SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: June 24, 2016 Contractor: Pepco Electric Power Co Permit type: Excavation; electric ml conduit (trench), excavation; manhole installation | Permit status: Issued | Expiration date: September 15, 2016 | Permit id: Pa179695 | |||||
SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: June 24, 2016 Contractor: Pepco Electric Power Co Permit type: Excavation; electric ml conduit (trench), excavation; manhole installation | Permit status: Permit expired | Expiration date: September 15, 2016 | Permit id: Pa179695 | |||||
SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: August 25, 2016 Contractor: Pepco Electric Power Co Permit type: Excavation; electric ml conduit (trench), excavation; manhole installation | Permit status: Permit expired | Expiration date: November 14, 2016 | Permit id: Pa179695-R1 | |||||
SCORE 88 Marathon Date: March 14, 2012 Contractor: Brian Ulery Permit status: Expired | Expiration date: March 17, 2012 | Permit id: Pa10052438 | |||||
SCORE 95 Construction staging area Date: October 25, 2013 Contractor: Pepco Holdings Inc Permit status: Expired | Expiration date: November 8, 2013 | Permit id: Pa10118718 | |||||
SCORE 95 Construction staging area Contractor: Pepco Holdings Inc Permit status: Rejected | Expiration date: November 13, 2013 | Permit id: 0 | |||||
SCORE 95 Construction staging area Date: November 13, 2013 Contractor: Pepco Holdings Inc Permit status: Expired | Expiration date: November 22, 2013 | Permit id: Pa10120458 | |||||
SCORE 89 Excavation; electric ml conduit (trench), excavation; manhole installation Date: July 22, 2016 Contractor: Pepco Electric Power Co Permit status: 8 | Expiration date: September 15, 2016 | Permit id: Pa179695 | |||||
SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: February 22, 2017 Contractor: Pepco Electric Power Co Permit type: Excavation; electric ml conduit (trench), excavation; manhole installation | Permit status: Permit expired | Expiration date: May 13, 2017 | Permit id: Pa179695-R4 | |||||
SCORE 96 Construction staging area Date: February 19, 2016 Contractor: Potomac Electric Power Company Permit status: Expired | Expiration date: March 25, 2016 | Permit id: Pa10230245 | |||||
SCORE 96 Construction staging area Date: July 26, 2016 Contractor: Potomac Electric Power Company Permit status: Expired | Expiration date: August 17, 2016 | Permit id: Pa10314624 | |||||
SCORE 96 Construction staging area Date: July 1, 2016 Contractor: Potomac Electric Power Company Permit status: Expired | Expiration date: August 14, 2016 | Permit id: Pa10312393 | |||||
SCORE 96 Construction staging area Date: July 18, 2016 Contractor: Potomac Electric Power Company Permit status: Expired | Expiration date: August 21, 2016 | Permit id: Pa10314114 | |||||
SCORE 93 Steel plate- single location Date: August 24, 2016 Contractor: Matt Fry Cw And Sons Infrastructure, Inc Permit status: Expired | Expiration date: September 12, 2016 | Permit id: Pa10333162 | |||||
SCORE 96 Construction staging area Contractor: Potomac Electric Power Company Permit status: Resubmit | Expiration date: January 28, 2017 | Permit id: 0 | |||||
SCORE 93 Steel plate- single location Date: January 27, 2017 Contractor: Matt Fry Cw And Sons Infrastructure, Inc Permit status: Expired | Expiration date: January 31, 2017 | Permit id: Pa10374401 | |||||
SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: December 21, 2016 Contractor: Pepco Electric Power Co Permit status: Issued | Expiration date: March 14, 2017 | Permit id: Pa179695-R3 | |||||
SCORE 95 Construction staging area Contractor: Pepco Holdings Inc Permit status: Rejected | Expiration date: November 13, 2013 | Permit id: 0 | |||||
SCORE 96 Construction staging area Date: August 24, 2016 Contractor: Potomac Electric Power Company Permit status: Permit expired | Expiration date: September 27, 2016 | Permit id: Pa10330765 | |||||
SCORE 96 Construction staging area Contractor: Potomac Electric Power Company Permit status: Resubmit | Expiration date: January 28, 2017 | Permit id: 0 | |||||
SCORE 96 Construction staging area Date: March 2, 2017 Contractor: Potomac Electric Power Company Permit status: Permit expired | Expiration date: March 28, 2017 | Permit id: Pa10377657 | |||||
SCORE 89 Pepco is installing two 2 kv pipe-type along half street sw, potomac avenue and r street sw. Date: March 2, 2017 Contractor: Pepco Electric Power Co Permit status: Permit expired | Expiration date: May 13, 2017 | Permit id: Pa179695-R4 | |||||
SCORE 95 Construction staging area Contractor: Pepco Holdings Inc Permit status: Rejected | Expiration date: November 13, 2013 | Permit id: 0 | |||||
SCORE 96 Construction staging area Contractor: Potomac Electric Power Company Permit status: Resubmit | Expiration date: January 28, 2017 | Permit id: 0 | |||||
SCORE 96 Construction staging area Date: August 8, 2017 Contractor: Potomac Electric Power Company Permit status: Expired | Expiration date: August 24, 2017 | Permit id: Pa10453624 | |||||
SCORE 96 Construction staging area Contractor: Coakley Williams Construction Inc Permit status: Approved | Expiration date: October 7, 2017 | Permit id: 0 | |||||
SCORE 95 Construction staging area Date: October 1, 2013 Contractor: Pepco Holdings Inc Permit status: Permit expired | Expiration date: November 1, 2013 | Permit id: Pa10115268 | |||||
SCORE 95 Construction staging area Contractor: Pepco Holdings Inc Permit status: Rejected | Expiration date: November 13, 2013 | Permit id: 0 | |||||
SCORE 77 Manhole access 11 days Date: December 16, 2016 Contractor: Turner Construction Construction Company Permit status: Permit expired | Expiration date: December 23, 2016 | Permit id: Pa10357549 | |||||
SCORE 96 Construction staging area Contractor: Potomac Electric Power Company Permit status: Resubmit | Expiration date: January 28, 2017 | Permit id: 0 | |||||
SCORE 96 Construction staging area Date: July 18, 2017 Contractor: Potomac Electric Power Company Permit status: Permit expired | Expiration date: July 23, 2017 | Permit id: Pa10429435 | |||||
SCORE 96 Construction staging area Date: August 22, 2017 Contractor: Coakley Williams Construction Inc Permit status: Permit expired | Expiration date: September 21, 2017 | Permit id: Pa10453060 | |||||
SCORE 96 Construction staging area Contractor: Coakley Williams Construction Inc Permit status: Approved (pending payment | Expiration date: October 7, 2017 | Permit id: 0 | |||||
SCORE 95 Construction staging area Date: May 23, 2017 Contractor: Pepco Holdings Inc Permit status: Permit expired | Expiration date: June 20, 2017 | Permit id: Pa10398361 |