Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 59 Construction of on-site sewer system Date: December 12, 2011 Contractor: Los Angeles Biomedical Research Engineer: Julio Ribeiro | Applicant: Valverde Michael | Permit status: Finaled | Completion date: February 20, 2013 | Expiration date: December 11, 2012 | Permit id: 1112120003 | |||||
SCORE 99 Construction of on-site domestic water system Date: December 12, 2011 Contractor: Architectural Design And Signs Inc Engineer: Julio Ribeiro | Applicant: Valverde Michael | Permit status: Finaled | Completion date: February 20, 2013 | Expiration date: December 11, 2012 | Permit id: 1112120016 | |||||
SCORE 100 Foundation with ada ramp for modular building Engineer: David Dahmen | Applicant: Brandall Modular Corp | Permit status: Finaled | Completion date: April 15, 2009 | Expiration date: January 10, 2004 | Permit id: 208070042 | |||||
SCORE 100 Foundation for modular building Engineer: David Dahmen | Applicant: Brandall Modular Corp | Permit status: Finaled | Completion date: April 15, 2009 | Expiration date: January 10, 2004 | Permit id: 208070052 | |||||
SCORE 93 Demolish bldg Applicant: Viking Equipment Corp | Permit status: Permisud | Expiration date: September 16, 2005 | Permit id: 409210016 | |||||
Relocate 2 south medical office building; interim helipad and ramps-oshpd review Date: May 8, 2007 Value: $700,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 2, 2008 | Expiration date: May 2, 2008 | Permit id: 508110057 | |||||
SCORE 93 Demo trailer b-2 Date: August 18, 2005 Contractor: M T M Construction Applicant: Moon | Permit status: Finaled | Completion date: September 1, 2005 | Expiration date: August 13, 2006 | Permit id: 508180088 | |||||
SCORE 95 Demo building n35 Applicant: Moon John | Permit status: Permisud | Expiration date: August 13, 2006 | Permit id: 508180094 | |||||
SCORE 95 Demolish building n24 Date: November 8, 2007 Contractor: Mtm Construction Applicant: John Moon | Permit status: Finaled | Completion date: December 13, 2007 | Expiration date: May 6, 2008 | Permit id: 711080083 | |||||
SCORE 95 Relocate modular trailers Applicant: Matt Dugan | Permit status: Finaled | Completion date: March 31, 2009 | Expiration date: April 18, 2009 | Permit id: 804100046 | |||||
SCORE 77 Non-structual tenant improvements Applicant: Trish Moyer | Permit status: Finaled | Completion date: May 26, 2009 | Expiration date: May 25, 2009 | Permit id: 810070062 | |||||
SCORE 77 Re-roof and repair with the hot-mop (asphalt) Applicant: Trish Moyer | Permit status: Finaled | Completion date: January 9, 2009 | Expiration date: April 27, 2009 | Permit id: 810290020 | |||||
SCORE 56 Install 36 sq. Ft modular bldg. Addition to existing Applicant: Brandall | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: March 10, 2011 | Permit id: 910140023 | |||||
SCORE 98 Relocation of central drive, south portion realignment Applicant: Fred Cravea | Permit status: Finaled | Completion date: December 15, 2010 | Expiration date: May 24, 2011 | Permit id: 912170033 | |||||
SCORE 99 Temporary shoring for basement excavation Applicant: Fred Cravea | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: March 22, 2011 | Permit id: 1001270008 | |||||
SCORE 95 Demo n1 building Applicant: Kim Kim | Permit status: Finaled | Completion date: March 8, 2010 | Expiration date: February 11, 2011 | Permit id: 1002110054 | |||||
SCORE 95 Add new 2 s. F. Metal canopy over existing trash enclosure. Applicant: Giordano Marco | Permit status: Finaled | Completion date: September 10, 2010 | Expiration date: April 22, 2011 | Permit id: 1003080080 | |||||
SCORE 95 Add 1 new sign 8x 6. Applicant: Dugan Matt | Permit status: Finaled | Completion date: June 4, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220028 | |||||
SCORE 95 Add 1 new sign 4x 6. Applicant: Dugan Matt | Permit status: Finaled | Completion date: June 1, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220029 | |||||
SCORE 98 Sitework including restriping for parking & pedestrian walk ways Applicant: Fred Cravea | Permit status: Finaled | Completion date: January 16, 2014 | Expiration date: December 8, 2011 | Permit id: 1007060071 | |||||
SCORE 98 Demolition of (1) story bldg 28 sq ft Applicant: Duran Nicolas | Permit status: Finaled | Completion date: September 28, 2010 | Expiration date: September 16, 2011 | Permit id: 1009160044 | |||||
SCORE 99 Photovoltaic panel anchorage details & calcs for new freestanding parking structure. Engineer: Craig Williamson | Applicant: Duran Nick | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: December 28, 2011 | Permit id: 1011170003 | |||||
Washer/disinfector relocation to warehouse Date: September 7, 2011 Value: $45,000 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1106290077 | |||||
SCORE 99 Foundation & pole only for the sign Engineer: Julio Ribeiro | Applicant: Cohen Barb | Permit status: Permisud | Expiration date: September 26, 2012 | Permit id: 1109140014 | |||||
SCORE 99 Prefabricated atm kiosk on concrete foundation Applicant: Eric Gribble | Permit status: Finaled | Completion date: August 24, 2013 | Expiration date: May 10, 2013 | Permit id: 1205010070 | |||||
SCORE 99 New 120l x 4h site retaining wall adjacent to atm kiosk Engineer: Khr Associates Consulting Engineers | Applicant: Eric Gribble | Permit status: Permisud | Expiration date: June 6, 2013 | Permit id: 1205100077 | |||||
SCORE 99 Non-combustible canopy projection above 3rd tier(roof level) elevator door for freestanding parking structure Engineer: James Mckenzie | Applicant: Nicholas Duran Cravea | Permit status: Finaled | Completion date: December 17, 2013 | Expiration date: May 23, 2014 | Permit id: 1303280036 | |||||
SCORE 95 Demolition of interim helistop 25 sq ft Date: December 4, 2013 Contractor: Torres Construction Corp Applicant: Eduardo Ruvalcaba | Permit status: Finaled | Completion date: February 12, 2014 | Expiration date: December 4, 2014 | Permit id: 1312040038 | |||||
SCORE 100 Temp. Powaer poles Date: March 12, 2007 Contractor: National Construction Rentals Applicant: Santillan Deleit | Permit status: Finaled | Completion date: July 4, 2007 | Expiration date: September 8, 2007 | Permit id: 703120008 | |||||
SCORE 100 Temp. Power poles Date: April 30, 2007 Contractor: National Construction Rentals Applicant: Santillan Deleit | Permit status: Finaled | Completion date: May 3, 2007 | Expiration date: October 27, 2007 | Permit id: 704300047 | |||||
Relocate 2 south medical office building; interim helipad and ramps-oshpd review Date: May 8, 2007 Applicant: Same As Owner | Permit status: Finaled | Completion date: May 22, 2007 | Expiration date: November 4, 2007 | Permit id: 705080030 | |||||
SCORE 100 1 temp. Pole & 1 sub-pole Date: September 18, 2007 Contractor: Power Plus Applicant: Zamora Carlos | Permit status: Finaled | Completion date: September 24, 2007 | Expiration date: March 16, 2008 | Permit id: 709180020 | |||||
SCORE 95 Relocate modular trailers Date: October 20, 2008 Contractor: Mackone Development Inc Applicant: Matt Dugan | Permit status: Finaled | Completion date: April 1, 2009 | Expiration date: April 18, 2009 | Permit id: 809040014 | |||||
SCORE 99 Non-structural tenant improvement Date: January 6, 2009 Contractor: Csi Electrical Contractors Inc Applicant: Stephanie Goad | Permit status: Finaled | Completion date: May 26, 2009 | Expiration date: July 5, 2009 | Permit id: 812220009 | |||||
Install additional convenience outlets Date: February 5, 2009 Applicant: Same As Owner | Permit status: Finaled | Completion date: June 10, 2009 | Expiration date: August 4, 2009 | Permit id: 902050003 | |||||
SCORE 82 Electrical work, installation of elevator Date: May 27, 2009 Contractor: Juno Electrical System Inc Applicant: Chang Joon | Permit status: Finaled | Completion date: May 29, 2009 | Expiration date: November 23, 2009 | Permit id: 905270046 | |||||
SCORE 98 Temp power poles for inspectors trailer Date: March 22, 2010 Contractor: S And S Rentafence Engineer: Craig Williamson | Applicant: Eric Jacoby Gilbert | Permit status: Finaled | Completion date: March 31, 2010 | Expiration date: March 22, 2011 | Permit id: 1003220001 | |||||
SCORE 95 Electrical for 1 new 4x6 sign. Date: April 22, 2010 Contractor: Mackone Development Inc Applicant: Dugan Matt | Permit status: Finaled | Completion date: August 18, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220016 | |||||
SCORE 95 Electrical for new 8x6 sign. Date: April 22, 2010 Contractor: Mackone Development Inc Applicant: Dugan Matt | Permit status: Finaled | Completion date: August 18, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220018 | |||||
SCORE 99 El for solar pv on new freestanding parking structure Date: December 28, 2010 Contractor: Hensel Phelps Construction Engineer: Craig Williamson | Applicant: Duran, Nick | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: December 28, 2011 | Permit id: 1010250001 | |||||
SCORE 95 One 20amp circuit @ temporary loading dock Date: June 7, 2011 Contractor: Mackone Development Inc Engineer: Me Engineers | Applicant: Dugan Matt | Permit status: Finaled | Completion date: July 11, 2011 | Expiration date: June 6, 2012 | Permit id: 1106070011 | |||||
Electrical for washer/disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070026 | |||||
SCORE 98 Relocation of south portion of central dr. East hosp. Campus Date: May 11, 2010 Contractor: Hensel Phelps Construction Co Applicant: Fred Cravea | Permit status: Finaled | Completion date: December 15, 2010 | Expiration date: May 11, 2011 | Permit id: 912170001 | |||||
SCORE 98 New freestanding parking structure-155,4 s. F. Date: May 10, 2010 Contractor: Hensel Phelps Construction Co Engineer: Craig Williamson | Applicant: Ruvalcaba Gilbert | Permit status: Finaled | Completion date: July 19, 2010 | Expiration date: May 10, 2011 | Permit id: 1002030001 | |||||
SCORE 98 Rough & finish grading work, asphalt & concrete paving for parking & pedestrian walkways. Date: November 17, 2010 Contractor: Hensel Phelps Construction Co Applicant: Duran Nicolas | Permit status: Finaled | Completion date: January 16, 2014 | Expiration date: November 17, 2011 | Permit id: 1007060003 | |||||
SCORE 61 Landscaping for new freestanding parking structure on harbo ucla medical center campus Date: April 20, 2011 Contractor: Pierre Sprinkler And Landscape Engineer: Environmental Patterns | Applicant: Patricia Golden | Permit status: Finaled | Completion date: February 2, 2012 | Expiration date: April 19, 2012 | Permit id: 1104200002 | |||||
SCORE 56 Mechanical p. C. Date: January 28, 2009 Contractor: Cbcs Inc Applicant: Henry Hirsch | Permit status: Finaled | Completion date: September 28, 2009 | Expiration date: July 27, 2009 | Permit id: 901270007 | |||||
SCORE 61 Mechanical items for mri replacement projects. Date: April 23, 2009 Contractor: So Cal Mechanical Applicant: Patricia Moyer | Permit status: Finaled | Completion date: May 26, 2009 | Expiration date: October 20, 2009 | Permit id: 904210019 | |||||
SCORE 99 Me for new freestanding parking structure-155,4 s. F. Date: July 26, 2010 Contractor: Hensel Phelps Construction Engineer: Craig Williamson | Applicant: Thiele, Scott | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: July 26, 2011 | Permit id: 1007260022 | |||||
Mechanical for washer/disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070013 | |||||
SCORE 77 Non-structual tenant improvements(plumbing Date: February 11, 2009 Contractor: Hock Construction Co Applicant: Trish Moyer | Permit status: Finaled | Completion date: May 26, 2009 | Expiration date: August 10, 2009 | Permit id: 902110017 | |||||
SCORE 70 Plumbing for new modular building,addition to existing. Date: March 25, 2010 Contractor: Crp Plumbing Inc Applicant: Chuck Pine | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: March 25, 2011 | Permit id: 1003250019 | |||||
SCORE 99 Pl for new freestanding parking structure-155,4 s. F. Date: July 26, 2010 Contractor: Hensel Phelps Construction Engineer: Craig Williamson | Applicant: Thiele, Scott | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: July 26, 2011 | Permit id: 1007260030 | |||||
Plumbing for washer/disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070009 | |||||
SCORE 99 Cap (5) existing sewer lines proposed surgery-emergency replacement project parking lot grading work. Date: May 3, 2012 Contractor: Hensel Phelps Construction Engineer: James Kawamura, Khr Associates | Applicant: Eric Gribble | Permit status: Finaled | Completion date: January 16, 2014 | Expiration date: May 3, 2013 | Permit id: 1205010008 | |||||
SCORE 99 Foundation & pole only for the sign Engineer: Julio Ribeiro | Applicant: Cohen Barb | Permit status: Permisud | Expiration date: September 26, 2012 | Permit id: 1109140014 | |||||
SCORE 99 Construction of on-site domestic water system Date: December 12, 2011 Contractor: Architectural Design And Signs Inc Engineer: Julio Ribeiro | Applicant: Valverde Michael | Permit status: Finaled | Completion date: February 20, 2013 | Expiration date: December 11, 2012 | Permit id: 1112120016 | |||||
SCORE 100 Relocate modular trailers Applicant: Matt Dugan | Permit status: Finaled | Completion date: March 31, 2009 | Expiration date: April 18, 2009 | Permit id: 804100046 | |||||
SCORE 100 Add new 2 s. F. Metal canopy over existing trash enclosure. Applicant: Giordano Marco | Permit status: Finaled | Completion date: September 10, 2010 | Expiration date: April 22, 2011 | Permit id: 1003080080 | |||||
SCORE 100 Add 1 new sign 8x 6. Applicant: Dugan Matt | Permit status: Finaled | Completion date: June 4, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220028 | |||||
SCORE 100 Add 1 new sign 4x 6. Applicant: Dugan Matt | Permit status: Finaled | Completion date: June 1, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220029 | |||||
Washer disinfector relocation to warehouse Date: September 7, 2011 Value: $45,000 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1106290077 | |||||
SCORE 95 Foundation & pole only for the sign Engineer: Julio Ribeiro | Applicant: Cohen Barb | Permit status: Permisud | Expiration date: September 26, 2012 | Permit id: 1109140014 | |||||
SCORE 100 Relocate modular trailers Date: October 20, 2008 Contractor: Mackone Development, Inc Applicant: Matt Dugan | Permit status: Finaled | Completion date: April 1, 2009 | Expiration date: April 18, 2009 | Permit id: 809040014 | |||||
SCORE 99 Non-structural tenant improvement Date: January 6, 2009 Contractor: Csi Electrical Contractors, Inc Applicant: Stephanie Goad | Permit status: Finaled | Completion date: May 26, 2009 | Expiration date: July 5, 2009 | Permit id: 812220009 | |||||
SCORE 59 Electrical work, installation of elevator Date: May 27, 2009 Contractor: Juno Electrical System Inc * Applicant: Chang Joon | Permit status: Finaled | Completion date: May 29, 2009 | Expiration date: November 23, 2009 | Permit id: 905270046 | |||||
SCORE 98 Temp power poles for inspectors trailer Date: March 22, 2010 Contractor: S And S Rentafence Engineer: Craig Williamson | Applicant: Eric Jacoby Gilbert | Permit status: Finaled | Completion date: March 31, 2010 | Expiration date: March 22, 2011 | Permit id: 1003220001 | |||||
SCORE 100 Electrical for 1 new 4x6 sign. Date: April 22, 2010 Contractor: Mackone Development, Inc Applicant: Dugan Matt | Permit status: Finaled | Completion date: August 18, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220016 | |||||
SCORE 100 Electrical for new 8x6 sign. Date: April 22, 2010 Contractor: Mackone Development, Inc Applicant: Dugan Matt | Permit status: Finaled | Completion date: August 18, 2010 | Expiration date: April 22, 2011 | Permit id: 1004220018 | |||||
SCORE 100 One 20amp circuit @ temporary loading dock Date: June 7, 2011 Contractor: Mackone Development, Inc Engineer: Me Engineers | Applicant: Dugan Matt | Permit status: Finaled | Completion date: July 11, 2011 | Expiration date: June 6, 2012 | Permit id: 1106070011 | |||||
Electrical for washer disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070026 | |||||
SCORE 56 Mechanical p. C. Date: January 28, 2009 Contractor: Cbcs, Inc Applicant: Henry Hirsch | Permit status: Finaled | Completion date: September 28, 2009 | Expiration date: July 27, 2009 | Permit id: 901270007 | |||||
Mechanical for washer disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070013 | |||||
SCORE 65 Plumbing for new modular building,addition to existing. Date: March 25, 2010 Contractor: Crp Plumbing, Inc Applicant: Chuck Pine | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: March 25, 2011 | Permit id: 1003250019 | |||||
Plumbing for washer disinfector relocation to warehouse Date: September 7, 2011 Engineer: Julio Ribeiro | Applicant: Same As Owner | Permit status: Permisud | Expiration date: September 6, 2012 | Permit id: 1109070009 | |||||
SCORE 95 Construction of on-site domestic water system Date: December 12, 2011 Contractor: Architectural Design And Signs, Inc Engineer: Julio Ribeiro | Applicant: Valverde Michael | Permit status: Finaled | Completion date: February 20, 2013 | Expiration date: December 11, 2012 | Permit id: 1112120016 | |||||
SCORE 59 Electrical work, installation of elevator Date: May 27, 2009 Contractor: Juno Electrical System Inc * Applicant: Chang Joon | Permit status: Finaled | Completion date: May 29, 2009 | Expiration date: November 23, 2009 | Permit id: 905270046 | |||||
SCORE 99 New storage building w/roof top helistop Engineer: Kmd Architecture | Applicant: Brehm Stuart | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 3, 2013 | Permit id: 1110310027 | |||||
SCORE 99 Replace 2 existing non-compliant ingress/egress stairs at existing buildings due to grading work for hospital addition Engineer: Kmd Architecture | Applicant: Cravea Fred | Permit status: Finaled | Completion date: May 12, 2013 | Expiration date: January 23, 2014 | Permit id: 1211150075 | |||||
Electrical work, installation of elevator Date: May 27, 2009 Applicant: Chang Joon | Permit status: Finaled | Completion date: May 29, 2009 | Expiration date: November 23, 2009 | Permit id: 905270046 | |||||
SCORE 99 El for new freestanding parking structure-155,4 s. F. Engineer: Craig Williamson | Applicant: Thiele, Scott | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: July 26, 2011 | Permit id: 1002030001 | |||||
SCORE 68 Electrical for new modular bldg 400a 120/208v from (e) campus. Date: August 5, 2010 Contractor: Whelan Electric Co Applicant: Lee Patrick Whelan | Permit status: Finaled | Completion date: February 4, 2011 | Expiration date: August 5, 2011 | Permit id: 1008050019 | |||||
SCORE 99 El for new storage building w/roof top helistop Date: May 7, 2012 Contractor: Hensel Phelps Construction Engineer: Kmd Architecture | Applicant: Brehm Stuart | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 7, 2013 | Permit id: 1205070060 | |||||
SCORE 99 Me for new storage building w/roof top helistop Date: May 7, 2012 Contractor: Hensel Phelps Construction Engineer: Kmd Architecture | Applicant: Brehm Stuart | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 7, 2013 | Permit id: 1205070022 | |||||
SCORE 98 Rerouting domestic/fireline,not include fire hydrants or connections to hospital Date: January 21, 2010 Contractor: Hensel Phelps Construction Co Applicant: Nicholas Duran | Permit status: Finaled | Completion date: April 5, 2010 | Expiration date: January 21, 2011 | Permit id: 912170007 | |||||
SCORE 99 Pl for new storage building w/roof top helistop Date: May 7, 2012 Contractor: Hensel Phelps Construction Engineer: Kmd Architecture | Applicant: Brehm Stuart | Permit status: Finaled | Completion date: April 7, 2014 | Expiration date: May 7, 2013 | Permit id: 1205070034 |