(7)(a)(. 4)) as an expansion of an exist. Gaming facility, with all other uses as previously approved, w. Accessory off-street parking for (2,611) space, including (48) accessible spaces & (11) van accessible spaces, & accessory signage as previously approved. See zoning permit# 5554 for zoning use registration permit application. Date: September 23, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 23, 2014 | Permit id: 562949 | |||||
SCORE 95 Complete new plumbing including 188 fixtures (casino) the installation will comply with the philadelphia plumbing code 2004 Date: February 10, 2015 Contractor: Falasca Mechanical Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 13, 2016 | Permit id: 586057 | |||||
SCORE 95 Earthwork, pile driving, installation of pile caps andinstallation of on grade structural slab for both expanded casino footprint and the parking garage. Limited modification to existing building facade. Date: October 7, 2014 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: New construction permit | Permit status: Completed | Completion date: September 13, 2016 | Permit id: 559761 | |||||
SCORE 100 Wire and install 3 new panels to feed a temp structure to house a poker room at sugarhouse, install receptacles, lighting,teledata, security, lightning protection, and grounding as per 2008 nec (east district) install on fa panel and associated devices for the temp poker room as per nfpa72 Date: October 3, 2014 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: June 12, 2015 | Permit id: 562783 | |||||
SCORE 95 Installation of three clean agent fm-2 fire suppression systems including fm-2 storage cylinders & nozzles (it room, surv. Equipment room and lv room) as per plans. Date: August 20, 2010 Contractor: Comprehensive Fire Technologie Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 282855 | |||||
SCORE 100 Mechanical applicance work to include installation of ductless units, rooftop units and erus as per approved plans. Separate permit required for ductwork installation Date: August 10, 2016 Contractor: Herman Goldner Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 21, 2016 | Permit id: 705743 | |||||
SCORE 100 Install new plumbing fixtures, sinks, urinals, water closets, mop sink, roof drains, floor drains, installing new water f and soil pipe associated with the new fixtures inside of building, site work is by others Date: December 3, 2009 Contractor: A T Chadwick Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 249026 | |||||
SCORE 100 Philadelphia fire department - fire code unit - fireworks approval - sugarhouse casino - 9 29 17 @845pm Date: September 29, 2017 Contractor: Pyrotecnico Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 25167 | |||||
SCORE 86 New restaurant being built in exsiting shell space within casino, including lighting and power as per 2008 nec (east district) install new fire alarm as per nfpa72 Date: November 4, 2016 Contractor: Independence Electric Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2016 | Permit id: 711671 | |||||
SCORE 100 12 30 2012 erect one (1) assembly use tent for sugar house casino Date: December 19, 2011 Contractor: Select Event Rentals Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 21307 | |||||
SCORE 100 2 22 2012 erection of two (2) assembly use tents for sugar house casino Date: March 9, 2012 Contractor: Knight Enterprises Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 21468 | |||||
SCORE 99 Amend permit #604649 dry standpipe to protect 7 levels of new parking garage. Installation in accordance with nfpa 13. Date: May 4, 2016 Contractor: Wayman Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: June 9, 2016 | Permit id: 681639 | |||||
SCORE 100 Install branch ckt wiring & raceways for art work signage boxes & up lights using available spaces in existing panel as per nec 2008 east district Date: March 4, 2016 Contractor: Adams Electrical Const Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: August 29, 2016 | Permit id: 665781 | |||||
SCORE 99 Relocate (59) existing sprinkler heads Date: October 10, 2013 Contractor: Wayman Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: January 8, 2015 | Permit id: 499734 | |||||
SCORE 100 Install of new lighting & power for high limits lounge, remove & reinstall fire alarm devices, install 1-208 1 volt 225 amp panelboard as per nec 2008 & nfpa 72 (casino) Date: November 8, 2013 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: August 20, 2016 | Permit id: 499743 | |||||
Preliminary plan review for expansion of existing casino building and the construction of a 15 parking space garage. Date: May 29, 2015 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: June 22, 2015 | Permit id: 537032 | |||||
SCORE 100 Level ii alterations as per plan. Separte permit is required for m. E. P. S. Date: September 19, 2017 Contractor: Ernest Bock And Sons Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Alteration permit | Permit status: Active | Completion date: November 30, 2017 | Permit id: 806431 | |||||
SCORE 100 Install 1 kw and 56 kw generator, temporary power for video, lighting, and television. Inspection friday 9 23 11 event 9 24 11 12pm to 10pm as per 2008 nec (east district) Date: September 22, 2011 Contractor: Caniglia And Co Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: October 21, 2011 | Permit id: 360720 | |||||
SCORE 86 Install (1) ul 3 wet chemical system Date: September 2, 2016 Contractor: J And S Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 29, 2016 | Permit id: 719480 | |||||
For the erection of an addition to an existing building, addition to extend the use of an existing eat-in restaurant. All work to be done per approved plans. Building to be fully sprinklered. Separate permits required for mechanical,electrical and fire supression work. Date: September 23, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Addition permit | Permit status: Completed | Completion date: January 10, 2014 | Permit id: 492070 | |||||
SCORE 100 Installing new hvac equipment and associated duct work as per plan. Separate permit is required for commercial cooking exhaust system. Date: February 5, 2010 Contractor: Chadwick Service Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 249040 | |||||
For the erection of a three (3) ten (10) eleven (11) story structure with canopies and for the erection of three (3) generators. Size and location as shown in the application. For a casino complex for uses as permitted in the commercial entertainment district to include licensed gaming facilities, off-track betting facilities, restaurants and nightclubs (use registration permits required prior to occupancy). For 3,0 interior and exterior accessory off-street parking spaces and for six (6) off-street loading spaces. Date: January 4, 2008 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 119990 | |||||
SCORE 99 For the installation of two (2) flatwall, internally-illuminated signs on elevator tower. All other existing signs as previously approved to remain. Separate permits to be required for electrical work. Date: August 26, 2016 Contractor: L And H Sign Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Sign permit | Permit status: Completed | Completion date: September 13, 2016 | Permit id: 687657 | |||||
SCORE 95 1 day t. C. O. Date: April 28, 2016 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: May 3, 2016 | Permit id: 687852 | |||||
SCORE 65 Sanitary sewer for new casino at sugarhouse Date: November 24, 2009 Contractor: Francis Lally Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 248437 | |||||
SCORE 100 3 11 16 erect assembly tent 80x1 - application received 3 14 16 Date: March 14, 2016 Contractor: Tlmes Corp Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 24059 | |||||
SCORE 100 Relocate power and low voltage wiring to slot machines, table games, lighting and signs per submitted drawings as per 2008 nec (east dist) Date: July 28, 2011 Contractor: Gordon Group Electric Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: November 9, 2011 | Permit id: 353109 | |||||
SCORE 99 Signs Date: September 15, 2016 Contractor: L And H Sign Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Sign permit | Permit status: Completed | Completion date: May 15, 2017 | Permit id: 716318 | |||||
SCORE 65 For interior renovations to include interior partition wall installations, new structural roof framing, floor slab alterations, interior wall ceiling floor finishing, and access service counter installation. (iebc 2009, compliance path: work-area method, lvl ii alterations) separate permits to be required for plumbing, electrical, mechanical, and fire suppression system alterations. Date: July 26, 2016 Contractor: The Norwood Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Alteration permit | Permit status: Completed | Completion date: November 21, 2016 | Permit id: 693884 | |||||
SCORE 100 Rework of existing ductwork and addition of diffueses for new noodle bar as per plan. Date: July 26, 2016 Contractor: Chadwick Service Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 25, 2016 | Permit id: 707285 | |||||
SCORE 86 Install five (5) kitchen hoods as per plans. Exhaust ductwork and fans to be issued under separate permit. Date: November 16, 2015 Contractor: J And S Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 8, 2016 | Permit id: 649007 | |||||
SCORE 100 New construction of structure as per plans. Street department gives approval for the building permit of sugarhouse casino with the following conditions: (1). Must complete hop process with penndot by january 1, 2010. (2). Must complete design plans as required by hop for roadway and traffic signals by february 1, 2010. (3). All road work and traffic signal work must be completed by opening day of the casino. Separate permit is required for certificate of occupancy and lawful occupancy signs. Date: December 4, 2009 Contractor: Keating Building Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: New construction permit | Permit status: Completed | Completion date: November 24, 2010 | Permit id: 245090 | |||||
SCORE 99 Chemical extinguishing fire suppression system for commercial kitchen exhaust hood for sugarhouse casino restaurant Date: September 19, 2011 Contractor: H And H Systems Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 11, 2011 | Permit id: 361850 | |||||
Extension of an open terrace and partial enclosure of the same, to include hvac duct enclosure,with a corresponding ornamental enclosure on the opposite side (size and location as shown on the application). For the extension of existing eat-in restaurant night club with outdoor dining as part of an existing casino complex to include 1,7 slot machines and a nite club on the first floor with accessory offices on the second floor (mezzanine) with accessory storage and food prep throughout, parking spaces 1081 total, 37 accessible and 317 compact spaces. ( total accessory parking on ap # 269718 , 1516 spaces ). Date: September 6, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 14, 2014 | Permit id: 490408 | |||||
SCORE 100 Alterations: interior plumbing for casino - the installation will comply with the philadephia plumbing code 2004 Date: August 10, 2016 Contractor: Chadwick Service Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 29, 2016 | Permit id: 707289 | |||||
SCORE 95 Tco for employee dining room, employee quiet room and associated back of house corridors spaces. Date: May 17, 2016 Contractor: Skanska Usa Building Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: May 20, 2016 | Permit id: 692566 | |||||
SCORE 93 Ez permit sprinkler relocation (nfpa 13)- for the relocation of sprinkler heads as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: July 6, 2016 Contractor: Harring Fire Protection Llc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: November 29, 2016 | Permit id: 705246 | |||||
SCORE 99 Installation of additional sprinklers,lines. Add 4 new dry systems and dry standpipe to protect 2 levels of new parking garage. Add 4 new wet systems to protect new casino level and banquet level, renovations of existing system, nfpa 13. See calcs & plans for additional detail on scope of work. Date: July 6, 2015 Contractor: Wayman Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Completed | Completion date: September 12, 2016 | Permit id: 604649 | |||||
SCORE 93 For mechanical alterations to include new registers diffusers, mechanical appliances, and associated ductwork for a new museum as per approved plans. Date: April 7, 2015 Contractor: Bonland Industries Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: January 27, 2017 | Permit id: 593062 | |||||
SCORE 100 Philadelphia fire department - fire code unit -fireworks approval- sugarhouse casino barge waterfront - 5 7 16 - 9pm grand opening Date: April 19, 2016 Contractor: Pyrotecnico Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Expired | Permit id: 24136 | |||||
SCORE 100 Remove existing kitchen sink mop reception and hot water heater install 1 new floor drain with piping 3" install 1 new kitchen sink with sanitay and water piping install 1 new mop receptor with sanitary and water install 1 new hot water heater. Date: September 22, 2017 Contractor: Elliott Lewis Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Active | Completion date: November 30, 2017 | Permit id: 811478 | |||||
SCORE 86 Install 2 kitchen exhaust hood systems , associated duct work, fans,mechanicals. Date: November 4, 2015 Contractor: J And S Fire Protection Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 8, 2016 | Permit id: 643425 | |||||
SCORE 65 Ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: March 24, 2017 Contractor: The Norwood Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Demolition permit | Permit status: Completed | Completion date: June 17, 2017 | Permit id: 769331 | |||||
SCORE 93 Partial demolition of existing ductwork at first floor level; installation of new ductwork with associated grilles, registers, diffusers, vav units and fire dampers per plans in casino and banquet levels at new addition. This approval does not include rooftop units or commercial kitchen exhaust hoods suppression systems. Separate permits required for all electrical, plumbing and fire suppression work. Date: March 20, 2015 Contractor: Bonland Industries Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: September 12, 2016 | Permit id: 588806 | |||||
SCORE 65 Interior alterations to include millwork in refinery, remove glass low wall and modify location of high limit entry with new millwork. Date: August 17, 2011 Contractor: Wyatt Incorporated Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Alteration permit | Permit status: Completed | Completion date: November 17, 2011 | Permit id: 353156 | |||||
SCORE 86 New commercial kitchen exhaust hood existing kitchen exhaust duct work for sugarhouse casino restaurant Date: September 19, 2011 Contractor: General Rest Equipment Supply Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 11, 2011 | Permit id: 360969 | |||||
For level ii alterations to existing east west restroom on ground floor, alterations to include the demoltion removal of existing partition walls and fixtures and provide new parition walls, fixtures and furnishes. All work to be done per approved plans. Separate permits required for mechanical, electrical and plumbing work. Date: October 3, 2013 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Alteration permit | Permit status: Completed | Completion date: January 15, 2014 | Permit id: 496317 | |||||
SCORE 100 Install receptacles,lights and fiber data drop per 2008 nec (casino) no fire on this permit Date: November 3, 2017 Contractor: Mjk Electrical Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Active | Completion date: November 3, 2017 | Permit id: 821333 | |||||
SCORE 100 Relocate (72) existing sprinkler heads. (commercial) Date: October 4, 2017 Contractor: Patriot Sprinkler Company Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Suppression permit | Permit status: Active | Completion date: November 30, 2017 | Permit id: 821549 | |||||
For the erection of an detached building w. Off-street private parking lot & erection of one (1) animated illumination roof sign; size & location as shown in approved plans w. Lowest floor elevation (18) inches minimum above base flood elevation. For use as assembly & entertainment casino on the same lot as an exist. Gaming facility, w. Maximum of 17 gaming positions, w. Nightclub & private club, sit-down restaurant, accessory business & professional offices, accessory private parking lot for (1081) on-site spaces & (435) off-site spaces on immediately adjoining lot, including (321) compact spaces & (37) accessible spaces, for a total of (1516) spaces per zoning use registration permit# 269718, & accessory signage. Date: September 3, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 19, 2014 | Permit id: 555430 | |||||
Erection of a standalone, pre-engineered structure adjoining csino building to be used as a temporary poker room until the permanent poker room is completed as part fo the phase ia expansion project. Structure will be dismantled when permanent poker room opens. Permit application is for building only. Separate permit required for mechanical, electrical and fire protection Date: September 9, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Addition permit | Permit status: Completed | Completion date: October 30, 2014 | Permit id: 556730 | |||||
For a lot adjustment to create one (1) lot from two (2) existing lots at 01001 n delaware ave (opa# 882028200) & 01107-19 n delaware ave (opa# 882028000); size & location as shown in approved plans. Date: September 12, 2014 Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Zoning permit | Permit status: Completed | Completion date: September 19, 2014 | Permit id: 555440 | |||||
SCORE 100 Amend permit #2450 as per plan. Separate permit required for office trailer. Date: August 18, 2010 Contractor: Keating Building Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Administrative permit | Permit status: Completed | Completion date: November 19, 2010 | Permit id: 289692 | |||||
SCORE 100 Installation of one x temporary tent structure located north of sugarhouse casino Date: September 23, 2015 Contractor: Jefmar Party Rentals Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Operations permit | Permit status: Completed | Permit id: 23778 | |||||
SCORE 100 Casino expansion for sugarhouse casino, all work performed is low voltage control wiring - 134-vav, 30-ef, 18-infared uh, 11-large rtu, 8-small rtu, 4-eru, 7-mua, 2-domestic hw heaters & lighting control interface as per nec 2008 east district Date: October 23, 2015 Contractor: Cahill Controls Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Completed | Completion date: August 24, 2016 | Permit id: 636545 | |||||
SCORE 100 Installing area drains,sinks,faucets,root drains 2 area drains,2 foot drains and replace 27 lavs (casino) Date: December 4, 2013 Contractor: Devine Brothers Inc Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 21, 2014 | Permit id: 501162 | |||||
SCORE 100 Fire alarm ground level rcp relocate one smoke detector on existing fire alarm system ceiling mounted,fire alarm system mezzanine level plan relocate 6-fire alarm combo speaker visual light ceiling mounted as per nfpa72 Date: December 5, 2017 Contractor: Mjk Electrical Corporation Client: Sugarhouse Hsp Gaming Lp | Client Company: Gregory A Carlin | Permit type: Electrical permit | Permit status: Active | Completion date: December 5, 2017 | Permit id: 829631 | |||||
Operations permit Date: June 20, 2013 Client: Sugarhouse Hsp Gaming Lp | Permit status: Completed | Permit id: 22415 | |||||
Operations permit Date: July 21, 2014 Client: Sugarhouse Hsp Gaming Lp | Permit status: Completed | Permit id: 23029 | |||||
SCORE 100 06 12 2013 erect assembly tent(15x40) at sugar house casino 1085 n delaware ave Date: June 20, 2013 Contractor: Knight Enterprises Inc Client: Sugarhouse Hsp Gaming Lp | Permit type: Operations permit | Permit status: Completed | Permit id: 22415 | |||||
SCORE 100 07 21 2014 erect assembly tent (30x50) sugar house casino ground breaking event Date: July 21, 2014 Contractor: Knight Enterprises Inc Client: Sugarhouse Hsp Gaming Lp | Permit type: Operations permit | Permit status: Completed | Permit id: 23029 |