Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Suppression permit Date: April 28, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 196098 | |||||
Suppression permit Date: April 19, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 685489 | |||||
Electrical permit Date: June 6, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 689085 | |||||
Alteration permit Date: August 19, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 279124 | |||||
Mechanical permit Date: October 24, 2014 Client: Episcopal Hospital | Permit status: Expired | Permit id: 564596 | |||||
Alteration permit Date: December 8, 2014 Client: Episcopal Hospital | Permit status: Expired | Permit id: 551910 | |||||
Suppression permit Date: November 9, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 305999 | |||||
Zoning/use permit Date: August 3, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 293701 | |||||
Electrical permit Date: October 7, 2014 Client: Episcopal Hospital | Permit status: Expired | Permit id: 561933 | |||||
Alteration permit Date: August 10, 2007 Client: Episcopal Hospital | Permit status: Completed | Permit id: 57066 | |||||
Electrical permit Date: December 3, 2010 Client: Episcopal Hospital | Permit status: Expired | Permit id: 310226 | |||||
Mechanical permit Date: December 22, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 253873 | |||||
Mechanical permit Date: October 17, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 432006 | |||||
Demolition permit Date: November 25, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 131765 | |||||
Alteration permit Date: October 4, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 427368 | |||||
Plumbing permit Date: November 4, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 310034 | |||||
Plumbing permit Date: September 3, 2014 Client: Episcopal Hospital | Permit status: Completed | Permit id: 558935 | |||||
Plumbing permit Date: September 21, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 428354 | |||||
Operations permit Date: August 26, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 12060 | |||||
Zoning permit Date: October 9, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 179662 | |||||
Demolition permit Date: March 21, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 677996 | |||||
Alteration permit Date: August 14, 2013 Client: Episcopal Hospital | Permit status: Completed | Permit id: 486552 | |||||
Use permit Date: April 3, 2013 Client: Episcopal Hospital | Permit status: Completed | Permit id: 462984 | |||||
Operations permit Date: September 14, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 20674 | |||||
Electrical permit Date: December 22, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 183143 | |||||
Alteration permit Date: April 11, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 677983 | |||||
Plumbing permit Date: June 10, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 698822 | |||||
Alteration permit Date: April 15, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 208993 | |||||
Electrical permit Date: January 21, 2011 Client: Episcopal Hospital | Permit status: Expired | Permit id: 317117 | |||||
Electrical permit Date: October 22, 2007 Client: Episcopal Hospital | Permit status: Completed | Permit id: 104592 | |||||
Alteration permit Date: August 14, 2015 Client: Episcopal Hospital | Permit status: Completed | Permit id: 626482 | |||||
Suppression permit Date: November 15, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 438165 | |||||
Suppression permit Date: October 10, 2014 Client: Episcopal Hospital | Permit status: Completed | Permit id: 567495 | |||||
Electrical permit Date: October 26, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 432551 | |||||
Operations permit Date: September 14, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 20674 | |||||
Use permit Date: April 3, 2013 Client: Episcopal Hospital | Permit status: Completed | Permit id: 462984 | |||||
Plumbing permit Date: June 10, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 698822 | |||||
Plumbing permit Date: September 3, 2014 Client: Episcopal Hospital | Permit status: Completed | Permit id: 558935 | |||||
Alteration permit Date: April 15, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 208993 | |||||
Alteration permit Date: December 8, 2014 Client: Episcopal Hospital | Permit status: Expired | Permit id: 551910 | |||||
Electrical permit Date: November 14, 2014 Client: Episcopal Hospital | Permit status: Completed | Permit id: 566516 | |||||
Electrical permit Date: December 22, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 183143 | |||||
Mechanical permit Date: May 6, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 199703 | |||||
Electrical permit Date: December 3, 2010 Client: Episcopal Hospital | Permit status: Expired | Permit id: 310226 | |||||
Plumbing permit Date: October 24, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 434591 | |||||
Suppression permit Date: November 15, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 438165 | |||||
Suppression permit Date: April 28, 2009 Client: Episcopal Hospital | Permit status: Completed | Permit id: 196098 | |||||
Suppression permit Date: November 9, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 305999 | |||||
Electrical permit Date: October 26, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 432551 | |||||
Electrical permit Date: February 19, 2016 Client: Episcopal Hospital | Permit status: Expired | Permit id: 662667 | |||||
Zoning use permit Date: August 3, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 293701 | |||||
Suppression permit Date: April 19, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 685489 | |||||
Alteration permit Date: August 19, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 279124 | |||||
Plumbing permit Date: November 4, 2010 Client: Episcopal Hospital | Permit status: Completed | Permit id: 310034 | |||||
Alteration permit Date: April 11, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 677983 | |||||
Alteration permit Date: August 14, 2013 Client: Episcopal Hospital | Permit status: Completed | Permit id: 486552 | |||||
Suppression permit Date: October 10, 2014 Client: Episcopal Hospital | Permit status: Completed | Permit id: 567495 | |||||
Mechanical permit Date: October 17, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 432006 | |||||
Alteration permit Date: August 10, 2007 Client: Episcopal Hospital | Permit status: Completed | Permit id: 57066 | |||||
Demolition permit Date: March 21, 2016 Client: Episcopal Hospital | Permit status: Completed | Permit id: 677996 | |||||
Alteration permit Date: October 4, 2012 Client: Episcopal Hospital | Permit status: Completed | Permit id: 427368 | |||||
Operations permit Date: August 26, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 12060 | |||||
Zoning permit Date: October 9, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 179662 | |||||
Electrical permit Date: January 21, 2011 Client: Episcopal Hospital | Permit status: Expired | Permit id: 317117 | |||||
Alteration permit Date: August 14, 2015 Client: Episcopal Hospital | Permit status: Completed | Permit id: 626482 | |||||
Demolition permit Date: November 25, 2008 Client: Episcopal Hospital | Permit status: Completed | Permit id: 131765 | |||||
Mechanical permit Date: October 24, 2014 Client: Episcopal Hospital | Permit status: Expired | Permit id: 564596 | |||||
Electrical permit Date: October 22, 2007 Client: Episcopal Hospital | Permit status: Completed | Permit id: 104592 | |||||
SCORE 96 For level ii alterations to an existing office area on the sixth floor level, alterations to include erection of partition walls, provide finishes, furnishings, and provide accessiblity improvements. All work to be done per approved plans. If field conditions vary contact design professional prior to the start of any work. Separate permits required for mechanical, electrical, plumbing and fire suppression work. Date: April 11, 2016 Contractor: Massa Construction Corp Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: June 30, 2016 | Permit id: 677983 | |||||
SCORE 100 Add 2 flow alarm and 2 tamper switches to new wet standpipe and connect to existin simples system as per 2008 nec (east district) Date: January 21, 2011 Contractor: William Lex Jr Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Expired | Completion date: January 21, 2011 | Permit id: 317117 | |||||
SCORE 100 2 fixtures with piping for temp trailer Date: November 4, 2010 Contractor: John J Mulholland Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 20, 2015 | Permit id: 310034 | |||||
SCORE 100 Disconnect existing trailer feed,reconnect existing feed to new trailer disconnect existing fire alarm,as per nfpa-72, reinstall in new trailer as per 2008 nec(e district) Date: December 3, 2010 Contractor: William Lex Jr Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Expired | Completion date: December 3, 2010 | Permit id: 310226 | |||||
SCORE 100 Ez permit ductwork & warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: March 7, 2017 Contractor: Lormar Mechanical Services Client: Episcopal Hospital | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 764621 | |||||
SCORE 100 Relocate (32) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. No changes to exterior. No work alterations to windows or doors. Date: March 7, 2017 Contractor: A And S Sprinkler Co Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 764891 | |||||
SCORE 100 Install new wc, lav and supply and install new waste and water lines. Remove 2 sinks(hospital) Date: October 24, 2012 Contractor: John J Mulholland Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 23, 2015 | Permit id: 434591 | |||||
SCORE 100 Relocating 7 sprinklers on the 3rd floor in the crisis response center of potter morris Date: November 15, 2012 Contractor: Oliver Sprinkler Co Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 438165 | |||||
Retail sales foor beverages and groceries Date: April 3, 2013 Client: Episcopal Hospital | Permit type: Use permit | Permit status: Completed | Completion date: April 3, 2013 | Permit id: 462984 | |||||
Pre code use - no change in use and occupancy classification. Interior demolition of partition walls as per engineers letter and per approved plans. Date: August 14, 2013 Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: November 23, 2014 | Permit id: 486552 | |||||
SCORE 96 For interior alterations to the potter morris bldg, 1st floor (emergency) to include the demolition and erection of non-bearing partitions. Separate permits required for plumbing, electrical, mechanical and fire suppression. Date: December 8, 2014 Contractor: Massa Construction Corp Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Expired | Completion date: April 30, 2015 | Permit id: 551910 | |||||
SCORE 100 8 27 08 - tent erected on site Date: August 26, 2008 Contractor: Select Event Rentals Client: Episcopal Hospital | Permit type: Operations permit | Permit status: Completed | Permit id: 12060 | |||||
Partial demolition: remove two buildings on hospital site - aspinwal bldg. And harrison housebldg. Other buildings to remain per plans. Date: November 25, 2008 Client: Episcopal Hospital | Permit type: Demolition permit | Permit status: Completed | Completion date: October 28, 2009 | Permit id: 131765 | |||||
Partial demolition of two (2) structures aspinwal building and harrison house with all other structures to remain as part of an existing hospital complex with all other uses previously approved (size and location as shown in the application). Date: October 9, 2008 Client: Episcopal Hospital | Permit type: Zoning permit | Permit status: Completed | Completion date: October 9, 2008 | Permit id: 179662 | |||||
SCORE 100 Replace existing 480v disconnects with locking type extend power to new controllers, install locking disconnect on cab lights replace lights in penthouse machine room, existing fire alarm controls to be connected to new controllers by elevator installer as per 2005 ne (east district) Date: December 22, 2008 Contractor: William Lex Jr Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 183143 | |||||
SCORE 96 For the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans Date: February 2, 2017 Contractor: Massa Construction Corp Client: Episcopal Hospital | Permit type: Demolition permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 755802 | |||||
SCORE 100 Install water closet, lavatory, sink.. Extend from existing sanitary, vent and domestic water Date: June 10, 2016 Contractor: Lormar Mechanical Services Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 30, 2016 | Permit id: 698822 | |||||
SCORE 99 Relocate and relamp existing lighting, rework lighting circuits for new floor plan, provide 8 receptacles tied into existing circuits as per nec 2008 & relocate existing fire alarm devices, provide 1 new fa strobe, provide 1 new fa speaker strobe as per nfpa 72 Date: June 6, 2016 Contractor: Lex William Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: June 30, 2016 | Permit id: 689085 | |||||
SCORE 100 Install exposure protection on outside face of hospital Date: April 28, 2009 Contractor: Fire Protection Industries Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: June 19, 2009 | Permit id: 196098 | |||||
SCORE 94 Installation of exhaust hood, fan, make up air unit and ductwork Date: May 6, 2009 Contractor: Epay Inc Client: Episcopal Hospital | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 9, 2009 | Permit id: 199703 | |||||
Repoint building. Rebuild parapet walls, remove dated vents from walls. Recaulk windows, roofing, and patio decks. Date: April 15, 2009 Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: December 10, 2009 | Permit id: 208993 | |||||
SCORE 100 8 24 10-erection of (2)- assembly use tents attached to form (1)-tent Date: September 14, 2010 Contractor: Select Event Rentals Client: Episcopal Hospital | Permit type: Operations permit | Permit status: Completed | Permit id: 20674 | |||||
SCORE 100 Install 15 kv conduit and wire to replace existing 2400v system phase 1 no gear at this time only conduit and wire to distribution, future as per 2005 nec (east district) Date: October 22, 2007 Contractor: William Lex Jr Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: December 16, 2009 | Permit id: 104592 | |||||
SCORE 94 Kitchen ansul system. See a p #199703 for kitchen hood permit. Date: October 26, 2009 Contractor: Epay Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: November 9, 2009 | Permit id: 234798 | |||||
SCORE 100 Install two (2) new mechanical air handl units, with associated piping, as per approved plans Date: December 22, 2009 Contractor: Ramm Inc Client: Episcopal Hospital | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 253873 | |||||
SCORE 56 Pre code use - no change in use and occupancy classification. Interior alterations to the bathrooms located on the 1st and 2nd floor as per approved plans. Separate permit required for mechanical and plumbing work. Date: August 14, 2015 Contractor: Daniel Hoban T A Jd Home Llc Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: March 21, 2016 | Permit id: 626482 | |||||
SCORE 100 Install 3-low voltage cameras as per nec 2008 east district Date: February 19, 2016 Contractor: Vector Security Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Expired | Completion date: February 19, 2016 | Permit id: 662667 | |||||
Widen door opening from 4 to 10 Date: August 10, 2007 Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: May 12, 2008 | Permit id: 57066 | |||||
SCORE 96 Interior demo ez interior demolition- for the interior demolition of non load-bearing partition walls and ceilings as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: March 21, 2016 Contractor: Massa Construction Corp Client: Episcopal Hospital | Permit type: Demolition permit | Permit status: Completed | Completion date: June 30, 2016 | Permit id: 677996 | |||||
SCORE 100 Alterations: interior plumbing; medical office -the installation shall comply with the philadelphia plumbing code, 2004 Date: March 30, 2017 Contractor: Lormar Mechanical Services Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 768167 | |||||
SCORE 100 Relocate (11) existing sprinkler heads in order to accommodate tenant layouts as per nfpa no. 13 and all local codes. No changes to exterior. Date: April 19, 2016 Contractor: A And S Sprinkler Co Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: June 30, 2016 | Permit id: 685489 | |||||
SCORE 100 Relocation of 13 sprinlker heads Date: October 10, 2014 Contractor: Independence Fire Sprinkler Co Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: July 30, 2015 | Permit id: 567495 | |||||
SCORE 100 Alterations to existing hvac system to include reconnecting existing steam supply and return lines, replacing existing 5hp motor with 5 hp. Vfd rated motor, reconnecting existing condenste drain line and replacing existing ductwork, ahus and grds as per approved plans. Date: October 24, 2014 Contractor: Elliott Lewis Corporation Client: Episcopal Hospital | Permit type: Mechanical permit | Permit status: Expired | Completion date: March 25, 2016 | Permit id: 564596 | |||||
SCORE 100 For interior alterations as per plans - additional permits required for electrical, mechanical, plumbing and fire suppression Date: October 4, 2012 Contractor: Commercial Construction Inc Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: March 6, 2013 | Permit id: 427368 | |||||
SCORE 100 Run 3" sanitary line from main and rough in 4" from main for toilet. Run 1-1 2" sanitary from main to lav, run hot and cold water from existing to feed two fixtures Date: September 21, 2012 Contractor: Nagellavin Inc Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 25, 2014 | Permit id: 428354 | |||||
SCORE 100 Hvac, including ductwork, for crisis respond center - registers diffusers Date: October 17, 2012 Contractor: Ramm Inc Client: Episcopal Hospital | Permit type: Mechanical permit | Permit status: Completed | Completion date: June 9, 2014 | Permit id: 432006 | |||||
SCORE 99 Renovation and fit out for wound care medical facility on 1st fl of building. Remove existing lighting for re-use. Hvac circuits,reconfigure existing circuits for power,light and install fa devices on existing system per 2008 nec (health care facility) Date: November 14, 2014 Contractor: Lex William Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: January 21, 2015 | Permit id: 566516 | |||||
SCORE 100 Tower building 1st floor - woundcare & hyperbaric suite plumbing alterations - (3)water closets, (2)lavatories, (1)mop receptor, (7)sinks & (1)floor drain - note: medical gases not included in permit Date: October 20, 2014 Contractor: Elliott Lewis Corporation Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 2, 2015 | Permit id: 564329 | |||||
SCORE 99 Relocate exist lighting, add 4-duplex recepts, 1-double duplex, 2-gfci, relocate, exist nurse call devices, relocate telemeter system server & all ckts connecting to exist pnl as per nec 2008 (health care facility) Date: October 7, 2014 Contractor: Lex William Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Expired | Completion date: October 7, 2014 | Permit id: 561933 | |||||
SCORE 100 Installation of a sink, relocate cilnical sink and hand sink Date: September 3, 2014 Contractor: Lormar Mechanical Services Client: Episcopal Hospital | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 1, 2015 | Permit id: 558935 | |||||
SCORE 99 Replacement of 3 exisitng generators, 1-200kw facilities building, 2-500kw potter morris and centennial in generator building as per 2008 nec (east district) Date: September 26, 2014 Contractor: Lex William Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Expired | Completion date: September 26, 2014 | Permit id: 552855 | |||||
SCORE 100 Level ii interior alterations to create hyperbaric chamber room with associated offices on the first floor of an existing hospital building as per approved plans and pa doh approval. No exterior work. Separate permits required for mep & fire suppression work Date: September 15, 2014 Contractor: Target Building Construction Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: November 25, 2014 | Permit id: 558946 | |||||
Legalize double wide office trailer. Date: August 3, 2010 Client: Episcopal Hospital | Permit type: Zoning/use permit | Permit status: Completed | Completion date: August 3, 2010 | Permit id: 293701 | |||||
SCORE 100 Install new standpipe at east tower for hospital per submitted sealed plans. Date: November 19, 2010 Contractor: Oliver Sprinkler Co Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: February 15, 2011 | Permit id: 301145 | |||||
SCORE 99 Relocate and add to existing lighting, rework switch circuits in area, setlet demo of exissting power add duplex receptacles. All power connected to existing panels area as per nec 2008 east district Date: April 7, 2017 Contractor: Lex William Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 766169 | |||||
SCORE 96 For level ii interior alterations to an existing medical office as per approved plans. Work to include interior non-bearing partitions, millwork, finishes, new doors & assemblies, and ceiling repairs. Separate permits required for mechanical, electrical, plumbing, and fire suppression systems. All asbestos to be treated & removed prior to commencement of work. Date: February 23, 2017 Contractor: Massa Construction Corp Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: June 6, 2017 | Permit id: 756235 | |||||
SCORE 100 Installation of dry sprinkler system in adjacent office trailer, connect to existing system. Date: November 9, 2010 Contractor: Fire Protection Industries Inc Client: Episcopal Hospital | Permit type: Suppression permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 305999 | |||||
SCORE 100 Relocate existing lighting-install switching & power outlets, install fire alarm devices, utilize existing electrical services as is(100amp), no tele data as per 2008 nec & nfpa 72 (hospital) Date: October 26, 2012 Contractor: Mcgoldrick Electric Inc Client: Episcopal Hospital | Permit type: Electrical permit | Permit status: Completed | Completion date: March 11, 2013 | Permit id: 432551 | |||||
Removal of trailer and installation of new trailer. Date: August 19, 2010 Client: Episcopal Hospital | Permit type: Alteration permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 279124 |