Addition permit Date: April 10, 2014 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 515898 | |||||
Alteration permit Date: November 3, 2010 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 296661 | |||||
Zoning use permit Date: March 20, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 455399 | |||||
Electrical permit Date: May 27, 2014 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 532679 | |||||
New construction permit Date: April 29, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 458511 | |||||
Administrative permit Date: October 3, 2014 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 550545 | |||||
Suppression permit Date: May 20, 2010 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 280321 | |||||
Zoning use permit Date: December 23, 2010 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 317005 | |||||
Electrical permit Date: January 31, 2011 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 322741 | |||||
Administrative permit Date: February 1, 2016 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 666898 | |||||
Mechanical permit Date: August 1, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 475140 | |||||
Zoning permit Date: April 22, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 465435 | |||||
Suppression permit Date: October 23, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 492208 | |||||
Electrical permit Date: July 29, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 477226 | |||||
Administrative permit Date: April 2, 2013 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 462436 | |||||
Zoning use permit Date: December 22, 2014 Client: Tenet Healthsystem | Permit status: Completed | Permit id: 500350 | |||||
Construction of a (6) story addition to hospital for children. A new padot streets dept approved driveway and relocated traffic signal will be constructed. Consolidation done on permit#491665. The purpose of this application is to document current uses as hospital, medical office, and accessory parking garage, and proposed addition. Date: December 22, 2014 Client: Tenet Healthsystem | Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 22, 2014 | Permit id: 500350 | |||||
SCORE 95 Installation of portion of new fire sprinkler system interior, with 50" exterior piping for future tie into exterior 6" connection and exterior meter pit containing backflow assembly by others( separate permit required by others for exterior meter pit and backflow assembly, fire hydrant installations ). Owner responsible for any system deviations or hold up due to additional plan review for exterior portion of installation, required to have all sprinkler system components installed and permitted for certification. Date: October 23, 2013 Contractor: S A Comunale Co Inc Client: Tenet Healthsystem | Permit type: Suppression permit | Permit status: Completed | Completion date: November 23, 2014 | Permit id: 492208 | |||||
SCORE 97 New construction of 2 story structure, associated civil - site work. Building to be fully sprinklered. Additional permits required : electrical, plumbing ,hvac, sprinklers, signs. Associated demo permits under 1 e erie r Date: April 29, 2013 Contractor: Torcon Inc Client: Tenet Healthsystem | Permit type: New construction permit | Permit status: Completed | Completion date: September 12, 2014 | Permit id: 458511 | |||||
For the reconfiguration of existing parking spaces and the creation of parking spaces in garage (242 spaces) and surface lot (823 spaces) for a total of 1065 including forty-two (42) accessible off-street parking spaces (seven (7) van accessible parking spaces). Size and location as shown in the application. Existing public parking lot and five (5) story parking garage on the same lot with existing steel warehouse, offices and all other uses as previously approved. Date: December 23, 2010 Client: Tenet Healthsystem | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 12, 2013 | Permit id: 317005 | |||||
For the lot adjustment to create one (1) lot from four (4) opa accounts and seven (7) deeded lots size and location as shown on application plans. Date: September 18, 2013 Client: Tenet Healthsystem | Permit type: Zoning permit | Permit status: Completed | Completion date: September 18, 2013 | Permit id: 495279 | |||||
SCORE 100 Relocate sprinkler heads(medical office building) Date: May 20, 2010 Contractor: Precision Sprinkler Services Client: Tenet Healthsystem | Permit type: Suppression permit | Permit status: Completed | Completion date: December 21, 2010 | Permit id: 280321 | |||||
SCORE 100 Renovations to make bldg more ada accessible. Furninsh & installing of ada doors & hardware. Correct accessibility clearances in bathrooms. Furnish & install signage correcting passages for public entry into exam suites as per plans. Date: November 3, 2010 Contractor: T N Ward Company Inc Client: Tenet Healthsystem | Permit type: Alteration permit | Permit status: Completed | Completion date: April 18, 2012 | Permit id: 296661 | |||||
SCORE 100 For the installation of two (2) rooftop mounted air handling units (ahus), two (2) rooftop mounted chiller units (cus), (330) terminal grilles, registers, diffusers (grds), & all associated supply, return, & exhaust ductwork for a two (2) story medical outpatient office building. Date: August 1, 2013 Contractor: Burns Mechanical Inc Client: Tenet Healthsystem | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 23, 2014 | Permit id: 475140 | |||||
SCORE 67 Administrative permit to change address on previously issued permit ap# 449030. Date: April 2, 2013 Contractor: Express Expeditors Client: Tenet Healthsystem | Permit type: Administrative permit | Permit status: Completed | Completion date: April 25, 2013 | Permit id: 462436 | |||||
For the demolition of an existing two(2) story structure, medical office building to remain (nelsion building ), for the erection of two(2) story structure, for the removal of 211 off-street parking spaces and for the creation of 167 off-street parking spaces including with 27 h c spaces including with 3 van spaces(total 217 off street parking spaces), for the creation of two(2) loading spaces and for the erection of eight(8) feet high fence on rear and side. Size and location as shown in the application. For an office building ( medical office ) including with 217 off-street parking spaces, 27 h c spaces and two(2) loading spaces. Date: March 20, 2013 Client: Tenet Healthsystem | Permit type: Zoning/use permit | Permit status: Completed | Completion date: June 12, 2013 | Permit id: 455399 | |||||
SCORE 95 Misc. Electrical device relocations as per 2008 nec ada requirements for toilet rooms (east dist) Date: January 31, 2011 Contractor: Hatzel And Buehler Inc Client: Tenet Healthsystem | Permit type: Electrical permit | Permit status: Completed | Completion date: August 6, 2012 | Permit id: 322741 | |||||
For the relocation of lot lines to create two lots from one lot.(size and location as shown on the application) Date: April 22, 2013 Client: Tenet Healthsystem | Permit type: Zoning permit | Permit status: Completed | Completion date: June 12, 2013 | Permit id: 465435 | |||||
Temporary certificate of occupancy so that vendors can occupy work area. Date: February 1, 2016 Client: Tenet Healthsystem | Permit type: Administrative permit | Permit status: Completed | Completion date: February 1, 2016 | Permit id: 666898 | |||||
SCORE 100 New construction new 1200amp service entrance switch board installation of lights & receptacles required for medical office bldg installation of site lighting incoming service 277 480v and is transformed down for power requirement on each fl per 2008 nec (medical office bldg) Date: July 29, 2013 Contractor: Shelly Electric Co Inc Client: Tenet Healthsystem | Permit type: Electrical permit | Permit status: Completed | Completion date: November 14, 2014 | Permit id: 477226 | |||||
SCORE 100 Installation of new fire alarm system i new building. Install head end notification devices and initiating devices to supplement work on permit 477226 per 2008 nec (medical office bldg) Date: May 27, 2014 Contractor: Shelly Electric Co Inc Client: Tenet Healthsystem | Permit type: Electrical permit | Permit status: Completed | Completion date: November 14, 2014 | Permit id: 532679 | |||||
SCORE 97 Amend permit #515898 to revised approved floor plan to leave partial 3rd and 4th floors as shell space. Separate co reqd for shell space.. Date: October 3, 2014 Contractor: Torcon Inc Client: Tenet Healthsystem | Permit type: Administrative permit | Permit status: Completed | Completion date: October 9, 2015 | Permit id: 550545 | |||||
SCORE 97 Tco for entire building Date: July 24, 2014 Contractor: Torcon Inc Client: Tenet Healthsystem | Permit type: Administrative permit | Permit status: Completed | Completion date: August 6, 2014 | Permit id: 551544 | |||||
New 5-story additon including patient care @ 1st four floors, mechanical equipemnt @ 5th floor, and helipad and access penthouse above 5th floor roof. Date: April 10, 2014 Client: Tenet Healthsystem | Permit type: Addition permit | Permit status: Completed | Completion date: March 7, 2016 | Permit id: 515898 |