Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Alteration permit Date: August 31, 2010 Client: General Electric Co | Permit status: Completed | Permit id: 297593 | |||||
Plumbing permit Date: December 28, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 445279 | |||||
Alteration permit Date: November 24, 2015 Client: General Electric Co | Permit status: Completed | Permit id: 642277 | |||||
Suppression permit Date: June 4, 2009 Client: General Electric Co | Permit status: Completed | Permit id: 216875 | |||||
Electrical permit Date: March 12, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 382697 | |||||
Electrical permit Date: December 7, 2015 Client: General Electric Co | Permit status: Expired | Permit id: 647231 | |||||
Suppression permit Date: June 26, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 406865 | |||||
Electrical permit Date: November 19, 2008 Client: General Electric Co | Permit status: Completed | Permit id: 182241 | |||||
Electrical permit Date: October 17, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 367187 | |||||
Suppression permit Date: June 29, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 349724 | |||||
Alteration permit Date: October 16, 2008 Client: General Electric Co | Permit status: Completed | Permit id: 181105 | |||||
Plumbing permit Date: April 26, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 337558 | |||||
Alteration permit Date: April 19, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 382150 | |||||
Alteration permit Date: September 12, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 354087 | |||||
Mechanical permit Date: October 25, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 370128 | |||||
Alteration permit Date: September 12, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 354087 | |||||
Electrical permit Date: December 7, 2015 Client: General Electric Co | Permit status: Expired | Permit id: 647231 | |||||
Alteration permit Date: August 31, 2010 Client: General Electric Co | Permit status: Completed | Permit id: 297593 | |||||
Suppression permit Date: July 8, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 346432 | |||||
Suppression permit Date: June 26, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 406865 | |||||
Suppression permit Date: June 4, 2009 Client: General Electric Co | Permit status: Completed | Permit id: 216875 | |||||
Plumbing permit Date: April 26, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 337558 | |||||
Electrical permit Date: July 22, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 350979 | |||||
Electrical permit Date: June 12, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 406732 | |||||
Plumbing permit Date: February 29, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 389660 | |||||
Mechanical permit Date: October 25, 2011 Client: General Electric Co | Permit status: Completed | Permit id: 370128 | |||||
Alteration permit Date: April 19, 2012 Client: General Electric Co | Permit status: Completed | Permit id: 382150 | |||||
Electrical permit Date: November 19, 2008 Client: General Electric Co | Permit status: Completed | Permit id: 182241 | |||||
Alteration permit Date: November 24, 2015 Client: General Electric Co | Permit status: Completed | Permit id: 642277 | |||||
Alteration permit Date: October 16, 2008 Client: General Electric Co | Permit status: Completed | Permit id: 181105 | |||||
SCORE 100 Separation of storm and sanitary sewer systems - installation of new storm water system (interior and exterior) - install new rest rooms and new siphonic roof drain system Date: February 29, 2012 Contractor: Lgb Mechanical Inc Client: General Electric Co | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 7, 2012 | Permit id: 389660 | |||||
SCORE 67 Installation of pre-fab building inside existing building for use as restroom with ramp and stairs. Separate pemits required for mechanical, electrical, plumbing and fire suppression. Date: April 19, 2012 Contractor: Panther Technologies Inc Client: General Electric Co | Permit type: Alteration permit | Permit status: Completed | Completion date: March 20, 2013 | Permit id: 382150 | |||||
SCORE 100 Replace (3) urinal and replace corroded piping. Date: December 28, 2012 Contractor: Lgb Mechanical Inc Client: General Electric Co | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 20, 2013 | Permit id: 445279 | |||||
SCORE 67 Removal of existing concrete floor. For the installation of x x 4 reinforced concrete foundation as per approved plans. Separate permit required for any mechanical, electrical, plumbing work. Date: November 24, 2015 Contractor: Panther Technologies Inc Client: General Electric Co | Permit type: Alteration permit | Permit status: Completed | Completion date: February 27, 2016 | Permit id: 642277 | |||||
SCORE 100 Install new 15kv switch gear with step down transformer as per 2008 nec (east district) Date: December 7, 2015 Contractor: Albarell Electric Inc Client: General Electric Co | Permit type: Electrical permit | Permit status: Expired | Completion date: December 7, 2015 | Permit id: 647231 | |||||
Installation of vent piping from existing process equipment. Vent piping is through wall for the processi tank and through the roof for the oven. Date: October 25, 2011 Client: General Electric Co | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 1, 2012 | Permit id: 370128 | |||||
SCORE 100 Furnish and install new deisel fire pump with new concrete housekeeping pad and metal shed to replace existing pump. Relocate existing fire dept connection and dvc backflow preventor to pump room install in accrodance with nfpa 20. Date: June 29, 2011 Contractor: Independence Fire Sprinkler Co Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: August 10, 2011 | Permit id: 349724 | |||||
SCORE 89 Supply and install 3 4 back flow preventor and meter with piping Date: April 26, 2011 Contractor: Joseph Oboyle Client: General Electric Co | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 31, 2011 | Permit id: 337558 | |||||
SCORE 100 For the installation of fire suppression system to include piping, sprinkler heads, and backflow prevention assembly and to connect to existing wet sprinkler riser as per plan. Date: July 8, 2011 Contractor: Independence Fire Sprinkler Co Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: August 10, 2011 | Permit id: 346432 | |||||
SCORE 100 Replace for faultty valve in riser #3. 6" size see wall post indicating valve in kind Date: September 8, 2009 Contractor: Keystone Fire Protection Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: September 22, 2009 | Permit id: 226833 | |||||
Remove existing slag and built up roof. Install 2. 5" insulation and new tpo roof membrane roof covering. Date: August 31, 2010 Client: General Electric Co | Permit type: Alteration permit | Permit status: Completed | Completion date: April 18, 2011 | Permit id: 297593 | |||||
SCORE 56 Install new feeder from existing b-19 to bathroom trailer unit. Instll new gfci and flood alarm and power to solenoids as per 2008 nec(industrial)(east dist) Date: March 12, 2012 Contractor: Harry W Gibson Jr Client: General Electric Co | Permit type: Electrical permit | Permit status: Completed | Completion date: October 10, 2012 | Permit id: 382697 | |||||
SCORE 100 Install new heads to existing fire suppression system in accordance with nfpa 13 throughout the restroom area. All work shall comply with the approved plans. All work shall be performed by a fire suppression contractor licensed by the city of philadelphia. Date: June 26, 2012 Contractor: Independence Fire Sprinkler Co Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: November 7, 2012 | Permit id: 406865 | |||||
SCORE 100 Furnish and install new foam suppression system as per plan. Date: October 27, 2011 Contractor: Independence Fire Sprinkler Co Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: June 4, 2012 | Permit id: 369651 | |||||
SCORE 56 Interior alterations to create a room. Date: October 16, 2008 Contractor: Clean Harbor Client: General Electric Co | Permit type: Alteration permit | Permit status: Completed | Completion date: September 21, 2009 | Permit id: 181105 | |||||
SCORE 99 Lighting, recepts, connection of 7 well pumps and control panel as per 2005 nec (east district) Date: November 19, 2008 Contractor: Riggs Distler And Co Inc Client: General Electric Co | Permit type: Electrical permit | Permit status: Completed | Completion date: September 11, 2009 | Permit id: 182241 | |||||
SCORE 100 Installation of dry sprinkler system for unheated space, as per plans and calcs, to extg system. Date: June 4, 2009 Contractor: Cintas 2 Corporation Client: General Electric Co | Permit type: Suppression permit | Permit status: Completed | Completion date: September 22, 2009 | Permit id: 216875 | |||||
SCORE 100 Install 1-480v 400a auto transfer sww, 1 generator tap box, panel board, 1 45kva transformer. 1-175a 208 120v panel board and 1 enclose circ breaker as per 2008,transformer secondary conductors to comply with art. 240. 21(c)(2). Date: June 12, 2012 Contractor: Albarell Electric Inc Client: General Electric Co | Permit type: Electrical permit | Permit status: Completed | Completion date: July 25, 2012 | Permit id: 406732 | |||||
SCORE 100 Provide 200amp, 3 phase feeder to imprex inc, control panel, install raceways (conduit) to install factory supplied wiring to vpi tank controls, furnish and install two light fixtures as per 2008 nec (east district) Date: October 17, 2011 Contractor: Albarell Electric Inc Client: General Electric Co | Permit type: Electrical permit | Permit status: Completed | Completion date: December 6, 2011 | Permit id: 367187 | |||||
SCORE 100 Install 1 100amp bus duct switch, 1 75kva transformer,1 250amp circuit panel, install 4 fixtures,1 exit sign, 1 heater,1 switch, 1 gfci receptacle and control wiring as per 2008 nec Date: July 22, 2011 Contractor: Albarell Electric Inc Client: General Electric Co | Permit type: Electrical permit | Permit status: Completed | Completion date: September 12, 2011 | Permit id: 350979 | |||||
Installation of a masonary containment dike for vpi installation. Construction of a new steel access platform. Date: September 12, 2011 Client: General Electric Co | Permit type: Alteration permit | Permit status: Completed | Completion date: December 27, 2011 | Permit id: 354087 |